up_reraStatus: Completed
CASE ID: 0901126071452022

Appellant / Complainant

Mukesh Kumar

VS

Respondent

Paarth Infrabuild Private Limited

Developer Firm

paarth infrabuild private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Sale Deed & Title TransferNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

41 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126071452022 by Mukesh Kumar against Paarth Infrabuild Private Limited before up_rera.

Sale Deed & Title TransferNon-Compliance & Execution
2
Stage 128/01/2026

Hearing

The appeal was dismissed as withdrawn after the parties reported an amicable settlement, noting that the conveyance deed was executed and the appellant has taken physical possession of the unit.

3
Stage 218/12/2025

Hearing

The Tribunal granted the respondent time to complete flat work and pay delay interest, and adjourned the appeal to 28.01.2026.

4
Stage 302/12/2025

Hearing

The Tribunal adjourned the proceedings due to the absence of both parties and rescheduled the hearing for December 18, 2025.

5
Stage 417/11/2025

Hearing

The Tribunal noted that the respondent has executed the conveyance deed, delivered possession to the appellant on 07.03.2025, and uploaded a settlement deed dated 05.10.2025; the matter is listed for 02.12.2025.

6
Stage 527/10/2025

Hearing

The Tribunal noted the absence of both parties and adjourned the appeal to 17.11.2025 in the interest of justice.

7
Stage 622/09/2025

Hearing

No text available.

8
Stage 703/09/2025

Hearing

At the request of the learned counsel for both parties, the appeal has been listed for orders on 22.09.2025.

9
Stage 818/08/2025

Hearing

The Tribunal has granted a request to list the appeal for orders or hearing on September 3, 2025.

10
Stage 922/07/2025

For Order

The respondent promoter has committed to handing over the unit to the appellant in habitable condition within three weeks, with an affidavit of compliance to be filed by the next hearing on 18.08.2025.

11
Stage 1030/05/2025

For Order

The court granted an adjournment requested by the appellant's counsel and rescheduled the appeal for orders/hearing on 22.07.2025.

12
Stage 1120/05/2025

For Order

The Tribunal granted an adjournment request from the appellant's counsel and rescheduled the appeal for hearing on 30.05.2025, with a warning that no further adjournments will be granted and the case may proceed ex parte if the counsel fails to attend.

13
Stage 1225/04/2025

For Order

The Tribunal noted that the primary remaining issue is delayed interest and scheduled the appeal for a subsequent hearing on 20.05.2025.

14
Stage 1327/03/2025

For Order

The Tribunal noted the appellant's submission regarding the execution of the conveyance deed and scheduled the appeal for further orders/hearing on 25.04.2025.

15
Stage 1404/03/2025

For Order

The Tribunal granted a request for adjournment on behalf of the appellant's counsel and rescheduled the appeal for hearing on 27.03.2025.

16
Stage 1510/02/2025

For Order

The court granted a request from the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 04.03.2025.

17
Stage 1627/01/2025

For Order

The Tribunal noted the respondent's failure to comply with an undertaking regarding the execution of a conveyance deed and ordered the respondent to pay a cost of Rs. 20,000 to the appellant by the next hearing date on 10.02.2025.

18
Stage 1719/12/2024

For Order

The Tribunal accepted an undertaking from the Respondent to execute the conveyance deed for the subject apartment expeditiously, preferably by 20.01.2025, and directed that the deed be brought on record before the next hearing on 27.01.2025.

19
Stage 1805/11/2024

For Order

The appellant offered to deposit an outstanding amount of Rs. 1,67,874.70 within two weeks to secure unit possession and the execution of the sale-deed, a proposal which the respondent agreed to consider in accordance with the law.

20
Stage 1925/09/2024

For Order

The Tribunal granted the respondent 7 days to file objections to the appellant's amendment application, with the appellant permitted to file a reply within one week thereafter.

21
Stage 2006/09/2024

For Order

The Tribunal granted the respondent seven days to file an objection to the appellant's amendment application and scheduled the matter for hearing on 25.09.2024.

22
Stage 2106/08/2024

For Order

The Tribunal granted the respondent seven days to file objections to the appellant's amendment application and directed the appellant to file a reply within a week thereafter, scheduling the next hearing for 06.09.2024.

23
Stage 2208/07/2024

For Order

The Tribunal granted the appellant one week to upload missing pages to the memo of appeal and rescheduled the hearing to 06.08.2024 upon the joint request of both parties.

24
Stage 2309/05/2024

For Order

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 08.07.2024.

25
Stage 2408/04/2024

Delay condonation

The Tribunal closed the respondent's opportunity to file objections due to repeated failure to comply with timelines and ordered the matter to be listed for an ex parte hearing on 09.05.2024.

26
Stage 2513/03/2024

Delay condonation

The Tribunal granted the respondent three days to file objections and scheduled the next hearing for 08.04.2024.

27
Stage 2607/02/2024

Delay condonation

The Tribunal noted the absence of both parties and ordered the appeal to be listed for orders on 13.03.2024.

28
Stage 2708/11/2023

Delay condonation

No text available.

29
Stage 2825/09/2023

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and directed the subsequent filing of a reply by the appellant, with the matter listed for hearing on 08.11.2023.

30
Stage 2908/08/2023

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the appeal and directed the exchange of electronic copies between parties, scheduling the next hearing for 25.09.2023.

31
Stage 3026/05/2023

Delay condonation

No text available.

32
Stage 3117/04/2023

Delay condonation

The Tribunal directed the Registry to examine the appeal for defects and convert it into a Regular Appeal, while issuing notice to the respondent for the next hearing on 26.05.2023.

33
Stage 32Interim Order

Tribunal Order #0901126071452022-17-11-2025

The Tribunal noted that the respondent has executed the conveyance deed, delivered possession to the appellant on 07.03.2025, and uploaded a settlement deed dated 05.10.2025; the matter is listed for 02.12.2025.

34
Stage 33Interim Order

Tribunal Order #0901126071452022-22-07-2025

The respondent promoter has committed to handing over the unit to the appellant in habitable condition within three weeks, with an affidavit of compliance to be filed by the next hearing on 18.08.2025.

35
Stage 34Interim Order

Tribunal Order #0901126071452022-27-01-2025

The Tribunal noted the respondent's failure to comply with an undertaking regarding the execution of a conveyance deed and ordered the respondent to pay a cost of Rs. 20,000 to the appellant by the next hearing date on 10.02.2025.

36
Stage 35Interim Order

Tribunal Order #0901126071452022-19-12-2024

The Tribunal accepted an undertaking from the Respondent to execute the conveyance deed for the subject apartment expeditiously, preferably by 20.01.2025, and directed that the deed be brought on record before the next hearing on 27.01.2025.

37
Stage 36Interim Order

Tribunal Order #0901126071452022-17-04-2023

The Tribunal directed the Registry to examine the appeal for defects and convert it into a Regular Appeal, while issuing notice to the respondent for the next hearing on 26.05.2023.

38
Stage 37Interim Order

Tribunal Order #0901126071452022-05-11-2024

The appellant offered to deposit an outstanding amount of Rs. 1,67,874.70 within two weeks to secure unit possession and the execution of the sale-deed, a proposal which the respondent agreed to consider in accordance with the law.

39
Stage 38Final Ruling Order

Tribunal Order #0901126071452022-28-01-2026

The appeal was dismissed as withdrawn after the parties reported an amicable settlement, noting that the conveyance deed was executed and the appellant has taken physical possession of the unit.

40
Stage 39Interim Order

Tribunal Order #0901126071452022-08-04-2024

The Tribunal closed the respondent's opportunity to file objections due to repeated failure to comply with timelines and ordered the matter to be listed for an ex parte hearing on 09.05.2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal was dismissed as withdrawn after the parties reported an amicable settlement, noting that the conveyance deed was executed and the appellant has taken physical possession of the unit. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal was dismissed as withdrawn after the parties reported an amicable settlement, noting that the conveyance deed was executed and the appellant has taken physical possession of the unit.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 11(4)(f)Section 17Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shailendra Kumar Singh

Respondent Advocate(s)

  • Azhar Ikram
  • Manish Singh

Official RERA Tribunal Orders (8)

INTERIM_ORDEROrder ID: 0901126071452022-17-11-2025

The Tribunal noted that the respondent has executed the conveyance deed, delivered possession to the appellant on 07.03.2025, and uploaded a settlement deed dated 05.10.2025; the matter is listed for 02.12.2025.

INTERIM_ORDEROrder ID: 0901126071452022-22-07-2025

The respondent promoter has committed to handing over the unit to the appellant in habitable condition within three weeks, with an affidavit of compliance to be filed by the next hearing on 18.08.2025.

INTERIM_ORDEROrder ID: 0901126071452022-27-01-2025

The Tribunal noted the respondent's failure to comply with an undertaking regarding the execution of a conveyance deed and ordered the respondent to pay a cost of Rs. 20,000 to the appellant by the next hearing date on 10.02.2025.

INTERIM_ORDEROrder ID: 0901126071452022-19-12-2024

The Tribunal accepted an undertaking from the Respondent to execute the conveyance deed for the subject apartment expeditiously, preferably by 20.01.2025, and directed that the deed be brought on record before the next hearing on 27.01.2025.

INTERIM_ORDEROrder ID: 0901126071452022-17-04-2023

The Tribunal directed the Registry to examine the appeal for defects and convert it into a Regular Appeal, while issuing notice to the respondent for the next hearing on 26.05.2023.

INTERIM_ORDEROrder ID: 0901126071452022-05-11-2024

The appellant offered to deposit an outstanding amount of Rs. 1,67,874.70 within two weeks to secure unit possession and the execution of the sale-deed, a proposal which the respondent agreed to consider in accordance with the law.

FINAL_ORDEROrder ID: 0901126071452022-28-01-2026

The appeal was dismissed as withdrawn after the parties reported an amicable settlement, noting that the conveyance deed was executed and the appellant has taken physical possession of the unit.

INTERIM_ORDEROrder ID: 0901126071452022-08-04-2024

The Tribunal closed the respondent's opportunity to file objections due to repeated failure to comply with timelines and ordered the matter to be listed for an ex parte hearing on 09.05.2024.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paarth infrabuild private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →