up_reraStatus: Active
CASE ID: 0901126057632022

Appellant / Complainant

Mohammad Imran Khan

VS

Respondent

Paarth Infrabuild Private Limited

Developer Firm

paarth infrabuild private limited

Disputed Amount

17,35,630

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

22 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126057632022 by Mohammad Imran Khan against Paarth Infrabuild Private Limited before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 130/04/2026

For Order

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 25.05.2026.

3
Stage 207/05/2024

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeal, ruling that 'assured return' or commercial profit-driven arrangements fall outside the regulatory domain of the RERA Act 2016 and confirming that the Covid-19 pandemic constitutes a valid force majeure period for interest calculations.

4
Stage 320/03/2024

Hearing

The Tribunal condoned a six-day delay in filing the appeal and proceeded to hear arguments regarding the appellant's challenge against the Regulatory Authority's decision on force majeure interest deductions and the non-admissibility of assured returns.

5
Stage 404/03/2024

Hearing

The Tribunal granted an adjournment to the respondent's counsel on health grounds but scheduled the matter for an ex-parte hearing on 20.03.2024.

6
Stage 525/01/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for March 4, 2024.

7
Stage 627/10/2023

Hearing

No text available.

8
Stage 715/09/2023

Hearing

The tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing/orders on 27.10.2023.

9
Stage 827/07/2023

Hearing

No text available.

10
Stage 905/07/2023

Notice

The Tribunal decided to proceed ex-parte against the respondent, Paarth Infrabuild Private Limited, due to their failure to file objections or appear despite being granted sufficient time. The matter is scheduled for hearing on the application for condonation of delay on 27.07.2023.

11
Stage 1027/04/2023

Notice

The Tribunal ruled that service of notice to the respondent was sufficient via post and email, granting the respondent 10 days to file objections to the condonation of delay application and the appeal grounds.

12
Stage 1120/03/2023

Notice

No text available.

13
Stage 1209/02/2023

Notice

No text available.

14
Stage 1305/01/2023

Notice

No text available.

15
Stage 1405/12/2022

Notice

No text available.

16
Stage 1504/11/2022

Notice

No text available.

17
Stage 1627/09/2022

Delay condonation

The Tribunal issued a notice to the respondent regarding an application for condonation of delay and scheduled the matter for hearing on 04.11.2022.

18
Stage 17Final Ruling Order

Tribunal Order #0901126057632022-07-05-2024

The Appellate Tribunal dismissed the appeal, ruling that 'assured return' or commercial profit-driven arrangements fall outside the regulatory domain of the RERA Act 2016 and confirming that the Covid-19 pandemic constitutes a valid force majeure period for interest calculations.

19
Stage 18Interim Order

Tribunal Order #0901126057632022-20-03-2024

The Tribunal condoned a six-day delay in filing the appeal and proceeded to hear arguments regarding the appellant's challenge against the Regulatory Authority's decision on force majeure interest deductions and the non-admissibility of assured returns.

20
Stage 19Interim Order

Tribunal Order #0901126057632022-05-07-2023

The Tribunal decided to proceed ex-parte against the respondent, Paarth Infrabuild Private Limited, due to their failure to file objections or appear despite being granted sufficient time. The matter is scheduled for hearing on the application for condonation of delay on 27.07.2023.

21
Stage 20Interim Order

Tribunal Order #0901126057632022-27-04-2023

The Tribunal ruled that service of notice to the respondent was sufficient via post and email, granting the respondent 10 days to file objections to the condonation of delay application and the appeal grounds.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal, ruling that 'assured return' or commercial profit-driven arrangements fall outside the regulatory domain of the RERA Act 2016 and confirming that the Covid-19 pandemic constitutes a valid force majeure period for interest calculations. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% as fixed by the State Bank of India.

Disposal Winner: RespondentInterest Rate: MCLR+1% as fixed by the State Bank of IndiaStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal, ruling that 'assured return' or commercial profit-driven arrangements fall outside the regulatory domain of the RERA Act 2016 and confirming that the Covid-19 pandemic constitutes a valid force majeure period for interest calculations.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1% as fixed by the State Bank of India

Interest Period

from 11.04.2019 till the date of giving actual possession of the Unit, excluding the period from 25.03.2020 to 25.09.2020

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Surangama Sharma

Respondent Advocate(s)

  • Saurabh Misra
  • Krishna Kumar Singh

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126057632022-07-05-2024

The Appellate Tribunal dismissed the appeal, ruling that 'assured return' or commercial profit-driven arrangements fall outside the regulatory domain of the RERA Act 2016 and confirming that the Covid-19 pandemic constitutes a valid force majeure period for interest calculations.

INTERIM_ORDEROrder ID: 0901126057632022-20-03-2024

The Tribunal condoned a six-day delay in filing the appeal and proceeded to hear arguments regarding the appellant's challenge against the Regulatory Authority's decision on force majeure interest deductions and the non-admissibility of assured returns.

INTERIM_ORDEROrder ID: 0901126057632022-05-07-2023

The Tribunal decided to proceed ex-parte against the respondent, Paarth Infrabuild Private Limited, due to their failure to file objections or appear despite being granted sufficient time. The matter is scheduled for hearing on the application for condonation of delay on 27.07.2023.

INTERIM_ORDEROrder ID: 0901126057632022-27-04-2023

The Tribunal ruled that service of notice to the respondent was sufficient via post and email, granting the respondent 10 days to file objections to the condonation of delay application and the appeal grounds.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paarth infrabuild private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →