Appellant / Complainant
Shahinda Praveen
Respondent
Paarth Infrabuild Private Limited
paarth infrabuild private limited
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126042752021 by Shahinda Praveen against Paarth Infrabuild Private Limited before up_rera.
Hearing
The appeal was dismissed as withdrawn and rendered infructuous following an amicable settlement reached between the parties outside of court via a settlement deed dated 15.11.2025.
Hearing
The Tribunal granted a request from the appellant's counsel to list the appeal for orders or hearing on 21.11.2025.
Hearing
The Tribunal has granted a request from the learned counsel of both parties to adjourn the appeal and list the matter on 14.11.2025.
Hearing
Upon the joint request of the counsel for both parties, the appeal has been adjourned for orders/hearing to 31.10.2025.
Hearing
The Tribunal granted a request for adjournment following opposition from the appellant and scheduled the case for orders on 10.10.2025.
Hearing
The Tribunal noted that settlement processes are ongoing and adjourned the appeal to 16.09.2025 for further orders or hearing.
Hearing
The Tribunal granted the respondent promoter time to seek instructions regarding their readiness to comply with Section 18(1) of the Act by paying delay interest until the date of possession.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel but issued a warning that no further adjournments will be permitted, noting the appeal will proceed based on available records if the respondent fails to appear on the next date.
Hearing
The Tribunal has adjourned the appeal to 16.07.2025 upon the joint request of the parties, noting that no further adjournments will be granted.
Hearing
The Tribunal granted a request by the appellant's counsel to list the case for orders or hearing on 23.05.2025.
Further Hearing
The tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 22.04.2025.
Further Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 26.03.2025, noting that no further adjournments will be permitted.
Further Hearing
The Tribunal has granted a request from the appellant's counsel to reschedule the hearing of the appeal to March 3, 2025.
Further Hearing
The Tribunal scheduled the appeal for orders/hearing on 07.02.2025 and advised the appellant to file an appropriate amendment application if necessary.
Further Hearing
The Tribunal has adjourned the appeal to 16.01.2025 following a joint request from the learned counsel for both parties.
Further Hearing
The Tribunal granted a final opportunity to the respondent to conclude settlement regarding delay interest and listed the appeal for 18.12.2024, noting that no further extensions would be provided.
Hearing
The parties have expressed an intent to pursue an amicable out-of-court settlement, and the matter is adjourned to 06.12.2024 for orders.
Hearing
The respondent's counsel undertook to deposit the cost of Rs. 5,000/- imposed by the previous order dated 14.05.2024, and the matter is listed for orders on 05.11.2024.
Hearing
The Tribunal granted a request from both counsels to reschedule the hearing of Appeal-950/2021 to 25.09.2024.
Hearing
The Tribunal has scheduled the appeal for a hearing on 12.09.2024, noting that a similar matter is listed for the same date.
Hearing
The Tribunal has adjourned the appeal to 29.08.2024 for hearing, following a joint request from the counsels for both parties.
Hearing
The Tribunal adjourned the matter due to the respondent's counsel's absence but imposed a cost of Rs. 5,000/- on the respondent for failing to make alternative arrangements despite a prior order prohibiting further adjournments.
Hearing
The Tribunal scheduled the appeal for hearing on 14.05.2024 and directed that no further adjournments will be granted, noting that the matter will proceed based on available records if no party appears.
Hearing
The Tribunal granted the respondent's counsel one week to furnish information via affidavit and scheduled the next hearing for April 16, 2024.
Hearing
The Tribunal granted a request for adjournment due to the respondent's counsel's health and scheduled the appeal for hearing on 13.03.2024.
Hearing
The Tribunal granted a request from the respondent's counsel to adjourn the proceedings and rescheduled the hearing for March 4, 2024.
Hearing
The Tribunal adjourned the matter to 20.02.2024 and directed the respondent to finally address the query regarding why the conveyance deed was executed without an OC/CC in violation of the U.P. Apartment Act, 2010, warning that no further adjournments will be granted.
Hearing
The Tribunal adjourned the proceedings and rescheduled the hearing for 16.10.2023 due to a three-day strike called by the Bar Council of Uttar Pradesh.
Hearing
The Tribunal granted a request from the appellant's counsel to reschedule the appeal for hearing or orders to 06.09.2023.
Hearing
The Tribunal adjourned the matter to 18.07.2023 and directed the respondent to ensure compliance with the previous order dated 08.08.2022.
For Order
The Tribunal adjourned the proceedings due to the respondent's counsel's illness and directed the respondent to comply with the previous order dated 08.08.2022 before the next hearing.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to the hospitalization of concerned parties and directed the respondent to file relevant documents via affidavit by the next hearing on 12.04.2023.
Hearing
The Tribunal adjourned the proceedings due to the non-appearance of the respondent and scheduled the matter for hearing on 24.03.2023, noting that the case will proceed based on the existing record if the respondent fails to appear again.
Hearing
The proceedings for the day were adjourned due to the counsel for the respondent being on sanctioned leave.
Hearing
The Tribunal adjourned the proceedings due to heavy rain in the city and rescheduled the appeal for orders on 15.11.2022.
Hearing
The Tribunal granted a request for adjournment from the respondent's counsel and rescheduled the hearing for 10.10.2022.
For Order
The Tribunal granted the respondent's counsel one week's time to address the Tribunal regarding a previous query and scheduled the appeal for a hearing on 08.09.2022.
For Order
The Tribunal noted that the respondent has failed to provide a valid Occupancy Certificate (OC) or Completion Certificate (CC), and granted the respondent one week to explain why the appellant was forced to execute a conveyance deed in violation of the U.P. Apartment Act, 2010.
For Order
The Tribunal granted a 15-day extension to the appellant to take possession of the property following a settlement between the parties, adjourning the matter to 08.08.2022.
Delay condonation
The Tribunal granted an adjournment and listed the appeal for 30.05.2022 to allow the parties to continue their ongoing efforts to resolve the matter amicably.
Delay condonation
The Tribunal directed the Registry to convert the defective appeal into a regular appeal after verifying that it was filed within the period of limitation and that the respondent's objections were addressed.
Delay condonation
The Tribunal noted the filing of objections by the respondent and directed the appellant to file a reply via e-mail and the e-portal within one week, scheduling the next hearing for 04.05.2022.
Notice
The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and directed the parties to exchange pleadings via the e-portal before the next hearing on 18.04.2022.
to file objections and its reply
The Tribunal issued fresh notices to the respondent and directed the appellant's counsel to complete service via speed post and email, while also ordering the removal of registry defects to convert the matter into a regular appeal.
Defect Removal
The Tribunal noted that the appeal was filed without defects and within the limitation period, subsequently issuing notice to the respondent and scheduling the next hearing for 18.01.2022.
Tribunal Order #0901126042752021-06-08-2025
The Tribunal granted the respondent promoter time to seek instructions regarding their readiness to comply with Section 18(1) of the Act by paying delay interest until the date of possession.
Tribunal Order #0901126042752021-04-05-2022
The Tribunal directed the Registry to convert the defective appeal into a regular appeal after verifying that it was filed within the period of limitation and that the respondent's objections were addressed.
Tribunal Order #0901126042752021-25-09-2024
The respondent's counsel undertook to deposit the cost of Rs. 5,000/- imposed by the previous order dated 14.05.2024, and the matter is listed for orders on 05.11.2024.
Tribunal Order #0901126042752021-14-05-2024
The Tribunal adjourned the matter due to the respondent's counsel's absence but imposed a cost of Rs. 5,000/- on the respondent for failing to make alternative arrangements despite a prior order prohibiting further adjournments.
Tribunal Order #0901126042752021-18-01-2024
The Tribunal adjourned the matter to 20.02.2024 and directed the respondent to finally address the query regarding why the conveyance deed was executed without an OC/CC in violation of the U.P. Apartment Act, 2010, warning that no further adjournments will be granted.
Tribunal Order #0901126042752021-05-05-2023
The Tribunal adjourned the matter to 18.07.2023 and directed the respondent to ensure compliance with the previous order dated 08.08.2022.
Tribunal Order #0901126042752021-12-04-2023
The Tribunal adjourned the proceedings due to the respondent's counsel's illness and directed the respondent to comply with the previous order dated 08.08.2022 before the next hearing.
Tribunal Order #0901126042752021-08-08-2022
The Tribunal noted that the respondent has failed to provide a valid Occupancy Certificate (OC) or Completion Certificate (CC), and granted the respondent one week to explain why the appellant was forced to execute a conveyance deed in violation of the U.P. Apartment Act, 2010.
Tribunal Disposal & Final Award Ruling
Dismissed as withdrawn on having rendered infructuous Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed as withdrawn on having rendered infructuous
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shailendra Kumar Singh
Respondent Advocate(s)
- Saurabh Misra
- Krishna Kumar Singh
Official RERA Tribunal Orders (8)
The Tribunal granted the respondent promoter time to seek instructions regarding their readiness to comply with Section 18(1) of the Act by paying delay interest until the date of possession.
The Tribunal directed the Registry to convert the defective appeal into a regular appeal after verifying that it was filed within the period of limitation and that the respondent's objections were addressed.
The respondent's counsel undertook to deposit the cost of Rs. 5,000/- imposed by the previous order dated 14.05.2024, and the matter is listed for orders on 05.11.2024.
The Tribunal adjourned the matter due to the respondent's counsel's absence but imposed a cost of Rs. 5,000/- on the respondent for failing to make alternative arrangements despite a prior order prohibiting further adjournments.
The Tribunal adjourned the matter to 20.02.2024 and directed the respondent to finally address the query regarding why the conveyance deed was executed without an OC/CC in violation of the U.P. Apartment Act, 2010, warning that no further adjournments will be granted.
The Tribunal adjourned the matter to 18.07.2023 and directed the respondent to ensure compliance with the previous order dated 08.08.2022.
The Tribunal adjourned the proceedings due to the respondent's counsel's illness and directed the respondent to comply with the previous order dated 08.08.2022 before the next hearing.
The Tribunal noted that the respondent has failed to provide a valid Occupancy Certificate (OC) or Completion Certificate (CC), and granted the respondent one week to explain why the appellant was forced to execute a conveyance deed in violation of the U.P. Apartment Act, 2010.
Need to research all rulings for paarth infrabuild private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.