Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126031732021 by Sunil Chandra Saxena against Paarth Infrabuild Private Limited before up_rera.

2
Stage 130/08/2022

Further Order

The U.P. Real Estate Appellate Tribunal dismissed the appeal due to the persistent absence of the applicant, concluding that the applicant no longer intended to pursue the defective appeal.

3
Stage 223/08/2022

Further Order

The case was adjourned due to the absence of both parties, with the matter rescheduled for hearing on 30.08.2022.

4
Stage 312/07/2022

Further Order

The Tribunal adjourned the appeal due to the absence of the appellant and scheduled a hearing for August 23, 2022, to address the defective appeal.

5
Stage 402/05/2022

Further Order

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for July 12, 2022.

6
Stage 523/03/2022

Further Order

The Tribunal noted that pleadings have been exchanged and directed the parties to submit a list of dates, events, and relied-upon judgments before the next hearing date.

7
Stage 610/03/2022

Further Order

The Tribunal ordered the case to be listed on 23.03.2022 alongside related Case No. 121 of 2021.

8
Stage 705/01/2022

Further Order

The Tribunal noted the absence of the respondent despite previous directions and ordered that the respondent's counsel must appear through a Director or Authorized Representative empowered to make final decisions at the next hearing.

9
Stage 814/12/2021

Delay condonation

The Tribunal condoned a 98-day delay in filing the appeal, citing COVID-19 pandemic relaxations as per Supreme Court guidelines, and directed the registry to convert the defective appeal into a regular appeal.

10
Stage 922/11/2021

Hearing

The Tribunal granted the applicant one week to file a reply to the respondent's objections and directed the exchange of contact information for electronic service of the reply.

11
Stage 1027/09/2021

Notice

The Tribunal granted the respondent time to file a Vakalat Nama and objections to the condonation application, scheduling the next hearing for November 22, 2021.

12
Stage 1108/09/2021

Delay condonation

The Tribunal noted that the applicant has removed all defects and scheduled the matter for 27.09.2021 to consider the application for condonation of delay.

13
Stage 12Final Ruling Order

Tribunal Order #0901126031732021-30-08-2022

The U.P. Real Estate Appellate Tribunal dismissed the appeal due to the persistent absence of the applicant, concluding that the applicant no longer intended to pursue the defective appeal.

14
Stage 13Interim Order

Tribunal Order #0901126031732021-14-12-2021

The Tribunal condoned a 98-day delay in filing the appeal, citing COVID-19 pandemic relaxations as per Supreme Court guidelines, and directed the registry to convert the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal due to the persistent absence of the applicant, concluding that the applicant no longer intended to pursue the defective appeal. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal due to the persistent absence of the applicant, concluding that the applicant no longer intended to pursue the defective appeal.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shailender Singh

Respondent Advocate(s)

  • Rajiv Shukla

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126031732021-30-08-2022

The U.P. Real Estate Appellate Tribunal dismissed the appeal due to the persistent absence of the applicant, concluding that the applicant no longer intended to pursue the defective appeal.

INTERIM_ORDEROrder ID: 0901126031732021-14-12-2021

The Tribunal condoned a 98-day delay in filing the appeal, citing COVID-19 pandemic relaxations as per Supreme Court guidelines, and directed the registry to convert the defective appeal into a regular appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paarth infrabuild private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →