up_reraStatus: Completed
CASE ID: 0901126027972021

Appellant / Complainant

Rohit Agarwal

VS

Respondent

Tulsiani Construction and Developers Pvt. Ltd.

Developer Firm

tulsiani construction and developers pvt. ltd.

Disputed Amount

89,21,146

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

30 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126027972021 by Rohit Agarwal against Tulsiani Construction and Developers Pvt. Ltd. before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 104/08/2023

Hearing

The Tribunal set aside direction no. 3 of the Regulatory Authority's order because it mandated a refund that the appellants had never requested, ruling instead that the developer must fulfill its obligation to deliver possession.

3
Stage 224/05/2023

Hearing

No text available.

4
Stage 315/05/2023

Hearing

The matter was adjourned due to lack of time, with the case rescheduled for hearing on 24.05.2023.

5
Stage 402/05/2023

Further Hearing

The Tribunal granted a request for an amicable settlement period and scheduled the appeal for orders on 15.05.2023, noting that oral arguments will proceed if no settlement is reached.

6
Stage 521/03/2023

Further Hearing

No text available.

7
Stage 610/02/2023

Further Hearing

No text available.

8
Stage 706/01/2023

Further Hearing

No text available.

9
Stage 806/12/2022

Further Hearing

No text available.

10
Stage 911/11/2022

Further Hearing

The Tribunal adjourned the matter to 06.12.2022 after the respondent's counsel noted that a moratorium has been issued by the NCLT and promised to upload the relevant order.

11
Stage 1011/10/2022

Further Order

The Tribunal heard arguments regarding the appellant's claim for possession versus the respondent's claim of unpaid loan obligations and scheduled the matter for further orders on 11.11.2022.

12
Stage 1121/09/2022

Further Order

The Tribunal heard arguments regarding the mortgage status of specific towers and scheduled the appeal for a final hearing on 11.10.2022.

13
Stage 1223/08/2022

Further Order

The Tribunal directed the respondent to submit a demand letter and specify the amount recoverable from the appellant before the next hearing scheduled for 21.09.2022.

14
Stage 1319/07/2022

Further Order

The Tribunal directed the parties to exchange and file a list of dates, events, and cited case laws at least 10 days prior to the next hearing scheduled for August 23, 2022.

15
Stage 1409/05/2022

Further Order

The Tribunal directed the appellant to pay a cost of Rs. 5000/- directly to the respondent and ordered both parties to file lists of dates, events, and cited cases at least seven days before the next hearing.

16
Stage 1504/04/2022

Delay condonation

The Tribunal condoned a 707-day delay in filing the appeal, subject to a cost of Rs. 10,000, and directed the defective appeal to be registered as a Regular Appeal.

17
Stage 1624/03/2022

Delay condonation

The Tribunal adjourned the matter to 04.04.2022 to consider the appellant's application for condonation of delay and any subsequent objections from the respondent.

18
Stage 1710/03/2022

Delay condonation

The Tribunal granted the appellant one week to file a better affidavit regarding the application for condonation of delay and directed the parties to exchange documents via email before the next hearing on 24.03.2022.

19
Stage 1805/01/2022

Delay condonation

The Tribunal granted an adjournment requested by the counsel for the appellant and rescheduled the case for hearing on 28.01.2022.

20
Stage 1921/12/2021

Delay condonation

The Tribunal granted the appellant a short extension of time to file a rejoinder and scheduled the defective appeal for further orders on 05.01.2022.

21
Stage 2023/11/2021

Delay condonation

The Tribunal heard arguments regarding a limitation application and granted the appellant's request to file a rejoinder affidavit, adjourning the matter to 21.12.2021.

22
Stage 2128/09/2021

Delay condonation

The Tribunal granted an adjournment due to the counsel's inability to attend and rescheduled the hearing for November 23, 2021.

23
Stage 2208/09/2021

Hearing

The Tribunal directed the parties to negotiate a potential settlement via email and instructed the respondent to file any objections through email, adjourning the matter to 28.09.2021.

24
Stage 2317/08/2021

Notice

The Tribunal directed the respondent's counsel to file a Vakalatnama within one week and to submit an objection to the limitation application online and in physical form. The matter is scheduled for 08.09.2021 to address the delay condonation application.

25
Stage 2419/07/2021

Defect Removal

The Tribunal issued notice to the respondent regarding the appeal and its delay condonation application, scheduling the matter for a hearing on 17.08.2021.

26
Stage 25Final Ruling Order

Tribunal Order #0901126027972021-04-08-2023

The Tribunal set aside direction no. 3 of the Regulatory Authority's order because it mandated a refund that the appellants had never requested, ruling instead that the developer must fulfill its obligation to deliver possession.

27
Stage 26Interim Order

Tribunal Order #0901126027972021-04-04-2022

The Tribunal condoned a 707-day delay in filing the appeal, subject to a cost of Rs. 10,000, and directed the defective appeal to be registered as a Regular Appeal.

28
Stage 27Interim Order

Tribunal Order #0901126027972021-23-08-2022

The Tribunal directed the respondent to submit a demand letter and specify the amount recoverable from the appellant before the next hearing scheduled for 21.09.2022.

29
Stage 28Interim Order

Tribunal Order #0901126027972021-09-05-2022

The Tribunal directed the appellant to pay a cost of Rs. 5000/- directly to the respondent and ordered both parties to file lists of dates, events, and cited cases at least seven days before the next hearing.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside direction no. 3 of the Regulatory Authority's order because it mandated a refund that the appellants had never requested, ruling instead that the developer must fulfill its obligation to deliver possession. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside direction no. 3 of the Regulatory Authority's order because it mandated a refund that the appellants had never requested, ruling instead that the developer must fulfill its obligation to deliver possession.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

from the proposed date of possession till the date of actual possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Fuhar Gupta

Respondent Advocate(s)

  • Saurabh Misra
  • Vikas Kumar Verma
  • Krishna Kumar Singh

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126027972021-04-08-2023

The Tribunal set aside direction no. 3 of the Regulatory Authority's order because it mandated a refund that the appellants had never requested, ruling instead that the developer must fulfill its obligation to deliver possession.

INTERIM_ORDEROrder ID: 0901126027972021-04-04-2022

The Tribunal condoned a 707-day delay in filing the appeal, subject to a cost of Rs. 10,000, and directed the defective appeal to be registered as a Regular Appeal.

INTERIM_ORDEROrder ID: 0901126027972021-23-08-2022

The Tribunal directed the respondent to submit a demand letter and specify the amount recoverable from the appellant before the next hearing scheduled for 21.09.2022.

INTERIM_ORDEROrder ID: 0901126027972021-09-05-2022

The Tribunal directed the appellant to pay a cost of Rs. 5000/- directly to the respondent and ordered both parties to file lists of dates, events, and cited cases at least seven days before the next hearing.

TathyaGrid RERA Intelligence AI

Need to research all rulings for tulsiani construction and developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →