up_reraStatus: Completed
CASE ID: 0901126020692021

Appellant / Complainant

Sethia Realty Pvt. Ltd.

VS

Respondent

Tulsiani Construction and Developers Pvt. Ltd. Plot No. 3 Green Park (Main) New Delhi -110016

Developer Firm

tulsiani construction and developers pvt. ltd.

Disputed Amount

69,88,674

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126020692021 by Sethia Realty Pvt. Ltd. against Tulsiani Construction and Developers Pvt. Ltd. Plot No. 3 Green Park (Main) New Delhi -110016 before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestNon-Compliance & Execution
2
Stage 101/04/2022

Further Hearing

The Tribunal permitted the appellant to withdraw the appeal to pursue execution proceedings for the refund of deposited amounts under direction no. 2 of the original Regulatory Authority order, noting that the respondent had failed to provide possession or a refund.

3
Stage 231/03/2022

Final Hearing

The Tribunal granted a request for adjournment due to the appellant's counsel being engaged in another court, rescheduling the hearing to 01.04.2022.

4
Stage 330/03/2022

Delay condonation

The Tribunal allowed the application for condonation of delay by 10 days, imposing a cost of Rs. 1,000/- on the appellant and directing the Registry to convert the defective appeal into a regular appeal.

5
Stage 414/03/2022

to file objections and its reply

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and scheduled the case for hearing on 30.03.2022 regarding the application for condonation of delay.

6
Stage 528/02/2022

to file objections and its reply

The Tribunal directed the respondent to upload and file their objections on the e-portal and with the Registry within one week, and scheduled the appeal for hearing on 14.03.2022.

7
Stage 618/01/2022

Hearing

No text available.

8
Stage 705/01/2022

Hearing

The Tribunal granted the appellant one week's time to file a reply to the respondent's objections and scheduled the matter for hearing on January 18, 2022.

9
Stage 806/12/2021

Hearing

No text available.

10
Stage 915/11/2021

Hearing

The Tribunal granted the respondent one week to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent deadline for the applicant's reply.

11
Stage 1023/09/2021

Hearing

The Tribunal directed the Respondent's counsel to file their Vakalatnama and objections to the limitation application, scheduling the matter for November 15, 2021.

12
Stage 1126/04/2021

Delay condonation

No text available.

13
Stage 1225/03/2021

Hearing on Appeal

The Tribunal directed the issuance of notice to the respondent via registered post and email and scheduled the matter for April 26, 2021, to address limitation issues.

14
Stage 13Final Ruling Order

Tribunal Order #0901126020692021-01-04-2022

The Tribunal permitted the appellant to withdraw the appeal to pursue execution proceedings for the refund of deposited amounts under direction no. 2 of the original Regulatory Authority order, noting that the respondent had failed to provide possession or a refund.

15
Stage 14Interim Order

Tribunal Order #0901126020692021-30-03-2022

The Tribunal allowed the application for condonation of delay by 10 days, imposing a cost of Rs. 1,000/- on the appellant and directing the Registry to convert the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal permitted the appellant to withdraw the appeal to pursue execution proceedings for the refund of deposited amounts under direction no. 2 of the original Regulatory Authority order, noting that the respondent had failed to provide possession or a refund. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal permitted the appellant to withdraw the appeal to pursue execution proceedings for the refund of deposited amounts under direction no. 2 of the original Regulatory Authority order, noting that the respondent had failed to provide possession or a refund.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

w.e.f. 01.02.2018 till the delivery of physical possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Himanshu Hemant Gupta

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126020692021-01-04-2022

The Tribunal permitted the appellant to withdraw the appeal to pursue execution proceedings for the refund of deposited amounts under direction no. 2 of the original Regulatory Authority order, noting that the respondent had failed to provide possession or a refund.

INTERIM_ORDEROrder ID: 0901126020692021-30-03-2022

The Tribunal allowed the application for condonation of delay by 10 days, imposing a cost of Rs. 1,000/- on the appellant and directing the Registry to convert the defective appeal into a regular appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for tulsiani construction and developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →