up_reraStatus: Completed
CASE ID: 0901126027912021

Appellant / Complainant

Sunita Agarwal

VS

Respondent

Tulsiani Construction and Developers Pvt. Ltd.

Developer Firm

tulsiani construction and developers pvt. ltd.

Disputed Amount

89,21,146

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

31 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126027912021 by Sunita Agarwal against Tulsiani Construction and Developers Pvt. Ltd. before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 104/08/2023

Hearing

The Tribunal set aside direction no. 3 of the Regulatory Authority's order because it mandated a refund that the appellants had never requested, ruling instead that the developer must fulfill its obligation to deliver possession.

3
Stage 224/05/2023

Hearing

No text available.

4
Stage 315/05/2023

Hearing

The matter was adjourned due to lack of time, with the court directing the case to be listed again on 24.05.2023.

5
Stage 402/05/2023

Further Order

The Tribunal granted a request for an adjournment to allow the parties to attempt an amicable settlement, scheduling the matter for orders on 15.05.2023, with oral arguments to proceed if no settlement is reached.

6
Stage 521/03/2023

Further Order

No text available.

7
Stage 610/02/2023

Further Order

No text available.

8
Stage 706/01/2023

Further Order

No text available.

9
Stage 806/12/2022

Further Order

No text available.

10
Stage 911/11/2022

Further Order

The Tribunal adjourned the matter to 06.12.2022 after the respondent's counsel noted that a moratorium has been issued by the NCLT and committed to uploading the relevant order.

11
Stage 1011/10/2022

Further Order

The Tribunal heard arguments regarding the appellant's claim for possession of a flat and the respondent's claim regarding unpaid loan amounts, subsequently adjourning the matter to 11.11.2022.

12
Stage 1121/09/2022

Further Order

The Tribunal heard arguments regarding the mortgage status of specific towers and scheduled the appeal for a final hearing on 11.10.2022.

13
Stage 1223/08/2022

Further Order

The Tribunal directed the respondent to submit a demand letter and specify the amount recoverable from the appellant prior to the next hearing on September 21, 2022.

14
Stage 1319/07/2022

Further Order

The Tribunal directed the parties to file a list of dates, events, and cited case laws at least 10 days before the next hearing, which is scheduled for 23.08.2022.

15
Stage 1409/05/2022

Further Order

The Tribunal directed the appellant to pay a cost of Rs. 5,000/- directly to the respondent and ordered both parties to file lists of dates, events, and cited cases at least seven days before the next hearing.

16
Stage 1504/04/2022

Delay condonation

The Tribunal condoned a 707-day delay in filing the appeal, subject to a cost of Rs. 10,000, and directed the matter to be registered as a Regular Appeal for hearing on merits.

17
Stage 1624/03/2022

Hearing

The Tribunal scheduled the matter for 04.04.2022 to address the appellant's application for condonation of delay and any subsequent objections from the respondent.

18
Stage 1708/03/2022

Delay condonation

The Tribunal granted the appellant one week to file a better affidavit for condonation of delay and directed parties to upload pleadings on the e-portal before the next hearing on 24.03.2022.

19
Stage 1807/03/2022

Delay condonation

The Tribunal granted a request from the Appellant's counsel to adjourn the matter to 08.03.2022 to allow for oral submissions and the citation of judgments regarding an application for condonation of delay.

20
Stage 1905/01/2022

Hearing

The Tribunal granted a request for adjournment due to the illness of the appellant's counsel and rescheduled the case for hearing on 24.01.2022.

21
Stage 2021/12/2021

Hearing

The Tribunal adjourned the matter to 05.01.2022 for the disposal of a limitation application and directed the appellant's counsel to file a replication within three days.

22
Stage 2123/11/2021

Hearing

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the defective appeal for hearing on 21.12.2021.

23
Stage 2228/09/2021

Delay condonation

No text available.

24
Stage 2308/09/2021

Hearing

No text available.

25
Stage 2417/08/2021

Notice

The Tribunal directed the respondent's counsel to file a Vakalatnama within one week and instructed them to file an objection to the limitation application before the next hearing on 08.09.2021.

26
Stage 2519/07/2021

Defect Removal

The Tribunal issued notice to the respondent regarding the appeal and scheduled the matter for a hearing on 17.08.2021.

27
Stage 26Interim Order

Tribunal Order #0901126027912021-09-05-2022

The Tribunal directed the appellant to pay a cost of Rs. 5,000/- directly to the respondent and ordered both parties to file lists of dates, events, and cited cases at least seven days before the next hearing.

28
Stage 27Interim Order

Tribunal Order #0901126027912021-04-04-2022

The Tribunal condoned a 707-day delay in filing the appeal, subject to a cost of Rs. 10,000, and directed the matter to be registered as a Regular Appeal for hearing on merits.

29
Stage 28Final Ruling Order

Tribunal Order #0901126027912021-04-08-2023

The Tribunal set aside direction no. 3 of the Regulatory Authority's order because it mandated a refund that the appellants had never requested, ruling instead that the developer must fulfill its obligation to deliver possession.

30
Stage 29Interim Order

Tribunal Order #0901126027912021-23-08-2022

The Tribunal directed the respondent to submit a demand letter and specify the amount recoverable from the appellant prior to the next hearing on September 21, 2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside direction no. 3 of the Regulatory Authority's order because it mandated a refund that the appellants had never requested, ruling instead that the developer must fulfill its obligation to deliver possession. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside direction no. 3 of the Regulatory Authority's order because it mandated a refund that the appellants had never requested, ruling instead that the developer must fulfill its obligation to deliver possession.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

from the proposed date of possession till the date of actual possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Fuhar Gupta

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (4)

INTERIM_ORDEROrder ID: 0901126027912021-09-05-2022

The Tribunal directed the appellant to pay a cost of Rs. 5,000/- directly to the respondent and ordered both parties to file lists of dates, events, and cited cases at least seven days before the next hearing.

INTERIM_ORDEROrder ID: 0901126027912021-04-04-2022

The Tribunal condoned a 707-day delay in filing the appeal, subject to a cost of Rs. 10,000, and directed the matter to be registered as a Regular Appeal for hearing on merits.

FINAL_ORDEROrder ID: 0901126027912021-04-08-2023

The Tribunal set aside direction no. 3 of the Regulatory Authority's order because it mandated a refund that the appellants had never requested, ruling instead that the developer must fulfill its obligation to deliver possession.

INTERIM_ORDEROrder ID: 0901126027912021-23-08-2022

The Tribunal directed the respondent to submit a demand letter and specify the amount recoverable from the appellant prior to the next hearing on September 21, 2022.

TathyaGrid RERA Intelligence AI

Need to research all rulings for tulsiani construction and developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →