Appellant / Complainant
Gaursons Hi-Tech Infrastructure Private Limited
Respondent
Chanchal Bhatia
gaursons hi-tech infrastructure private limited
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126064992022 by Gaursons Hi-Tech Infrastructure Private Limited against Chanchal Bhatia before up_rera.
Delay condonation
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 75-day delay and consequently dismissed the appeal due to an unsatisfactory explanation regarding data retrieval issues.
Hearing
The Tribunal granted the appellant one week to file a better affidavit for condonation of delay and scheduled the hearing for 17.10.2024.
Hearing
Both parties filed applications for adjournment, resulting in the tribunal rescheduling the appeal for hearing on 06.09.2024.
Hearing
The Tribunal has granted a request from both parties' counsels to list the defective appeal for orders or hearing on 05.07.2024.
Hearing
The Tribunal noted that pleadings have been exchanged and scheduled the defective appeal for consideration of the application for condonation of delay on 08.05.2024.
Hearing
The Tribunal granted the applicant 10 days to file a reply to the respondent's objections and scheduled the hearing for April 5, 2024.
Hearing
The Tribunal granted the respondent 10 days to file objections and scheduled the matter for hearing on March 1, 2024, to consider condonation of delay.
Delay condonation
The Tribunal adjourned the proceedings due to a call by the Bar Council of Uttar Pradesh for lawyers to abstain from judicial work and rescheduled the hearing for 26.10.2023.
Delay condonation
The Tribunal granted the respondent 10 days to file objections regarding the condonation of delay and grounds of appeal, directing the appellant to reply within one week and scheduling the next hearing for 14.09.2023.
Delay condonation
The Tribunal accepted the appellant's proof of TDS payment compliance under Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 10.05.2023.
Delay condonation
The Tribunal directed the applicant's counsel to resolve technical issues regarding a missing application on the portal and instructed the Registry to ensure visibility of the application on the dashboard.
Delay condonation
The Tribunal granted the Appellant one week to ensure complete compliance with Section 43(5) of the Real Estate (Regulation and Development) Act, 2016, and allowed the Respondent time to file objections.
Delay condonation
The Tribunal granted the appellant a 10-day extension to comply with Section 43(5) of the Act 2016 by depositing the remaining amount, warning that failure to do so will result in the dismissal of the defective appeal.
Delay condonation
The Tribunal directed the appellant to deposit the unpaid TDS amount of Rs. 7,820/- within one week to comply with Section 43(5) of the Act regarding mandatory deposits for filing an appeal.
Tribunal Order #0901126064992022-17-10-2024
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 75-day delay and consequently dismissed the appeal due to an unsatisfactory explanation regarding data retrieval issues.
Tribunal Order #0901126064992022-01-03-2023
The Tribunal granted the appellant a 10-day extension to comply with Section 43(5) of the Act 2016 by depositing the remaining amount, warning that failure to do so will result in the dismissal of the defective appeal.
Tribunal Order #0901126064992022-29-03-2023
The Tribunal accepted the appellant's proof of TDS payment compliance under Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 10.05.2023.
Tribunal Order #0901126064992022-16-03-2023
The Tribunal granted the Appellant one week to ensure complete compliance with Section 43(5) of the Real Estate (Regulation and Development) Act, 2016, and allowed the Respondent time to file objections.
Tribunal Order #0901126064992022-06-02-2023
The Tribunal directed the appellant to deposit the unpaid TDS amount of Rs. 7,820/- within one week to comply with Section 43(5) of the Act regarding mandatory deposits for filing an appeal.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 75-day delay and consequently dismissed the appeal due to an unsatisfactory explanation regarding data retrieval issues. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 75-day delay and consequently dismissed the appeal due to an unsatisfactory explanation regarding data retrieval issues.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Samrat Vaish
- Mohit Yadav
Respondent Advocate(s)
- Abhishek Shukla
- Harprit Singh Arora
Official RERA Tribunal Orders (5)
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of a 75-day delay and consequently dismissed the appeal due to an unsatisfactory explanation regarding data retrieval issues.
The Tribunal granted the appellant a 10-day extension to comply with Section 43(5) of the Act 2016 by depositing the remaining amount, warning that failure to do so will result in the dismissal of the defective appeal.
The Tribunal accepted the appellant's proof of TDS payment compliance under Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 10.05.2023.
The Tribunal granted the Appellant one week to ensure complete compliance with Section 43(5) of the Real Estate (Regulation and Development) Act, 2016, and allowed the Respondent time to file objections.
The Tribunal directed the appellant to deposit the unpaid TDS amount of Rs. 7,820/- within one week to comply with Section 43(5) of the Act regarding mandatory deposits for filing an appeal.
Need to research all rulings for gaursons hi-tech infrastructure private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.