up_reraStatus: Completed
CASE ID: 0901126052902023

Appellant / Complainant

Monika Singh, Abhishek Singh

VS

Respondent

Sikka Infrastructure Pvt Ltd

Developer Firm

sikka infrastructure pvt ltd

Disputed Amount

18,31,500

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126052902023 by Monika Singh, Abhishek Singh against Sikka Infrastructure Pvt Ltd before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional Misrepresentation
2
Stage 123/04/2025

for delivery of Judgment/Order

The Appellate Tribunal modified the Regulatory Authority's order, directing the respondent to refund the full deposit of Rs. 18,31,500 with interest at MCLR+1% from the date of deposit, ruling that 'zero period' and 'COVID-19 period' do not qualify as force majeure in this instance.

3
Stage 229/01/2025

Part Heard

The Tribunal heard arguments from the counsel for both parties regarding the appeal, but has reserved the judgment for a later date.

4
Stage 315/01/2025

Hearing

The Tribunal notes that the matter is part-heard of Bench No. 2 and directs it to be listed before said Bench on January 29, 2025.

5
Stage 410/01/2025

Hearing

The matter was partially heard, and the Tribunal has scheduled the case to be listed before the appropriate bench on January 15, 2025.

6
Stage 507/01/2025

Hearing

The Tribunal granted both counsels time to upload rules/decisions and prepare briefs, adjourning the matter to 10.01.2025 for further hearing.

7
Stage 609/12/2024

Hearing

The Tribunal granted a request from the respondent's counsel for additional time to prepare arguments and adjourned the appeal to 07.01.2025.

8
Stage 705/11/2024

Delay condonation

The Tribunal condoned a 16-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.

9
Stage 825/09/2024

Delay condonation

The Tribunal granted the respondent seven days to file objections to the appellant's new affidavit regarding the delay in filing the appeal and scheduled the matter for orders on November 5, 2024.

10
Stage 927/08/2024

Delay condonation

The Tribunal granted the applicant 7 days to file a better affidavit regarding the condonation of delay, with subsequent timelines set for respondent objections and applicant replies.

11
Stage 1024/07/2024

Admission

The Tribunal directed the appellant to serve a copy of their rejoinder to the respondent within three days and scheduled the next hearing for 27.08.2024.

12
Stage 1124/05/2024

Admission

The Tribunal noted the absence of the applicant and directed that any reply to the respondent's objections be filed within 10 days, listing the defective appeal for hearing on 24.07.2024.

13
Stage 1224/04/2024

Admission

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on May 24, 2024, regarding the application for condonation of delay.

14
Stage 1319/03/2024

Admission

The Tribunal granted the respondent an additional week to file objections to the grounds of appeal and directed the applicant to file replies to existing objections within specified timelines.

15
Stage 1415/02/2024

Admission

The Tribunal granted the respondent 10 days to file objections and scheduled the matter for hearing on March 19, 2024, regarding the application for condonation of delay.

16
Stage 1508/01/2024

Defect Removal

The Tribunal directed the issuance of notice to the respondent following the removal of registry defects and set a timeline for service of process and filing of objections regarding the application for condonation of delay.

17
Stage 1622/12/2023

Defect Removal

The Tribunal directed the Registry to communicate existing defects to the appellant and ordered that the appeal be listed on 08.01.2024, noting that failure to rectify these defects will result in dismissal.

18
Stage 17Final Ruling Order

Tribunal Order #0901126052902023-23-04-2025

The Appellate Tribunal modified the Regulatory Authority's order, directing the respondent to refund the full deposit of Rs. 18,31,500 with interest at MCLR+1% from the date of deposit, ruling that 'zero period' and 'COVID-19 period' do not qualify as force majeure in this instance.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal modified the Regulatory Authority's order, directing the respondent to refund the full deposit of Rs. 18,31,500 with interest at MCLR+1% from the date of deposit, ruling that 'zero period' and 'COVID-19 period' do not qualify as force majeure in this instance. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: AppellantInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal modified the Regulatory Authority's order, directing the respondent to refund the full deposit of Rs. 18,31,500 with interest at MCLR+1% from the date of deposit, ruling that 'zero period' and 'COVID-19 period' do not qualify as force majeure in this instance.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1% per annum

Interest Period

from the date of deposit till the date of actual payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anilesh Tewari

Respondent Advocate(s)

  • Mandeep Singh
  • Rohit Jaiswal

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126052902023-23-04-2025

The Appellate Tribunal modified the Regulatory Authority's order, directing the respondent to refund the full deposit of Rs. 18,31,500 with interest at MCLR+1% from the date of deposit, ruling that 'zero period' and 'COVID-19 period' do not qualify as force majeure in this instance.

TathyaGrid RERA Intelligence AI

Need to research all rulings for sikka infrastructure pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →