Appellant / Complainant
Wasim Ahmed, Sadaf Ayesha
Respondent
Rudra Buildwell Infra Pvt. Ltd.
rudra buildwell infra pvt. ltd.
₹34,53,341
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126048522022 by Wasim Ahmed, Sadaf Ayesha against Rudra Buildwell Infra Pvt. Ltd. before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal set aside the Regulatory Authority's order that directed allottees to take possession and pay balance dues, remanding the matter back for reconsideration in light of the allottees' unqualified right to seek a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to offer possession within the stipulated timeline.
Hearing
This is a procedural order directing the reader to refer to the orders passed in Appeal No. 545/2022 for substantive directions.
Hearing
The Tribunal has scheduled the appeal for a hearing on 07.02.2024 and referred to a previous order passed in Appeal No. 545/2022.
Hearing
The Tribunal has scheduled the appeal for a hearing on 30.10.2023 and referred to a previous order passed in Appeal No. 545/2022.
Hearing
This document appears to be a header or a formal case identification entry for Appeal-556/2022 involving Mr. Wasimahmed before the U.P. Real Estate Appellate Tribunal, containing no substantive rulings or directives.
Hearing
The Tribunal directed that the order passed in Appeal No. 545/2022 (Ranjana Gupta Vs. M/s Rudra Buildwell Infra Pvt. Ltd.) applies to this matter and scheduled the appeal for hearing on 13.04.2023 along with similar cases.
Hearing
The Tribunal has scheduled the appeal for a hearing on March 2, 2023, and directed reference to a previous order passed in Appeal No. 545 of 2022.
Exchange of pleadings
The Tribunal granted the appellant a final opportunity to file a replication/rejoinder against the respondent's reply and scheduled the matter for hearing on 13.02.2023.
Exchange of pleadings
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 21.12.2022.
Exchange of pleadings
The Tribunal directed the appellant to file a replication to the respondent's reply within one week and provided a subsequent hearing date of 25.11.2022.
to file objections and its reply
The Tribunal directed the appellant's counsel to file a replication against the respondent's reply by the next hearing date and scheduled the matter for further orders on 01.11.2022.
Notice
The Tribunal directed the respondent's counsel to register on the e-portal and granted ten days for filing objections to the appeal, with a subsequent timeline set for the appellant's reply.
Admission
The Tribunal issued a notice to the respondent and established procedural timelines for service of appeal documents and the filing of objections/replies before the next hearing on 14.09.2022.
Tribunal Order #0901126048522022-07-05-2024
The Appellate Tribunal set aside the Regulatory Authority's order that directed allottees to take possession and pay balance dues, remanding the matter back for reconsideration in light of the allottees' unqualified right to seek a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to offer possession within the stipulated timeline.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal set aside the Regulatory Authority's order that directed allottees to take possession and pay balance dues, remanding the matter back for reconsideration in light of the allottees' unqualified right to seek a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to offer possession within the stipulated timeline. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal set aside the Regulatory Authority's order that directed allottees to take possession and pay balance dues, remanding the matter back for reconsideration in light of the allottees' unqualified right to seek a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to offer possession within the stipulated timeline.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR + 1 percent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
- Suyesh Pradhan
Respondent Advocate(s)
- Ajai Kumar Gupta
- Rishindra Vikram Singh
Official RERA Tribunal Orders (1)
The Appellate Tribunal set aside the Regulatory Authority's order that directed allottees to take possession and pay balance dues, remanding the matter back for reconsideration in light of the allottees' unqualified right to seek a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to offer possession within the stipulated timeline.
Need to research all rulings for rudra buildwell infra pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.