Appellant / Complainant
Rahul Kumar, Anju Rathi
Respondent
Rudra Buildwell Infra Pvt. Ltd.
rudra buildwell infra pvt. ltd.
₹34,53,341
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126048472022 by Rahul Kumar, Anju Rathi against Rudra Buildwell Infra Pvt. Ltd. before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.
Hearing
The Tribunal issued a procedural order referring the matter to the orders passed in Appeal No. 545/2022.
Hearing
The Tribunal has listed Appeal No. 553/2022 for a hearing on February 7, 2024, noting that orders regarding this matter can be found in the order passed in Appeal No. 545/2022.
Hearing
The Tribunal directed that the appeal be listed for hearing on 30.10.2023.
Hearing
The Tribunal refers the parties to a previously passed order in Appeal No. 545/2022 for the directions regarding this matter.
Hearing
The Tribunal directs the parties to refer to the order passed in Appeal No. 545/2022 (Ranjana Gupta Vs. M/s Rudra Buildwell Infra Pvt. Ltd.) for the relevant orders.
Hearing
The Tribunal has scheduled the appeal for a hearing on March 2, 2023, and directed reference to a previous order passed in Appeal No. 545 of 2022.
Exchange of pleadings
The Tribunal granted the appellant a final opportunity to file a replication/rejoinder against the respondent's reply and scheduled the next hearing for 13.02.2023.
Exchange of pleadings
The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the appeal for hearing on 21.12.2022.
Exchange of pleadings
The Tribunal directed the appellant to file a replication/response to the respondent's reply and serve it via email within one week, with the matter listed for hearing on 25.11.2022.
to file objections and its reply
The Tribunal granted the appellant permission to file a replication against the respondent's reply and scheduled the matter for further orders on 01.11.2022.
Notice
The Tribunal directed the respondent's counsel to register on the e-portal and granted ten days to file objections to the appeal, with a subsequent timeline for the appellant's reply.
Admission
The Tribunal issued a notice to the respondent and established a procedural timeline for service of appeal documents and the filing of objections and replies.
Tribunal Order #0901126048472022-07-05-2024
The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
- Suyesh Pradhan
Respondent Advocate(s)
- Ajai Kumar Gupta
- Rishindra Vikram Singh
Official RERA Tribunal Orders (1)
The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.