Appellant / Complainant
Utkarsh Gupta
Respondent
Rudra Buildwell Infra Pvt. Ltd.
rudra buildwell infra pvt. ltd.
₹34,53,341
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126048492022 by Utkarsh Gupta against Rudra Buildwell Infra Pvt. Ltd. before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.
Hearing
This is a procedural order directing the reader to refer to the orders passed on 07.02.2024 in Appeal No. 545/2022 for the relevant directions.
Hearing
The Tribunal has scheduled the appeal for a hearing on 07.02.2024 and referred to a previous order passed in Appeal No. 545/2022.
Hearing
The Tribunal has scheduled the appeal for a hearing on 30.10.2023, referencing a previous order passed in Appeal No. 545/2022.
Hearing
The Tribunal directs the parties to refer to the order previously passed in Appeal No. 545/2022 for the relevant orders.
Hearing
The Tribunal refers the parties to a previous order passed in Appeal No. 545/2022 (Ranjana Gupta Vs. M/s Rudra Buildwell Infra Pvt. Ltd.) for the relevant directions.
Hearing
The Tribunal scheduled the appeal for a hearing on March 2, 2023, and directed reference to a previous order passed in Appeal No. 545 of 2022.
Exchange of pleadings
The Tribunal granted the appellant a final opportunity to file a replication/rejoinder against the respondent's reply and adjourned the matter to 13.02.2023.
Exchange of pleadings
The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the appeal for hearing on 21.12.2022.
Exchange of pleadings
The Tribunal directed the appellant to file a replication/response to the respondent's reply within one week and serve it via email and the e-portal before the next hearing scheduled for 25.11.2022.
to file objections and its reply
The Tribunal granted the appellant permission to file a replication against the respondent's reply and scheduled the next hearing for November 1, 2022.
Notice
The Tribunal directed the respondent's counsel to register on the e-portal and granted ten days for filing objections to the appeal, with a subsequent timeline for the appellant's reply.
Admission
The Tribunal issued a notice to the respondent and outlined the procedural requirements for service of appeal documents and the subsequent exchange of objections and replies before the next hearing on 14.09.2022.
Tribunal Order #0901126048492022-07-05-2024
The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
- Suyesh Pradhan
Respondent Advocate(s)
- Ajay Kumar Gupta
- Rishindra Vikram Singh
Official RERA Tribunal Orders (1)
The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.