up_reraStatus: Completed
CASE ID: 0901126048202022

Appellant / Complainant

Navin Kumar Gupta, Tarun Gupta

VS

Respondent

Rudra Buildwell Infra Pvt. Ltd.

Developer Firm

rudra buildwell infra pvt. ltd.

Disputed Amount

36,30,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126048202022 by Navin Kumar Gupta, Tarun Gupta against Rudra Buildwell Infra Pvt. Ltd. before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 107/05/2024

for delivery of Judgment/Order

The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.

3
Stage 207/02/2024

Hearing

The court issued a procedural order referring to the orders passed in Appeal No. 545/2022.

4
Stage 329/01/2024

Hearing

The Tribunal directed that the appeal be listed for hearing on 07.02.2024 and referred to a previous order passed in Appeal No. 545/2022.

5
Stage 430/10/2023

Hearing

No text available.

6
Stage 518/09/2023

Hearing

The Tribunal has scheduled the appeal for a hearing on 30.10.2023 and referred to a previous order passed in Appeal No. 545/2022.

7
Stage 628/07/2023

Hearing

No text available.

8
Stage 717/05/2023

Hearing

No text available.

9
Stage 813/04/2023

Hearing

This is a procedural order noting that the orders for Appeal No. 547/2022 are to be found in the order passed for Appeal No. 545/2022.

10
Stage 902/03/2023

Hearing

The Tribunal has ordered the appeal to be listed on 13.04.2023 along with similar matters, referencing a previous order passed in a related case.

11
Stage 1013/02/2023

Hearing

The Tribunal has scheduled the appeal for a hearing on March 2, 2023, and directed reference to a previous order passed in Appeal No. 545 of 2022.

12
Stage 1121/12/2022

Exchange of pleadings

The Tribunal granted the appellant a final opportunity to file a replication/rejoinder against the respondent's reply and scheduled the matter for hearing on 13.02.2023.

13
Stage 1225/11/2022

Exchange of pleadings

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 21.12.2022.

14
Stage 1301/11/2022

Exchange of pleadings

The Tribunal directed the appellant to file a replication to the respondent's reply and serve a soft copy via email within one week, with the matter listed for hearing on 25.11.2022.

15
Stage 1417/10/2022

to file objections and its reply

The Tribunal granted the appellant permission to file a replication against the respondent's reply and scheduled the matter for further orders on 01.11.2022.

16
Stage 1514/09/2022

Notice

The Tribunal directed the respondent's counsel to register on the e-portal and granted ten days to file objections to the grounds of appeal.

17
Stage 1618/08/2022

Admission

The Tribunal issued notice to the respondent and outlined specific procedural requirements for service of appeal documents via speed-post and email, scheduling the next hearing for 14.09.2022.

18
Stage 17Final Ruling Order

Tribunal Order #0901126048202022-07-05-2024

The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav
  • Suyesh Pradhan
  • Asif Anees

Respondent Advocate(s)

  • Ajai Kumar Gupta
  • Rishindra Vikram Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126048202022-07-05-2024

The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to examine the allottees' right to a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.

TathyaGrid RERA Intelligence AI

Need to research all rulings for rudra buildwell infra pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →