up_reraStatus: Completed
CASE ID: 0901126048182022

Appellant / Complainant

Ranjana Gupta, Shalini Gupta

VS

Respondent

Rudra Buildwell Infra Pvt. Ltd.

Developer Firm

rudra buildwell infra pvt. ltd.

Disputed Amount

34,53,341

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126048182022 by Ranjana Gupta, Shalini Gupta against Rudra Buildwell Infra Pvt. Ltd. before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 107/05/2024

for delivery of Judgment/Order

The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to the Authority to properly examine the allottees' right to seek a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.

3
Stage 207/02/2024

Hearing

The Tribunal reserved judgment after finding that the Regulatory Authority likely misread facts regarding the project's completion, possession period, and the status of the Occupancy Certificate (OC/CC) in relation to the Builder-Buyer Agreement.

4
Stage 329/01/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled a bunch of appeals (Sl. 42 to 53) for hearing on 07.02.2024, noting that no further adjournments will be permitted on the next date.

5
Stage 430/10/2023

Hearing

No text available.

6
Stage 518/09/2023

Hearing

The Tribunal granted an adjournment at the request of the appellant's counsel to allow for the correction and uploading of properly described annexures and to prepare arguments regarding refund demands under Section 18(1) of the Act.

7
Stage 628/07/2023

Hearing

No text available.

8
Stage 717/05/2023

Hearing

No text available.

9
Stage 813/04/2023

Hearing

The Tribunal directed the appellant to file clear or typed copies of unreadable annexures within one week and scheduled the next hearing for 17.05.2023.

10
Stage 902/03/2023

Hearing

The Tribunal adjourned the proceedings due to the absence of the respondent's counsel and scheduled the matter for hearing on 13.04.2023 along with similar appeals.

11
Stage 1013/02/2023

Hearing

The Tribunal granted a one-week extension to the respondent's counsel for preparation and rescheduled the hearing for this bunch of appeals to 02.03.2023.

12
Stage 1121/12/2022

Exchange of pleadings

The Tribunal granted the appellant a final opportunity to file a replication/rejoinder against the respondent's reply and scheduled the next hearing for 13.02.2023.

13
Stage 1225/11/2022

Exchange of pleadings

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the appeal for hearing on 21.12.2022.

14
Stage 1301/11/2022

Exchange of pleadings

The Tribunal directed the appellant to file a replication to the respondent's reply and serve it via email within one week, with the matter listed for hearing on 25.11.2022.

15
Stage 1417/10/2022

to file objections and its reply

The Tribunal granted the appellant permission to file a replication to the respondent's reply and scheduled the matter for further orders on 01.11.2022.

16
Stage 1514/09/2022

Notice

The Tribunal directed the respondent's counsel to register on the e-portal and granted ten days to file objections to the grounds of appeal, with a subsequent timeline set for the appellant's reply.

17
Stage 1618/08/2022

Admission

The Tribunal issued a notice to the respondent and established a procedural timeline for service of appeal documents and the filing of objections and replies.

18
Stage 17Final Ruling Order

Tribunal Order #0901126048182022-07-05-2024

The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to the Authority to properly examine the allottees' right to seek a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.

19
Stage 18Interim Order

Tribunal Order #0901126048182022-07-02-2024

The Tribunal reserved judgment after finding that the Regulatory Authority likely misread facts regarding the project's completion, possession period, and the status of the Occupancy Certificate (OC/CC) in relation to the Builder-Buyer Agreement.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to the Authority to properly examine the allottees' right to seek a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to the Authority to properly examine the allottees' right to seek a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav
  • Suyesh Pradhan

Respondent Advocate(s)

  • Ajai Kumar Gupta
  • Rishindra Vikram Singh
  • Asif Anees

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126048182022-07-05-2024

The Appellate Tribunal set aside the Regulatory Authority's order and remanded the matter back to the Authority to properly examine the allottees' right to seek a refund under Sections 18(1) and 19(4) of the RERA Act due to the developer's failure to provide possession within the stipulated timeline.

INTERIM_ORDEROrder ID: 0901126048182022-07-02-2024

The Tribunal reserved judgment after finding that the Regulatory Authority likely misread facts regarding the project's completion, possession period, and the status of the Occupancy Certificate (OC/CC) in relation to the Builder-Buyer Agreement.

TathyaGrid RERA Intelligence AI

Need to research all rulings for rudra buildwell infra pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →