Appellant / Complainant
Shishu Pal Singh
Respondent
Gaursons Hi-Tech Infrastructure Private Limited
gaursons hi-tech infrastructure private limited
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126047882023 by Shishu Pal Singh against Gaursons Hi-Tech Infrastructure Private Limited before up_rera.
Re-Hearing
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to insufficient explanation and subsequently dismissed the appeal.
Re-Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for May 19, 2025, noting that no further adjournments will be permitted.
Re-Hearing
The appeal was adjourned to 28.04.2025 because lawyers were abstaining from judicial work following a resolution by the Real Estate Bar Association, Lucknow.
Re-Hearing
The Tribunal adjourned the appeal to 28.03.2025 because the learned counsels are abstaining from judicial work following a resolution by the U.P. Bar Council.
Re-Hearing
The Tribunal granted a request to list the appeal for orders or hearing on 25.02.2025.
For Order
Upon the joint request of both parties, the Tribunal has adjourned the appeal to be listed for orders or hearing on 04.02.2025.
Delay condonation
The Tribunal heard arguments regarding an application for condonation of delay and has reserved its order.
Delay condonation
The Tribunal noted the exchange of pleadings and scheduled the defective appeal for consideration regarding the application for condonation of delay on 31.07.2024.
Delay condonation
The Tribunal has granted a request to list the defective appeal for consideration of an application for condonation of delay on 01.05.2024.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the hearing for the application for condonation of delay on 29.03.2024.
Delay condonation
The Tribunal granted the respondent a 10-day extension to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for February 23, 2024.
Delay condonation
The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and scheduled the matter for hearing on 16.01.2024.
Tribunal Order #0901126047882023-19-05-2025
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to insufficient explanation and subsequently dismissed the appeal.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to insufficient explanation and subsequently dismissed the appeal. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to insufficient explanation and subsequently dismissed the appeal.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
Respondent Advocate(s)
- Samrat Vaish
- Mohit Yadav
- Sangya Negi
Official RERA Tribunal Orders (1)
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to insufficient explanation and subsequently dismissed the appeal.
Need to research all rulings for gaursons hi-tech infrastructure private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.