Appellant / Complainant
Gaursons Hi-Tech Infrastructure Private Limited
Respondent
Surinder Singh Khullar
gaursons hi-tech infrastructure private limited
₹35,65,000
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126046142024 by Gaursons Hi-Tech Infrastructure Private Limited against Surinder Singh Khullar before up_rera.
for delivery of Judgment/Order
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the developer's appeal, upholding the Authority's order that requires the payment of delay interest to the allottee from 04.08.2022 until physical possession is handed over.
Hearing
The Tribunal heard arguments from both the appellant's counsel and the respondent in person, subsequently reserving the judgment for future pronouncement.
Hearing
The Tribunal noted that the matter is part-heard with another Bench and ordered the appeal to be listed on 27.11.2025 before the appropriate Bench.
Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for 10.11.2025.
Hearing
The Tribunal heard arguments from the appellant's counsel and the respondent in person, subsequently adjourning the appeal to 13.10.2025.
Hearing
The Tribunal granted an adjournment request from the respondent's counsel and rescheduled the appeal for hearing/orders on 16.09.2025.
Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the appeal for hearing on 28.08.2025.
Hearing
The Tribunal granted the appellant seven days to file a rejoinder affidavit and scheduled the appeal for hearing on 14.08.2025.
for delivery of Judgment/Order
The Tribunal allowed the appellant's application to condone an 11-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.
Delay condonation
The Tribunal heard arguments regarding the appellant's application for condonation of delay and reserved its order.
Delay condonation
The Tribunal granted the appellant 10 days to file a rejoinder affidavit to the respondent's objections and scheduled the next hearing for April 7, 2025.
Delay condonation
The court noted that the case was wrongly listed and directed it to be heard on its previously scheduled date of 28.02.2025.
Delay condonation
The Tribunal has granted a request to list the defective appeal for consideration of an application for delay and a subsequent hearing on 28.02.2025.
Delay condonation
The Tribunal issued notice to the respondent regarding the appellant's application for condonation of delay and directed the parties to exchange objections and replies via email before the next hearing on 07.02.2025.
Tribunal Order #0901126046142024-26-02-2026
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the developer's appeal, upholding the Authority's order that requires the payment of delay interest to the allottee from 04.08.2022 until physical possession is handed over.
Tribunal Order #0901126046142024-04-07-2025
The Tribunal allowed the appellant's application to condone an 11-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Disposal & Final Award Ruling
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the developer's appeal, upholding the Authority's order that requires the payment of delay interest to the allottee from 04.08.2022 until physical possession is handed over. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the developer's appeal, upholding the Authority's order that requires the payment of delay interest to the allottee from 04.08.2022 until physical possession is handed over.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR + 1%
Interest Period
from 04.08.2022 to the date of receipt of OC/CC or date of giving physical possession, whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Samrat Vaish
Respondent Advocate(s)
- Respondent In-Person
- In Person
Official RERA Tribunal Orders (2)
The Uttar Pradesh Real Estate Appellate Tribunal dismissed the developer's appeal, upholding the Authority's order that requires the payment of delay interest to the allottee from 04.08.2022 until physical possession is handed over.
The Tribunal allowed the appellant's application to condone an 11-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal.
Need to research all rulings for gaursons hi-tech infrastructure private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.