up_reraStatus: Completed
CASE ID: 0901126042172021

Appellant / Complainant

Lallan Mishra

VS

Respondent

Shinecity Infraproject Private Limited, U.P. Real Estate Regulatory Authority Lucknow

Developer Firm

shinecity infraproject private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Jurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

7 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126042172021 by Lallan Mishra against Shinecity Infraproject Private Limited, U.P. Real Estate Regulatory Authority Lucknow before up_rera.

Jurisdiction & Maintainability
2
Stage 107/03/2022

Delay condonation

The Tribunal dismissed the appeal and the underlying complaint because the respondent's project was not registered under Section 3 of the Act of 2016, rendering the matter non-maintainable.

3
Stage 204/01/2022

Notice

The Tribunal granted an adjournment requested by the appellant and directed them to file a separate application for condonation of delay via email and the e-portal.

4
Stage 329/11/2021

Notice

The Tribunal issued a notice to the respondent via registered post and email and directed the applicant to take necessary steps within a week. The case is scheduled for further orders on 04.01.2022.

5
Stage 408/11/2021

Delay condonation

The Tribunal issued a notice to the respondent via registered post, Dasti, and e-mail and scheduled the case for further orders on 29.11.2021.

6
Stage 5Final Ruling Order

Tribunal Order #0901126042172021-07-03-2022

The Tribunal dismissed the appeal and the underlying complaint because the respondent's project was not registered under Section 3 of the Act of 2016, rendering the matter non-maintainable.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal and the underlying complaint because the respondent's project was not registered under Section 3 of the Act of 2016, rendering the matter non-maintainable. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal and the underlying complaint because the respondent's project was not registered under Section 3 of the Act of 2016, rendering the matter non-maintainable.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra
  • Krishna Kumar Singh

Respondent Advocate(s)

  • | Versus INFRAPROJECT PRIVATE LIMITEDSHINECITY INFRAPROJECT PRIVATE LIMITED Counsel for Appellant | .............Respondent |

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126042172021-07-03-2022

The Tribunal dismissed the appeal and the underlying complaint because the respondent's project was not registered under Section 3 of the Act of 2016, rendering the matter non-maintainable.

TathyaGrid RERA Intelligence AI

Need to research all rulings for shinecity infraproject private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →