Appellant / Complainant
Rekha Pal
Respondent
U.P. Real Estate Regulatory Authority Lucknow, Shinecity Infraproject Private Limited
shinecity infraproject private limited
₹15,42,800
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126035372021 by Rekha Pal against U.P. Real Estate Regulatory Authority Lucknow, Shinecity Infraproject Private Limited before up_rera.
for delivery of Judgment/Order
The Tribunal set aside the Regulatory Authority's order and directed Respondent No. 1 to refund the appellant's entire deposited amount with interest at a rate of MCLR+1% per annum from the date of deposit until actual refund.
Hearing
The Tribunal reserved its judgment regarding the appellant's challenge to a Regulatory Authority order, seeking a refund of deposited amounts with interest due to the respondent's failure to honor post-dated cheques and the lack of a registered conveyance deed.
Hearing
The matter was listed but could not be heard due to lack of time; the court ordered the case to be put up on 06.07.2023.
Hearing
The Tribunal granted a request by the appellant's counsel to list the appeal for orders on 15.05.2023.
Hearing
The Tribunal granted the appellant's counsel additional time to prepare the brief and rescheduled the hearing for April 19, 2023.
Hearing
At the request of the appellant's counsel, the tribunal has rescheduled the appeal for orders or hearing to March 29, 2023.
Ex-Parte
The Tribunal adjourned the matter due to lack of time and rescheduled the appeal for hearing on 01.03.2023.
Ex-Parte
The Tribunal adjourned the appeal due to the absence of the respondent and scheduled the matter for an ex-parte hearing on 24.01.2023.
Ex-Parte
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for December 15, 2022.
Exchange of pleadings
The Tribunal noted the presence of the appellant's counsel and the absence of the respondent, subsequently adjourning the matter to 18.11.2022 for further orders.
Further Order
The Tribunal granted the respondent one final opportunity to file a reply to the grounds of appeal and scheduled the matter for further orders on 17.10.2022.
Further Order
The Tribunal condoned the 90-day delay in filing the appeal due to the COVID-19 pandemic relaxation and directed the respondent to file a reply before the next hearing on 29.08.2022.
Further Order
The Tribunal directed the respondent to file objections to the application for condonation of delay within two weeks and ordered parties to exchange pleadings via email before the next hearing on 19.07.2022.
Delay condonation
The Tribunal noted that the applicant published notices in newspapers not specified in the previous order and directed the applicant to take steps to publish notice in approved newspapers within 15 days.
Notice
The Tribunal granted the applicant one week's extension to file an affidavit of service for notice publication and scheduled the defective appeal for hearing on 01.04.2022.
Notice
The Tribunal granted the appellant additional time to publish a notice in local newspapers due to COVID-19 delays and scheduled the defective appeal for hearing on 16.03.2022.
Further Order
The Tribunal directed the appellant to publish a notice in a Lucknow-based newspaper (Amar Ujala, Dainik Jagran, or Hindustan Times) within 15 days and scheduled the next hearing for January 12, 2022.
Delay condonation
The Tribunal granted a request from the appellant's counsel to list the defective appeal on 10.11.2021.
Delay condonation
The Tribunal granted the appellant one week to file an application for service of notice via an alternative mode after the initial notice was returned unserved, and rescheduled the matter for 01.11.2021.
Delay condonation
The Tribunal issued notice on the application for condonation of delay and directed the parties to exchange documents via speed post and email before the next hearing on 08.10.2021.
Tribunal Order #0901126035372021-17-07-2023
The Tribunal set aside the Regulatory Authority's order and directed Respondent No. 1 to refund the appellant's entire deposited amount with interest at a rate of MCLR+1% per annum from the date of deposit until actual refund.
Tribunal Order #0901126035372021-06-07-2023
The Tribunal reserved its judgment regarding the appellant's challenge to a Regulatory Authority order, seeking a refund of deposited amounts with interest due to the respondent's failure to honor post-dated cheques and the lack of a registered conveyance deed.
Tribunal Order #0901126035372021-19-07-2022
The Tribunal condoned the 90-day delay in filing the appeal due to the COVID-19 pandemic relaxation and directed the respondent to file a reply before the next hearing on 29.08.2022.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the Regulatory Authority's order and directed Respondent No. 1 to refund the appellant's entire deposited amount with interest at a rate of MCLR+1% per annum from the date of deposit until actual refund. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% per annum.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the Regulatory Authority's order and directed Respondent No. 1 to refund the appellant's entire deposited amount with interest at a rate of MCLR+1% per annum from the date of deposit until actual refund.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1% per annum
Interest Period
from the date of deposit of the respective amount till the date of actual refund
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Saurabh Misra
- Krishna Kumar Singh
- Gautam Johri
Respondent Advocate(s)
- Krishna Kumar Singh
Official RERA Tribunal Orders (3)
The Tribunal set aside the Regulatory Authority's order and directed Respondent No. 1 to refund the appellant's entire deposited amount with interest at a rate of MCLR+1% per annum from the date of deposit until actual refund.
The Tribunal reserved its judgment regarding the appellant's challenge to a Regulatory Authority order, seeking a refund of deposited amounts with interest due to the respondent's failure to honor post-dated cheques and the lack of a registered conveyance deed.
The Tribunal condoned the 90-day delay in filing the appeal due to the COVID-19 pandemic relaxation and directed the respondent to file a reply before the next hearing on 29.08.2022.
Need to research all rulings for shinecity infraproject private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.