Appellant / Complainant
Arvind Kumar
Respondent
Aftek Developers Private Limited
aftek developers private limited
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126041612021 by Arvind Kumar against Aftek Developers Private Limited before up_rera.
Delay condonation
The Tribunal dismissed the appeal as withdrawn after the appellant acknowledged that the RERA's existing order—granting a refund with interest if possession is not provided by a specific deadline—had come into operation.
Delay condonation
The Tribunal granted the appellant three days to upload and file a physical copy of their reply to the respondent's objections and scheduled the matter for hearing on July 20, 2022.
Delay condonation
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for hearing on July 12, 2022.
Delay condonation
The Tribunal granted the respondent one week to file objections to the condonation application and grounds of appeal, with subsequent instructions for the applicant to reply and both parties to upload pleadings to the e-portal.
Delay condonation
The Tribunal directed the respondent to file objections within two days and the appellant to reply within a week, scheduling the case for consideration of delay condonation on 02.05.2022.
Delay condonation
The Tribunal granted the respondent one week to file objections and a vakalatnama, directing that pleadings be uploaded to the e-portal and scheduling the next hearing for April 13, 2022.
Delay condonation
The Tribunal granted the respondent two weeks to file a Vakalatnama and objections regarding the condonation of delay, with subsequent instructions for the exchange of replies and electronic filing before the next hearing on 25.03.2022.
Defect Removal
The Tribunal directed the appellant to remove registry defects within one week and ordered notice to be issued to the respondent via registered post and email.
Tribunal Order #0901126041612021-20-07-2022
The Tribunal dismissed the appeal as withdrawn after the appellant acknowledged that the RERA's existing order—granting a refund with interest if possession is not provided by a specific deadline—had come into operation.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal as withdrawn after the appellant acknowledged that the RERA's existing order—granting a refund with interest if possession is not provided by a specific deadline—had come into operation. Awarded in favor of Respondent. Awarded interest rate: SBI's MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal as withdrawn after the appellant acknowledged that the RERA's existing order—granting a refund with interest if possession is not provided by a specific deadline—had come into operation.
Ruling Awarded To
Respondent
Awarded Interest Rate
SBI's MCLR+1%
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Anand Kumar Bajpai
Respondent Advocate(s)
- Anurag Singh
Official RERA Tribunal Orders (1)
The Tribunal dismissed the appeal as withdrawn after the appellant acknowledged that the RERA's existing order—granting a refund with interest if possession is not provided by a specific deadline—had come into operation.
Need to research all rulings for aftek developers private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.