Appellant / Complainant
Man Singh
Respondent
Paarth Infrabuild Private Ltd
paarth infrabuild private ltd
₹1,47,864
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126037702025 by Man Singh against Paarth Infrabuild Private Ltd before up_rera.
Execution
The Tribunal disposed of the Execution Application as the respondent has satisfied the judgment and decree, with a directive to provide the TDS deduction certificate to the appellant within seven days.
Execution
The Tribunal granted a request from the respondent's counsel to adjourn the matter, rescheduling the hearing for March 31, 2026.
Execution
The judgment debtor has made a partial payment of Rs. 5,00,000/- via cheque, with an undertaking to pay the remaining balance within ten days.
Execution
The Tribunal directed the respondent to satisfy the balance payment pursuant to the existing judgment and decree and to file an affidavit of compliance by the next hearing date on 16.03.2026.
Execution
At the request of the respondent's counsel, the matter is adjourned to 13.02.2026 to monitor compliance with the decree.
Execution
The Tribunal noted the respondent's submission that the principal amount has been satisfied and the interest will be paid shortly, subsequently listing the matter for hearing on 06.02.2026.
Execution
The respondent (Paarth Infrabuild Private Ltd) handed over two cheques totaling Rs. 16,43,084 towards the satisfaction of the principal amount due to the appellant, with interest to be settled by the next hearing.
Execution
The Tribunal granted the respondent (judgment debtor) additional time to satisfy the decree and directed the filing of an affidavit of compliance.
Execution
The Tribunal granted the respondent 10 days to file an objection and scheduled the matter for hearing on November 28, 2025.
Execution
The Tribunal issued a notice to the respondent regarding Execution Application (EA) No. 45 of 2025 and outlined the procedural timeline for service of notice, filing of objections, and replies.
Tribunal Order #0901126037702025-16-03-2026
The judgment debtor has made a partial payment of Rs. 5,00,000/- via cheque, with an undertaking to pay the remaining balance within ten days.
Tribunal Order #0901126037702025-13-02-2026
The Tribunal directed the respondent to satisfy the balance payment pursuant to the existing judgment and decree and to file an affidavit of compliance by the next hearing date on 16.03.2026.
Tribunal Order #0901126037702025-12-12-2025
The respondent (Paarth Infrabuild Private Ltd) handed over two cheques totaling Rs. 16,43,084 towards the satisfaction of the principal amount due to the appellant, with interest to be settled by the next hearing.
Tribunal Order #0901126037702025-31-03-2026
The Tribunal disposed of the Execution Application as the respondent has satisfied the judgment and decree, with a directive to provide the TDS deduction certificate to the appellant within seven days.
Tribunal Order #0901126037702025-28-11-2025
The Tribunal granted the respondent (judgment debtor) additional time to satisfy the decree and directed the filing of an affidavit of compliance.
Tribunal Disposal & Final Award Ruling
The Tribunal disposed of the Execution Application as the respondent has satisfied the judgment and decree, with a directive to provide the TDS deduction certificate to the appellant within seven days. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal disposed of the Execution Application as the respondent has satisfied the judgment and decree, with a directive to provide the TDS deduction certificate to the appellant within seven days.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rachit Sondhi
Respondent Advocate(s)
- Saurabh Mishra
Official RERA Tribunal Orders (5)
The judgment debtor has made a partial payment of Rs. 5,00,000/- via cheque, with an undertaking to pay the remaining balance within ten days.
The Tribunal directed the respondent to satisfy the balance payment pursuant to the existing judgment and decree and to file an affidavit of compliance by the next hearing date on 16.03.2026.
The respondent (Paarth Infrabuild Private Ltd) handed over two cheques totaling Rs. 16,43,084 towards the satisfaction of the principal amount due to the appellant, with interest to be settled by the next hearing.
The Tribunal disposed of the Execution Application as the respondent has satisfied the judgment and decree, with a directive to provide the TDS deduction certificate to the appellant within seven days.
The Tribunal granted the respondent (judgment debtor) additional time to satisfy the decree and directed the filing of an affidavit of compliance.