up_reraStatus: Completed
CASE ID: 0901126037702025

Appellant / Complainant

Man Singh

VS

Respondent

Paarth Infrabuild Private Ltd

Developer Firm

paarth infrabuild private ltd

Disputed Amount

1,47,864

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126037702025 by Man Singh against Paarth Infrabuild Private Ltd before up_rera.

Non-Compliance & Execution
2
Stage 131/03/2026

Execution

The Tribunal disposed of the Execution Application as the respondent has satisfied the judgment and decree, with a directive to provide the TDS deduction certificate to the appellant within seven days.

3
Stage 227/03/2026

Execution

No text available.

4
Stage 326/03/2026

Execution

The Tribunal granted a request from the respondent's counsel to adjourn the matter, rescheduling the hearing for March 31, 2026.

5
Stage 416/03/2026

Execution

The judgment debtor has made a partial payment of Rs. 5,00,000/- via cheque, with an undertaking to pay the remaining balance within ten days.

6
Stage 513/02/2026

Execution

The Tribunal directed the respondent to satisfy the balance payment pursuant to the existing judgment and decree and to file an affidavit of compliance by the next hearing date on 16.03.2026.

7
Stage 606/02/2026

Execution

At the request of the respondent's counsel, the matter is adjourned to 13.02.2026 to monitor compliance with the decree.

8
Stage 721/01/2026

Execution

The Tribunal noted the respondent's submission that the principal amount has been satisfied and the interest will be paid shortly, subsequently listing the matter for hearing on 06.02.2026.

9
Stage 812/12/2025

Execution

The respondent (Paarth Infrabuild Private Ltd) handed over two cheques totaling Rs. 16,43,084 towards the satisfaction of the principal amount due to the appellant, with interest to be settled by the next hearing.

10
Stage 928/11/2025

Execution

The Tribunal granted the respondent (judgment debtor) additional time to satisfy the decree and directed the filing of an affidavit of compliance.

11
Stage 1007/11/2025

Execution

The Tribunal granted the respondent 10 days to file an objection and scheduled the matter for hearing on November 28, 2025.

12
Stage 1114/10/2025

Execution

The Tribunal issued a notice to the respondent regarding Execution Application (EA) No. 45 of 2025 and outlined the procedural timeline for service of notice, filing of objections, and replies.

13
Stage 12Interim Order

Tribunal Order #0901126037702025-16-03-2026

The judgment debtor has made a partial payment of Rs. 5,00,000/- via cheque, with an undertaking to pay the remaining balance within ten days.

14
Stage 13Interim Order

Tribunal Order #0901126037702025-13-02-2026

The Tribunal directed the respondent to satisfy the balance payment pursuant to the existing judgment and decree and to file an affidavit of compliance by the next hearing date on 16.03.2026.

15
Stage 14Interim Order

Tribunal Order #0901126037702025-12-12-2025

The respondent (Paarth Infrabuild Private Ltd) handed over two cheques totaling Rs. 16,43,084 towards the satisfaction of the principal amount due to the appellant, with interest to be settled by the next hearing.

16
Stage 15Final Ruling Order

Tribunal Order #0901126037702025-31-03-2026

The Tribunal disposed of the Execution Application as the respondent has satisfied the judgment and decree, with a directive to provide the TDS deduction certificate to the appellant within seven days.

17
Stage 16Interim Order

Tribunal Order #0901126037702025-28-11-2025

The Tribunal granted the respondent (judgment debtor) additional time to satisfy the decree and directed the filing of an affidavit of compliance.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal disposed of the Execution Application as the respondent has satisfied the judgment and decree, with a directive to provide the TDS deduction certificate to the appellant within seven days. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal disposed of the Execution Application as the respondent has satisfied the judgment and decree, with a directive to provide the TDS deduction certificate to the appellant within seven days.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rachit Sondhi

Respondent Advocate(s)

  • Saurabh Mishra

Official RERA Tribunal Orders (5)

INTERIM_ORDEROrder ID: 0901126037702025-16-03-2026

The judgment debtor has made a partial payment of Rs. 5,00,000/- via cheque, with an undertaking to pay the remaining balance within ten days.

INTERIM_ORDEROrder ID: 0901126037702025-13-02-2026

The Tribunal directed the respondent to satisfy the balance payment pursuant to the existing judgment and decree and to file an affidavit of compliance by the next hearing date on 16.03.2026.

INTERIM_ORDEROrder ID: 0901126037702025-12-12-2025

The respondent (Paarth Infrabuild Private Ltd) handed over two cheques totaling Rs. 16,43,084 towards the satisfaction of the principal amount due to the appellant, with interest to be settled by the next hearing.

FINAL_ORDEROrder ID: 0901126037702025-31-03-2026

The Tribunal disposed of the Execution Application as the respondent has satisfied the judgment and decree, with a directive to provide the TDS deduction certificate to the appellant within seven days.

INTERIM_ORDEROrder ID: 0901126037702025-28-11-2025

The Tribunal granted the respondent (judgment debtor) additional time to satisfy the decree and directed the filing of an affidavit of compliance.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paarth infrabuild private ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →