Appellant / Complainant
Alok Kumar
Respondent
Paarth Infrabuild Private Ltd
paarth infrabuild private ltd
₹5,00,000
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126028522021 by Alok Kumar against Paarth Infrabuild Private Ltd before up_rera.
for delivery of Judgment/Order
The Tribunal dismissed the appeal, ruling that under Section 18 of the RERA Act 2016, an allottee who chooses to stay in a project is entitled only to prescribed interest for delayed possession and cannot seek additional 'compensation' from the Adjudicating Officer.
Hearing
The Tribunal granted a request from the counsel for both parties to reschedule the hearing of Appeal-525/2021 to 04.01.2023.
Hearing
The Tribunal adjourned the appeal to 02.12.2022 due to the absence of the respondent's counsel and issued a warning that the matter will be heard ex-parte if no one appears on the next date.
Hearing
This text represents the header/caption of an appeal filed by Alok Kumar against Paarth Infrabuild Private Ltd before the U.P. Real Estate Appellate Tribunal, but it does not contain the substantive ruling or directive of the order.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the hearing for 09.09.2022.
Hearing
The Tribunal directed the respondent to appear at the next hearing through a Director or Authorized Representative empowered to make final decisions regarding a potential settlement concerning compensation for delayed possession.
Hearing
The Tribunal directed the respondent to file a list of dates and events within 10 days and scheduled the appeal for hearing on July 5, 2022.
Hearing
The Tribunal directed both parties to file and exchange a list of dates and events and scheduled the matter for further hearing on 15.04.2022.
Final Hearing
The Tribunal directed the respondent to file an affidavit within 10 days providing the NOCs annexed to their CC/OC application to verify the legality of the possession offer made to the appellant.
Final Hearing
The Tribunal noted that pleadings have been exchanged and adjourned the matter to 15.12.2021 for final hearing before Bench No. 1.
Hearing on Appeal
The Tribunal summoned the record from the Adjudicating Officer and scheduled the appeal for a final hearing on 03.12.2021 following the submission of maps, sanctioned plans, and replies by the appellant.
Hearing on Appeal
The Tribunal directed the appellant to produce evidence regarding plan deviations and compensation claims, while ordering the Registry to summon the original adjudication records for the next hearing on 15.11.2021.
Hearing on Appeal
The Tribunal adjourned the case due to the respondent's counsel's absence and imposed a cost of Rs. 1,000/- payable to the appellant for the inconvenience caused.
Delay condonation
The Tribunal condoned the delay in filing the appeal, ruling that since the appeal was uploaded on the e-portal within the prescribed time, it is treated as filed within the period of limitation. The Registry is directed to convert the defective appeal into a regular appeal.
Delay condonation
The Tribunal issued notice on the application for condonation of delay and directed the parties to exchange pleadings via email and upload them to the e-portal before the next hearing on 31.08.2021.
Tribunal Order #0901126028522021-30-05-2023
The Tribunal dismissed the appeal, ruling that under Section 18 of the RERA Act 2016, an allottee who chooses to stay in a project is entitled only to prescribed interest for delayed possession and cannot seek additional 'compensation' from the Adjudicating Officer.
Tribunal Order #0901126028522021-18-10-2021
The Tribunal directed the appellant to produce evidence regarding plan deviations and compensation claims, while ordering the Registry to summon the original adjudication records for the next hearing on 15.11.2021.
Tribunal Order #0901126028522021-24-09-2021
The Tribunal adjourned the case due to the respondent's counsel's absence and imposed a cost of Rs. 1,000/- payable to the appellant for the inconvenience caused.
Tribunal Order #0901126028522021-31-08-2021
The Tribunal condoned the delay in filing the appeal, ruling that since the appeal was uploaded on the e-portal within the prescribed time, it is treated as filed within the period of limitation. The Registry is directed to convert the defective appeal into a regular appeal.
Tribunal Order #0901126028522021-05-07-2022
The Tribunal directed the respondent to appear at the next hearing through a Director or Authorized Representative empowered to make final decisions regarding a potential settlement concerning compensation for delayed possession.
Tribunal Order #0901126028522021-15-12-2021
The Tribunal directed the respondent to file an affidavit within 10 days providing the NOCs annexed to their CC/OC application to verify the legality of the possession offer made to the appellant.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal, ruling that under Section 18 of the RERA Act 2016, an allottee who chooses to stay in a project is entitled only to prescribed interest for delayed possession and cannot seek additional 'compensation' from the Adjudicating Officer. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal, ruling that under Section 18 of the RERA Act 2016, an allottee who chooses to stay in a project is entitled only to prescribed interest for delayed possession and cannot seek additional 'compensation' from the Adjudicating Officer.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Anurag Arora
Respondent Advocate(s)
- Rajiv Shukla
- Suyash Bajpai
- Anuj Garg
Official RERA Tribunal Orders (6)
The Tribunal dismissed the appeal, ruling that under Section 18 of the RERA Act 2016, an allottee who chooses to stay in a project is entitled only to prescribed interest for delayed possession and cannot seek additional 'compensation' from the Adjudicating Officer.
The Tribunal directed the appellant to produce evidence regarding plan deviations and compensation claims, while ordering the Registry to summon the original adjudication records for the next hearing on 15.11.2021.
The Tribunal adjourned the case due to the respondent's counsel's absence and imposed a cost of Rs. 1,000/- payable to the appellant for the inconvenience caused.
The Tribunal condoned the delay in filing the appeal, ruling that since the appeal was uploaded on the e-portal within the prescribed time, it is treated as filed within the period of limitation. The Registry is directed to convert the defective appeal into a regular appeal.
The Tribunal directed the respondent to appear at the next hearing through a Director or Authorized Representative empowered to make final decisions regarding a potential settlement concerning compensation for delayed possession.
The Tribunal directed the respondent to file an affidavit within 10 days providing the NOCs annexed to their CC/OC application to verify the legality of the possession offer made to the appellant.