Appellant / Complainant
Uppal Chadha Hi-Tech Developers Pvt. Ltd
Respondent
Ajay Sharma, Neeti Sharma
uppal chadha hi-tech developers pvt. ltd
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126035302025 by Uppal Chadha Hi-Tech Developers Pvt. Ltd against Ajay Sharma, Neeti Sharma before up_rera.
For Order
The Tribunal directed the transfer of funds deposited by the appellant promoter under Section 43(5) of the Act to the U.P. Real Estate Regulatory Authority for disbursement in pending execution proceedings.
Tribunal Order #0901126035302025-16-10-2025
The Tribunal directed the transfer of funds deposited by the appellant promoter under Section 43(5) of the Act to the U.P. Real Estate Regulatory Authority for disbursement in pending execution proceedings.
Tribunal Disposal & Final Award Ruling
The Tribunal directed the transfer of funds deposited by the appellant promoter under Section 43(5) of the Act to the U.P. Real Estate Regulatory Authority for disbursement in pending execution proceedings. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal directed the transfer of funds deposited by the appellant promoter under Section 43(5) of the Act to the U.P. Real Estate Regulatory Authority for disbursement in pending execution proceedings.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Official RERA Tribunal Orders (1)
The Tribunal directed the transfer of funds deposited by the appellant promoter under Section 43(5) of the Act to the U.P. Real Estate Regulatory Authority for disbursement in pending execution proceedings.