Appellant / Complainant
Uppal Chadha Hi-Tech Developers Pvt. Ltd
Respondent
Shashi Bhatnagar, Amitabh Sahai
uppal chadha hi-tech developers pvt. ltd
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126021422025 by Uppal Chadha Hi-Tech Developers Pvt. Ltd against Shashi Bhatnagar, Amitabh Sahai before up_rera.
For Order
The Tribunal granted a review application to rectify a typographical error in its previous judgment, amending the interest period to be payable until the date of OC/CC or offer of possession, whichever is earlier.
For Order
The Tribunal notes that the review petition was incorrectly listed before a Larger Bench and directs it to be listed for hearing before Bench No. 1 on 18.09.2025.
For Order
The Tribunal granted a request from the appellant's counsel to reschedule the hearing of the appeal to 16.09.2025.
For Order
The Tribunal granted a final one-week extension for the filing of objections, noting that failure to do so will result in the review petition being heard ex-parte against the respondent.
For Order
The Tribunal confirmed sufficient service of notice on the appellant-judgment debtor and granted the respondent ten days to file objections, with the matter scheduled for hearing on 18.08.2025.
For Order
The Tribunal has directed the promoter to file objections to the review petition by the next hearing date and scheduled the case for orders on 04.08.2025.
For Order
The Tribunal issued a notice to the respondents regarding the review application and outlined the procedural timeline for service of notice, filing of objections, and subsequent replies.
Tribunal Order #0901126021422025-18-09-2025
The Tribunal granted a review application to rectify a typographical error in its previous judgment, amending the interest period to be payable until the date of OC/CC or offer of possession, whichever is earlier.
Tribunal Disposal & Final Award Ruling
The Tribunal granted a review application to rectify a typographical error in its previous judgment, amending the interest period to be payable until the date of OC/CC or offer of possession, whichever is earlier. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal granted a review application to rectify a typographical error in its previous judgment, amending the interest period to be payable until the date of OC/CC or offer of possession, whichever is earlier.
Ruling Awarded To
Respondent
Interest Period
from 08.12.2006 till the date of OC/CC or offer of possession, whichever is earlier
Statutory Sections Cited (RERA Act 2016)
Official RERA Tribunal Orders (1)
The Tribunal granted a review application to rectify a typographical error in its previous judgment, amending the interest period to be payable until the date of OC/CC or offer of possession, whichever is earlier.