up_reraStatus: Completed
CASE ID: 0901126033742021

Appellant / Complainant

Sanjeev Kumar Pandey Airship Forwarding India Pvt. Ltd.

VS

Respondent

Gaursons Hi-Tech Infrastructure Private Limited

Developer Firm

gaursons hi-tech infrastructure private limited

Disputed Amount

19,02,148

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126033742021 by Sanjeev Kumar Pandey Airship Forwarding India Pvt. Ltd. against Gaursons Hi-Tech Infrastructure Private Limited before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 107/02/2025

Re-Hearing

The Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposited amount of Rs 19,02,148/- along with interest at MCLR+1% from the promised possession date due to project delays and invalid possession offers.

3
Stage 210/01/2025

For Order

The Tribunal has scheduled the case for orders/hearing on 07.02.2025 and directed the Registry to issue a notice to the appellant regarding the fixed date.

4
Stage 320/05/2022

Hearing

The Tribunal directed both parties to file legal authorities on the relevant points of law within 15 days and reserved the judgment for further consideration.

5
Stage 418/04/2022

Hearing

The Tribunal directed the Registry to seek clarification from the Greater Noida Authority regarding the validity of a part completion certificate and ordered both parties to file lists of dates and cited cases before the next hearing.

6
Stage 525/02/2022

Hearing

No text available.

7
Stage 617/01/2022

Further Order

No text available.

8
Stage 715/12/2021

Further Order

The Tribunal granted the appellant permission to file a replication/rejoinder to the respondent's reply within one week and scheduled the matter for further orders on 17.01.2022.

9
Stage 822/11/2021

Notice

The Tribunal condoned a 14-day delay in filing the appeal due to COVID-19 pandemic relaxations and directed the defective appeal to be registered as a Regular Appeal.

10
Stage 927/09/2021

Delay condonation

The Tribunal issued a notice to the respondent via registered post and email and directed the appellant to take necessary steps within 10 days, scheduling the next hearing for 22.11.2021.

11
Stage 1007/09/2021

Delay condonation

The Tribunal noted that registry defects were removed and directed the issuance of notice to the respondent via registered post and email, scheduling the matter for 27.09.2021.

12
Stage 11Final Ruling Order

Tribunal Order #0901126033742021-07-02-2025

The Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposited amount of Rs 19,02,148/- along with interest at MCLR+1% from the promised possession date due to project delays and invalid possession offers.

13
Stage 12Interim Order

Tribunal Order #0901126033742021-18-04-2022

The Tribunal directed the Registry to seek clarification from the Greater Noida Authority regarding the validity of a part completion certificate and ordered both parties to file lists of dates and cited cases before the next hearing.

14
Stage 13Interim Order

Tribunal Order #0901126033742021-22-11-2021

The Tribunal condoned a 14-day delay in filing the appeal due to COVID-19 pandemic relaxations and directed the defective appeal to be registered as a Regular Appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposited amount of Rs 19,02,148/- along with interest at MCLR+1% from the promised possession date due to project delays and invalid possession offers. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposited amount of Rs 19,02,148/- along with interest at MCLR+1% from the promised possession date due to project delays and invalid possession offers.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

from the promised date of possession till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Mandeep Singh

Respondent Advocate(s)

  • Samrat Vaish
  • Mohit Yadav
  • C P Singh Yadav

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126033742021-07-02-2025

The Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposited amount of Rs 19,02,148/- along with interest at MCLR+1% from the promised possession date due to project delays and invalid possession offers.

INTERIM_ORDEROrder ID: 0901126033742021-18-04-2022

The Tribunal directed the Registry to seek clarification from the Greater Noida Authority regarding the validity of a part completion certificate and ordered both parties to file lists of dates and cited cases before the next hearing.

INTERIM_ORDEROrder ID: 0901126033742021-22-11-2021

The Tribunal condoned a 14-day delay in filing the appeal due to COVID-19 pandemic relaxations and directed the defective appeal to be registered as a Regular Appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for gaursons hi-tech infrastructure private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →