Appellant / Complainant
Sarita Gupta, Satyam Gupta
Respondent
Paramount Propbuild Pvt. Ltd.
paramount propbuild pvt. ltd.
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126033142022 by Sarita Gupta, Satyam Gupta against Paramount Propbuild Pvt. Ltd. before up_rera.
Hearing
The appeal was dismissed as withdrawn following a settlement reached between the appellant and the respondent.
Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the appeal for hearing on 16.05.2025.
Hearing
Upon the joint request of the counsel for both parties, the matter has been adjourned and listed for orders on 22.04.2025.
Hearing
The Tribunal granted an extension of time to the appellant as settlement talks are ongoing and listed the case for orders on 24.03.2025.
Hearing
The Tribunal granted an adjournment to the parties as they are in the process of reaching an amicable settlement outside of court, rescheduling the hearing for 27.02.2025.
Hearing
The parties have reached an amicable settlement, and the appeal has been listed for orders on 11.02.2025 at the request of both parties.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 21.01.2025.
Delay condonation
The Tribunal noted discrepancies regarding the completion status of Pine Tower and granted the respondent 10 days to produce the Occupancy Certificate (OC) or Completion Certificate (CC) for the project.
Delay condonation
The Tribunal allowed the appellant's application for condonation of delay due to medical grounds and directed the Registry to convert the defective appeal into a regular appeal, scheduling the merit hearing for 18.11.2024.
Hearing
The Tribunal granted a request for a short adjournment to allow counsel to prepare their briefs and scheduled the case for orders/hearing on 03.10.2024.
Hearing
The Tribunal has revised the listing of the case and scheduled it for orders/hearing on 09.09.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and scheduled the defective appeal for hearing on July 5, 2024.
Hearing
The Tribunal noted that pleadings have been exchanged and scheduled the defective appeal for consideration of the application for condonation of delay on 08.05.2024.
Hearing
The Tribunal noted the appellant's counsel was out of station and scheduled the defective appeal for consideration of the condonation of delay application on 05.04.2024.
Hearing
The Tribunal noted that the appeal is ripe for hearing and scheduled it for a subsequent hearing on March 1, 2024.
Hearing
The Tribunal has adjourned the appeal and scheduled it for orders or hearing on November 3, 2023.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for consideration of the condonation of delay application to 21.09.2023.
Delay condonation
The Tribunal granted the respondent one week to file objections to the better affidavit regarding the application for condonation of delay and scheduled the matter for hearing on 24.05.2023.
For Order
The Tribunal adjourned the proceedings due to the absence of the appellant's counsel and scheduled the defective appeal for a hearing on 18.04.2023.
For Order
Upon a joint request from the counsels for both parties, the tribunal adjourned the defective appeal to 26.02.2023.
For Order
The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for November 21, 2022.
Further Consideration
The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the defective appeal for hearing on 31.10.2022.
Delay condonation
The Tribunal granted the respondent one week to file objections to the application for condonation of delay and the grounds of appeal, with the case scheduled for hearing on 23.09.2022.
Delay condonation
The Tribunal issued a notice to the respondent regarding an application for condonation of delay and provided specific procedural instructions for service of notice and filing of objections.
Tribunal Order #0901126033142022-18-11-2024
The Tribunal noted discrepancies regarding the completion status of Pine Tower and granted the respondent 10 days to produce the Occupancy Certificate (OC) or Completion Certificate (CC) for the project.
Tribunal Order #0901126033142022-03-10-2024
The Tribunal allowed the appellant's application for condonation of delay due to medical grounds and directed the Registry to convert the defective appeal into a regular appeal, scheduling the merit hearing for 18.11.2024.
Tribunal Disposal & Final Award Ruling
Dismissed as withdrawn Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed as withdrawn
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
- Raj Singh
Respondent Advocate(s)
- Saurabh Misra
Official RERA Tribunal Orders (2)
The Tribunal noted discrepancies regarding the completion status of Pine Tower and granted the respondent 10 days to produce the Occupancy Certificate (OC) or Completion Certificate (CC) for the project.
The Tribunal allowed the appellant's application for condonation of delay due to medical grounds and directed the Registry to convert the defective appeal into a regular appeal, scheduling the merit hearing for 18.11.2024.