up_reraStatus: Completed
CASE ID: 0901126022252022

Appellant / Complainant

Ajay Kumar Jain

VS

Respondent

Paramount Propbuild Pvt. Ltd.

Developer Firm

paramount propbuild pvt. ltd.

Disputed Amount

8,56,650

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestMaintenance & Utility DisputesNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126022252022 by Ajay Kumar Jain against Paramount Propbuild Pvt. Ltd. before up_rera.

Delay in PossessionDelay Compensation / InterestMaintenance & Utility DisputesNon-Compliance & Execution
2
Stage 129/05/2023

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeal, ruling that the respondent had complied with the original RERA order by paying delay interest up to the date of the offer of possession and handing over the unit. The Tribunal held that the appellant could not challenge the calculation of interest through execution proceedings, as the original order had already attained finality.

3
Stage 204/01/2023

Hearing

The Tribunal directed the Registry to convert the appeal from a defective status to a regular appeal following the removal of defects by the appellant, and subsequently reserved judgment.

4
Stage 302/12/2022

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on January 4, 2023.

5
Stage 403/11/2022

Hearing

No text available.

6
Stage 529/09/2022

Hearing

The Tribunal granted the respondent time to file a list of dates and events and scheduled the appeal for hearing on November 3, 2022.

7
Stage 601/09/2022

Exchange of pleadings

The Tribunal directed the parties to exchange and submit a list of dates, events, and relied-upon judgments, scheduling the next hearing for September 29, 2022.

8
Stage 701/08/2022

Delay condonation

The Tribunal granted the appellant time to file a replication/rejoinder to the respondent's reply and scheduled the hearing for September 1, 2022.

9
Stage 807/07/2022

Notice

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and grounds of appeal, with a subsequent timeline set for the applicant's reply.

10
Stage 916/05/2022

Defect Removal

The Tribunal issued notice to the respondent subject to the removal of registry defects by the appellant and outlined the procedural requirements for service of notice and filing of objections.

11
Stage 10Final Ruling Order

Tribunal Order #0901126022252022-29-05-2023

The Appellate Tribunal dismissed the appeal, ruling that the respondent had complied with the original RERA order by paying delay interest up to the date of the offer of possession and handing over the unit. The Tribunal held that the appellant could not challenge the calculation of interest through execution proceedings, as the original order had already attained finality.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal, ruling that the respondent had complied with the original RERA order by paying delay interest up to the date of the offer of possession and handing over the unit. The Tribunal held that the appellant could not challenge the calculation of interest through execution proceedings, as the original order had already attained finality. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal, ruling that the respondent had complied with the original RERA order by paying delay interest up to the date of the offer of possession and handing over the unit. The Tribunal held that the appellant could not challenge the calculation of interest through execution proceedings, as the original order had already attained finality.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 31.12.2016 till receipt of OC/CC or offer of possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(d)Section 19(6)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Bhairav Dutt Sharma

Respondent Advocate(s)

  • Saurabh Misra
  • Shashank Kumar
  • Krishna Kumar Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126022252022-29-05-2023

The Appellate Tribunal dismissed the appeal, ruling that the respondent had complied with the original RERA order by paying delay interest up to the date of the offer of possession and handing over the unit. The Tribunal held that the appellant could not challenge the calculation of interest through execution proceedings, as the original order had already attained finality.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paramount propbuild pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →