up_reraStatus: Completed
CASE ID: 0901126032542022

Appellant / Complainant

Vibha Pandey

VS

Respondent

Pratham Buildcon Private Limited

Developer Firm

pratham buildcon private limited

Disputed Amount

25,00,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126032542022 by Vibha Pandey against Pratham Buildcon Private Limited before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 102/08/2023

for delivery of Judgment/Order

The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's entire deposited amount with interest at MCLR+1% per annum from the date of deposit until actual refund.

3
Stage 220/07/2023

Hearing

The appellant is challenging the Regulatory Authority's order regarding a delay in project possession, seeking a full refund of deposited amounts with interest instead of mere possession. The Tribunal heard arguments concerning the applicability of Supreme Court precedents and the respondent's failure to meet the Builder Buyer's Agreement timelines.

4
Stage 314/07/2023

Hearing

The Tribunal granted a request for adjournment by the respondent's counsel and scheduled the appeal for hearing on 20.07.2023.

5
Stage 402/05/2023

Exchange of pleadings

The Tribunal granted the respondent a one-week extension to file objections to the grounds of appeal and scheduled the next hearing for 14.07.2023.

6
Stage 521/03/2023

Exchange of pleadings

No text available.

7
Stage 610/02/2023

Exchange of pleadings

No text available.

8
Stage 706/01/2023

Exchange of pleadings

No text available.

9
Stage 806/12/2022

Exchange of pleadings

No text available.

10
Stage 910/11/2022

Further Order

The Tribunal noted that the appeal was filed within time and directed the respondent to file a reply to the grounds of appeal before the next hearing date.

11
Stage 1010/10/2022

Further Order

The Tribunal granted the respondent additional time to file objections to the delay condonation application and a reply to the grounds of appeal, scheduling the next hearing for November 10, 2022.

12
Stage 1109/09/2022

Further Order

No text available.

13
Stage 1210/08/2022

Hearing

The Tribunal noted the appellant's affidavit of service regarding notice to the respondent and adjourned the matter to 09.09.2022 for further orders.

14
Stage 1313/07/2022

Hearing

The Tribunal issued notice to the respondent regarding Appeal-400/2022 and directed the appellant to serve the notice via speed-post and email, scheduling the next hearing for August 10, 2022.

15
Stage 1411/07/2022

Hearing

The Tribunal directed the Registry to resolve a technical issue regarding the visibility of additional documents uploaded on 10.07.2022 and scheduled the matter for hearing on 13.07.2022.

16
Stage 1507/07/2022

Hearing on Appeal

The Tribunal granted the appellant's counsel two days to comply with the previous order dated 30.06.2022 and scheduled the appeal for hearing on 11.07.2022.

17
Stage 1630/06/2022

Hearing on Appeal

The Tribunal granted the appellant two days to provide evidence regarding the project's construction start date and scheduled the next hearing for July 7, 2022.

18
Stage 17Interim Order

Tribunal Order #0901126032542022-20-07-2023

The appellant is challenging the Regulatory Authority's order regarding a delay in project possession, seeking a full refund of deposited amounts with interest instead of mere possession. The Tribunal heard arguments concerning the applicability of Supreme Court precedents and the respondent's failure to meet the Builder Buyer's Agreement timelines.

19
Stage 18Final Ruling Order

Tribunal Order #0901126032542022-02-08-2023

The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's entire deposited amount with interest at MCLR+1% per annum from the date of deposit until actual refund.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's entire deposited amount with interest at MCLR+1% per annum from the date of deposit until actual refund. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% per annum of the State Bank of India.

Disposal Winner: AppellantInterest Rate: MCLR+1% per annum of the State Bank of IndiaStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's entire deposited amount with interest at MCLR+1% per annum from the date of deposit until actual refund.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1% per annum of the State Bank of India

Interest Period

from the date of the deposits till the refund of the same

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare
  • Aahuti Agarwal

Respondent Advocate(s)

  • Siddharth Nandwani
  • Abhishek Shukla

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126032542022-20-07-2023

The appellant is challenging the Regulatory Authority's order regarding a delay in project possession, seeking a full refund of deposited amounts with interest instead of mere possession. The Tribunal heard arguments concerning the applicability of Supreme Court precedents and the respondent's failure to meet the Builder Buyer's Agreement timelines.

FINAL_ORDEROrder ID: 0901126032542022-02-08-2023

The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's entire deposited amount with interest at MCLR+1% per annum from the date of deposit until actual refund.

TathyaGrid RERA Intelligence AI

Need to research all rulings for pratham buildcon private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →