up_reraStatus: Completed
CASE ID: 0901126039222021

Appellant / Complainant

Strescon Industries Limited

VS

Respondent

Uttar Pradesh Real Estate Regulatory Authority, Pratham Buildcon Private Limited, Dakshya Infra Developers Private Limited

Developer Firm

pratham buildcon private limited

Disputed Amount

30,00,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126039222021 by Strescon Industries Limited against Uttar Pradesh Real Estate Regulatory Authority, Pratham Buildcon Private Limited, Dakshya Infra Developers Private Limited before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional Misrepresentation
2
Stage 130/05/2023

for delivery of Judgment/Order

The Tribunal set aside the Regulatory Authority's order and directed Respondents 2 and 3 to refund the appellant's deposited amount for flats M-913 and M-914 with interest at MCLR+1% per annum from the date of deposit until the date of refund.

3
Stage 224/02/2023

Hearing

The Tribunal heard arguments from the counsel for both parties and reserved the judgment for a later date.

4
Stage 324/01/2023

Hearing

No text available.

5
Stage 404/01/2023

Hearing

The Tribunal granted the parties a final one-week extension to attempt an amicable settlement, noting that no further adjournments will be permitted and the case must proceed to a final hearing on the next date.

6
Stage 502/12/2022

Hearing

The Tribunal granted an adjournment requested by the counsel for both parties and scheduled the appeal for a hearing on January 4, 2023.

7
Stage 603/11/2022

Hearing

No text available.

8
Stage 729/09/2022

Hearing

The Tribunal allowed an adjournment application filed by the appellant's counsel and directed both parties to exchange a list of dates, events, and relied-upon judgments before the next hearing on 03.11.2022.

9
Stage 830/08/2022

Hearing

The Tribunal adjourned the appeal due to the respondent's counsel's absence and imposed a cost of Rs. 500/- to be deposited in the Tribunal's fund.

10
Stage 901/08/2022

Hearing

The Tribunal allowed an adjournment application filed by the respondent's counsel and rescheduled the hearing for August 30, 2022.

11
Stage 1013/07/2022

Hearing

The Tribunal noted that pleadings have been exchanged and parties are seeking an amicable settlement; consequently, the matter is adjourned to 01.08.2022.

12
Stage 1106/07/2022

Hearing

The Tribunal ordered the case to be rescheduled for hearing on 13.07.2022 before Bench No. I to ensure both this appeal and Appeal No. 609/2021 are heard by the same Bench.

13
Stage 1227/04/2022

Hearing

The Tribunal directed the Appellant to file a replication/rejoinder to the Respondent's reply and listed the matter for hearing on 06.07.2022.

14
Stage 1316/03/2022

Hearing

The Tribunal granted an adjournment requested by the appellant and rescheduled the hearing for April 27, 2022.

15
Stage 1428/02/2022

Hearing

No text available.

16
Stage 1503/02/2022

Hearing

No text available.

17
Stage 1610/01/2022

Hearing

The Tribunal granted the respondents a final two-week extension to file their reply against the grounds of appeal and scheduled the next hearing for February 3, 2022.

18
Stage 1706/12/2021

Final Hearing

No text available.

19
Stage 1812/11/2021

Hearing

The Tribunal directed the parties to exchange objections and replies via email and instructed them to upload their pleadings on the e-portal before the next hearing scheduled for 06.12.2021.

20
Stage 1927/09/2021

Hearing on Appeal

The Tribunal issued notice to the respondents and permitted the appellant's counsel to serve notice via his own email due to technical errors on the e-portal, scheduling the next hearing for 12.11.2021.

21
Stage 20Final Ruling Order

Tribunal Order #0901126039222021-30-05-2023

The Tribunal set aside the Regulatory Authority's order and directed Respondents 2 and 3 to refund the appellant's deposited amount for flats M-913 and M-914 with interest at MCLR+1% per annum from the date of deposit until the date of refund.

22
Stage 21Interim Order

Tribunal Order #0901126039222021-30-08-2022

The Tribunal adjourned the appeal due to the respondent's counsel's absence and imposed a cost of Rs. 500/- to be deposited in the Tribunal's fund.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order and directed Respondents 2 and 3 to refund the appellant's deposited amount for flats M-913 and M-914 with interest at MCLR+1% per annum from the date of deposit until the date of refund. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% per annum.

Disposal Winner: AppellantInterest Rate: MCLR + 1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order and directed Respondents 2 and 3 to refund the appellant's deposited amount for flats M-913 and M-914 with interest at MCLR+1% per annum from the date of deposit until the date of refund.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% per annum

Interest Period

from the date of deposit till the refund of the amount

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey

Respondent Advocate(s)

  • Abhishek Shukla
  • Siddharth Nandwani

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126039222021-30-05-2023

The Tribunal set aside the Regulatory Authority's order and directed Respondents 2 and 3 to refund the appellant's deposited amount for flats M-913 and M-914 with interest at MCLR+1% per annum from the date of deposit until the date of refund.

INTERIM_ORDEROrder ID: 0901126039222021-30-08-2022

The Tribunal adjourned the appeal due to the respondent's counsel's absence and imposed a cost of Rs. 500/- to be deposited in the Tribunal's fund.

TathyaGrid RERA Intelligence AI

Need to research all rulings for pratham buildcon private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →