up_reraStatus: Completed
CASE ID: 0901126032262023

Appellant / Complainant

Harsha Associates Pvt Ltd

VS

Respondent

Arun Bhati, Up Rera

Developer Firm

harsha associates pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Sale Deed & Title TransferNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126032262023 by Harsha Associates Pvt Ltd against Arun Bhati, Up Rera before up_rera.

Sale Deed & Title TransferNon-Compliance & Execution
2
Stage 123/07/2025

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of an 860-day delay and subsequently dismissed the appeal, finding the appellant failed to exercise due diligence.

3
Stage 203/07/2025

Delay condonation

The Tribunal granted a final opportunity to the appellant to file a rejoinder affidavit within seven days due to an adjournment request based on counsel's illness.

4
Stage 314/05/2025

Delay condonation

The Tribunal granted the appellant seven days to file a rejoinder affidavit due to a technical glitch on the portal and scheduled the next hearing for July 3, 2025.

5
Stage 423/04/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 14.05.2025.

6
Stage 527/03/2025

Delay condonation

The Tribunal granted the appellant 10 days to file a rejoinder affidavit to the respondent's objections and scheduled the case for hearing on 23.04.2025.

7
Stage 605/03/2025

Delay condonation

The Tribunal granted an adjournment at the request of the appellant's counsel and scheduled the matter for hearing on the application for condonation of delay on 27.03.2025.

8
Stage 707/02/2025

Delay condonation

The Tribunal noted the absence of both parties and ordered the defective appeal to be listed on 05.03.2025 for consideration of the application for condonation of delay.

9
Stage 822/01/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant and scheduled the matter for hearing on the application for condonation of delay on 07.02.2025.

10
Stage 909/01/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to him being out of station and rescheduled the matter for orders on 22.01.2025.

11
Stage 1027/11/2024

Delay condonation

The Tribunal granted an adjournment request from the appellant's counsel and scheduled the hearing for the application for condonation of delay on 09.01.2025.

12
Stage 1122/10/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to ongoing settlement negotiations between the parties and scheduled the matter for orders on 27.11.2024.

13
Stage 1219/09/2024

Delay condonation

The Tribunal granted an adjournment as the appellant's counsel stated that settlement talks are ongoing, and scheduled the matter for hearing on 22.10.2024.

14
Stage 1316/08/2024

Delay condonation

No text available.

15
Stage 1422/07/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the matter for hearing on 16.08.2024.

16
Stage 1522/05/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the hearing for the defective appeal to 22.07.2024.

17
Stage 1623/04/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the hearing for the application for condonation of delay on 22.05.2024.

18
Stage 1718/03/2024

Delay condonation

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the hearing for the application for condonation of delay on 23.04.2024.

19
Stage 1813/02/2024

Delay condonation

The Tribunal granted the appellant's counsel 10 days to file a reply to the objections and scheduled the appeal for consideration of the delay condonation application on 18.03.2024.

20
Stage 1918/01/2024

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on 13.02.2024 regarding the application for condonation of delay.

21
Stage 2020/12/2023

Defect Removal

The Tribunal issued notice to the respondent and directed the applicant to serve notice and file an affidavit of service, scheduling the matter for 18.01.2024 to consider the application for condonation of delay.

22
Stage 21Final Ruling Order

Tribunal Order #0901126032262023-23-07-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of an 860-day delay and subsequently dismissed the appeal, finding the appellant failed to exercise due diligence.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of an 860-day delay and subsequently dismissed the appeal, finding the appellant failed to exercise due diligence. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of an 860-day delay and subsequently dismissed the appeal, finding the appellant failed to exercise due diligence.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 11(4)(f)Section 17Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Mahima Pahwa
  • Prashant Kumar Singh

Respondent Advocate(s)

  • Harsha Vinoy

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126032262023-23-07-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of an 860-day delay and subsequently dismissed the appeal, finding the appellant failed to exercise due diligence.