up_reraStatus: Completed
CASE ID: 0901126028232023

Appellant / Complainant

Rise Projects Pvt Ltd

VS

Respondent

Ranjan Saha

Developer Firm

rise projects pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

27 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126028232023 by Rise Projects Pvt Ltd against Ranjan Saha before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 107/05/2025

Delay condonation

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but ruled that the promoter is mandatorily obligated to pay delay interest to the allottee from 21.01.2020 until possession (excluding the COVID-19 force majeure period) at the rate of MCLR+1%.

3
Stage 211/04/2025

Delay condonation

The court has adjourned the matter to 07.05.2025 following a joint request from the learned counsel for both parties.

4
Stage 318/03/2025

Delay condonation

The appeal is adjourned to 11.04.2025 because lawyers are abstaining from judicial work following a resolution by the Real Estate Bar Association, Lucknow.

5
Stage 414/02/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the next hearing for 18.03.2025, noting that no further adjournments will be permitted.

6
Stage 516/01/2025

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the matter for orders on 14.02.2025.

7
Stage 626/11/2024

Delay condonation

The Tribunal has adjourned the appeal to 16.01.2025 to allow both parties to file an affidavit regarding the project's delay, following a joint request from their respective counsels.

8
Stage 721/10/2024

Delay condonation

The Tribunal has adjourned the appeal to 26.11.2024 due to the illness of the counsels representing the appellant.

9
Stage 811/09/2024

Delay condonation

The Tribunal noted that pleadings have been exchanged and adjourned the matter to 21.10.2024 for orders/hearing following a request for time by the respondent's counsel.

10
Stage 920/08/2024

Delay condonation

The Tribunal has adjourned the appeal to 11.09.2024 for orders/hearing following a joint request from the counsel for both parties.

11
Stage 1007/08/2024

Delay condonation

The Tribunal granted a request by the appellant's counsel to list the defective appeal for orders or hearing on 20.08.2024.

12
Stage 1122/07/2024

Delay condonation

The Tribunal granted the respondent a final 7-day extension to file objections, after which the applicant may file a reply, and scheduled the matter for hearing on 07.08.2024.

13
Stage 1222/05/2024

Delay condonation

The Tribunal granted both parties extensions of time to file objections and replies regarding the application for condonation of delay and the grounds of appeal, scheduling the next hearing for 22.07.2024.

14
Stage 1323/04/2024

Delay condonation

The Tribunal granted the respondent a final 10-day extension to file objections to the grounds of appeal and the application for condonation of delay, with the matter scheduled for hearing on 22.05.2024.

15
Stage 1419/03/2024

Delay condonation

This is a procedural order directing the parties to refer to a previously passed order dated in Appeal No. D 543/2023.

16
Stage 1515/02/2024

Delay condonation

The Tribunal directed the issuance of fresh notice to the respondent via Dasti and electronic modes due to an incomplete address, with the next hearing scheduled for 19.03.2024.

17
Stage 1601/02/2024

Delay condonation

The Tribunal granted the applicant one additional week to file an affidavit of service and scheduled the defective appeal for consideration of the condonation of delay on 15.02.2024.

18
Stage 1702/11/2023

Delay condonation

No text available.

19
Stage 1820/09/2023

Delay condonation

The Tribunal granted the appellant's request to issue fresh notice to the respondent regarding the application for condonation of delay, with the matter listed for hearing on 02.11.2023.

20
Stage 1916/08/2023

Delay condonation

The Tribunal ruled that amounts already recovered via a Recovery Certificate shall be treated as compliance with Section 43(5) of the Act and directed the Recovery Officer to deposit these funds in a fixed deposit. Additionally, the Tribunal issued notice to the respondent regarding the application for condonation of delay.

21
Stage 2011/08/2023

Delay condonation

The Tribunal granted a request from the appellant's counsel to list the defective appeal for orders or hearing on 16.08.2023.

22
Stage 2108/08/2023

Delay condonation

The Tribunal granted the appellant two days to submit bank statements to prove prior payment of Rs. 5,83,107 to support their application for a waiver of the mandatory deposit required under Section 43(5) of the Act.

23
Stage 2207/08/2023

Delay condonation

No text available.

24
Stage 23Final Ruling Order

Tribunal Order #0901126028232023-07-05-2025

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but ruled that the promoter is mandatorily obligated to pay delay interest to the allottee from 21.01.2020 until possession (excluding the COVID-19 force majeure period) at the rate of MCLR+1%.

25
Stage 24Interim Order

Tribunal Order #0901126028232023-16-08-2023

The Tribunal ruled that amounts already recovered via a Recovery Certificate shall be treated as compliance with Section 43(5) of the Act and directed the Recovery Officer to deposit these funds in a fixed deposit. Additionally, the Tribunal issued notice to the respondent regarding the application for condonation of delay.

26
Stage 25Interim Order

Tribunal Order #0901126028232023-08-08-2023

The Tribunal granted the appellant two days to submit bank statements to prove prior payment of Rs. 5,83,107 to support their application for a waiver of the mandatory deposit required under Section 43(5) of the Act.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but ruled that the promoter is mandatorily obligated to pay delay interest to the allottee from 21.01.2020 until possession (excluding the COVID-19 force majeure period) at the rate of MCLR+1%. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but ruled that the promoter is mandatorily obligated to pay delay interest to the allottee from 21.01.2020 until possession (excluding the COVID-19 force majeure period) at the rate of MCLR+1%.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

w.e.f. 21.01.2020 till the date of offer of possession along with valid OC/CC (except the period from 25.03.2020 to 25.09.2020 on account of force majeure due to Covid-19 pandemic)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Siddharth Nandwani
  • Abhishek Shukla

Respondent Advocate(s)

  • Tushar Bahadur
  • Sachin Gupta

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126028232023-07-05-2025

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but ruled that the promoter is mandatorily obligated to pay delay interest to the allottee from 21.01.2020 until possession (excluding the COVID-19 force majeure period) at the rate of MCLR+1%.

INTERIM_ORDEROrder ID: 0901126028232023-16-08-2023

The Tribunal ruled that amounts already recovered via a Recovery Certificate shall be treated as compliance with Section 43(5) of the Act and directed the Recovery Officer to deposit these funds in a fixed deposit. Additionally, the Tribunal issued notice to the respondent regarding the application for condonation of delay.

INTERIM_ORDEROrder ID: 0901126028232023-08-08-2023

The Tribunal granted the appellant two days to submit bank statements to prove prior payment of Rs. 5,83,107 to support their application for a waiver of the mandatory deposit required under Section 43(5) of the Act.

TathyaGrid RERA Intelligence AI

Need to research all rulings for rise projects pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →