up_reraStatus: Completed
CASE ID: 0901126028362023

Appellant / Complainant

Rise Projects Pvt Ltd

VS

Respondent

Vivek Sharma

Developer Firm

rise projects pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126028362023 by Rise Projects Pvt Ltd against Vivek Sharma before up_rera.

2
Stage 116/01/2025

Delay condonation

The appeal filed by Rise Projects Pvt Ltd was dismissed as withdrawn following a request by the appellant's counsel.

3
Stage 226/11/2024

Delay condonation

The Tribunal granted a request from both parties to file an affidavit regarding the project's delay and adjourned the appeal to 16.01.2025 for orders.

4
Stage 321/10/2024

Delay condonation

The Tribunal has adjourned the appeal to 26.11.2024 due to the illness of the counsel representing the appellant.

5
Stage 411/09/2024

Delay condonation

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for orders/hearing on 21.10.2024.

6
Stage 520/08/2024

Delay condonation

The Tribunal has adjourned the appeal to 11.09.2024 for orders or hearing following a joint request from the counsels of both parties.

7
Stage 607/08/2024

Delay condonation

The Tribunal granted a request by the appellant's counsel to list the defective appeal for orders or hearing on 20.08.2024.

8
Stage 722/07/2024

Delay condonation

The Tribunal granted the respondent a final 7-day extension to file objections and directed that a copy be emailed to the applicant, with the applicant allowed 7 days thereafter to file a reply.

9
Stage 822/05/2024

Delay condonation

The Tribunal granted parties additional time to file objections and replies regarding the application for condonation of delay and the grounds of appeal, scheduling the next hearing for 22.07.2024.

10
Stage 923/04/2024

Delay condonation

The Tribunal granted the respondent a 10-day extension to file objections to the grounds of appeal and the application for condonation of delay, scheduling the next hearing for May 22, 2024.

11
Stage 1019/03/2024

Delay condonation

This is a procedural order directing the parties to refer to a previous order passed in Appeal No. D 543/2023.

12
Stage 1115/02/2024

Delay condonation

The Tribunal issued fresh notice to the respondent due to insufficient service tracking and set a procedural timeline for service via speed-post and email, scheduling the next hearing for 19.03.2024.

13
Stage 1201/02/2024

Delay condonation

The Tribunal granted the applicant one additional week to file an affidavit of service and scheduled the matter for hearing on 15.02.2024.

14
Stage 1302/11/2023

Delay condonation

No text available.

15
Stage 1420/09/2023

Delay condonation

The Tribunal granted a request for fresh notice to be issued to the respondent regarding the application for condonation of delay and scheduled the matter for hearing on 02.11.2023.

16
Stage 1516/08/2023

Delay condonation

The Tribunal ruled that the amount of Rs 5,63,275/- recovered via a Recovery Certificate shall be treated as compliance with Section 43(5) of the Act and directed the Recovery Officer to deposit said amount in a fixed deposit for 60 days.

17
Stage 1611/08/2023

Delay condonation

The Tribunal granted a request from the appellant's counsel to list the defective appeal for orders or hearing on 16.08.2023.

18
Stage 1708/08/2023

Delay condonation

The Tribunal granted the appellant two days to submit a bank statement verifying a prior payment of Rs. 5,63,275/- to support their application for waiver of deposit under Section 43(5) of the Act.

19
Stage 1807/08/2023

Delay condonation

No text available.

20
Stage 19Interim Order

Tribunal Order #0901126028362023-16-08-2023

The Tribunal ruled that the amount of Rs 5,63,275/- recovered via a Recovery Certificate shall be treated as compliance with Section 43(5) of the Act and directed the Recovery Officer to deposit said amount in a fixed deposit for 60 days.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Siddharth Nandwani
  • Abhishek Shukla

Respondent Advocate(s)

  • Tushar Bahadur
  • Sachin Gupta

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126028362023-16-08-2023

The Tribunal ruled that the amount of Rs 5,63,275/- recovered via a Recovery Certificate shall be treated as compliance with Section 43(5) of the Act and directed the Recovery Officer to deposit said amount in a fixed deposit for 60 days.