Appellant / Complainant
Ramu Sankhla
Respondent
Pratham Buildcon Private Limited
pratham buildcon private limited
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126028052023 by Ramu Sankhla against Pratham Buildcon Private Limited before up_rera.
for delivery of Judgment/Order
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to show sufficient cause for the 396-day delay following the Supreme Court's COVID-19 limitation extension.
Delay condonation
The Tribunal heard arguments regarding the application for condonation of delay and has reserved its judgment.
Delay condonation
The Tribunal has adjourned the matter to 02.07.2025 as the parties are currently engaged in negotiations for an amicable settlement.
Delay condonation
The Tribunal allowed the respondent's application to recall an order imposing a Rs. 10,000 cost and noted that both parties are attempting an amicable settlement outside of court.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 30.04.2025.
Delay condonation
The Tribunal ordered the respondent to pay costs of Rs. 10,000 to the appellant before the next listing date on 04.04.2025.
Delay condonation
The Tribunal granted the respondent 10 days to file a reply regarding an amendment application and scheduled the matter for hearing on March 17, 2025.
Delay condonation
The Tribunal granted the respondent time to file a reply to newly submitted documents and scheduled the matter for hearing on the application for condonation of delay on 19.02.2025.
Delay condonation
The Tribunal directed the appellant's counsel to comply with a previous order by filing a copy of the CC obtained via RTI and scheduled the matter for orders on 29.01.2025.
Delay condonation
The Tribunal granted the appellant's counsel time to file a copy of the CC obtained via RTI and adjourned the matter for hearing on 16.01.2025.
Delay condonation
The tribunal granted an adjournment requested by the appellant's counsel and rescheduled the matter for hearing on 05.11.2024.
Delay condonation
The Tribunal has adjourned the appeal to 23.09.2024 for orders/hearing based on a joint request from the counsel for both parties.
Delay condonation
The Tribunal granted a joint request from the counsels of both parties to list the defective appeal for orders or hearing on 20.08.2024.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to health issues and rescheduled the hearing for July 23, 2024.
Delay condonation
The Tribunal granted the respondent one week to examine the reply filed regarding the application for condonation of delay and scheduled the matter for hearing on 23.05.2024.
Delay condonation
The Tribunal granted the respondent a final 3-day extension to file objections and an application for condonation of delay, subject to a cost of Rs. 10,000/- to be used for the legal library.
Delay condonation
The Tribunal granted the respondent a 10-day extension to comply with a previous order and scheduled the matter for hearing on March 18, 2024, regarding the application for condonation of delay.
Delay condonation
The Tribunal granted the respondent 10 days to file a reply to the applicant's objections and scheduled the matter for hearing on February 13, 2024, regarding the application for condonation of delay.
Delay condonation
The Tribunal issued a notice to the respondent regarding the application for condonation of delay and directed the applicant to serve the notice via speed-post and email, scheduling the matter for hearing on 03.10.2023.
Tribunal Order #0901126028052023-11-08-2025
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to show sufficient cause for the 396-day delay following the Supreme Court's COVID-19 limitation extension.
Tribunal Order #0901126028052023-30-04-2025
The Tribunal allowed the respondent's application to recall an order imposing a Rs. 10,000 cost and noted that both parties are attempting an amicable settlement outside of court.
Tribunal Order #0901126028052023-17-03-2025
The Tribunal ordered the respondent to pay costs of Rs. 10,000 to the appellant before the next listing date on 04.04.2025.
Tribunal Order #0901126028052023-18-03-2024
The Tribunal granted the respondent a final 3-day extension to file objections and an application for condonation of delay, subject to a cost of Rs. 10,000/- to be used for the legal library.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to show sufficient cause for the 396-day delay following the Supreme Court's COVID-19 limitation extension. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to show sufficient cause for the 396-day delay following the Supreme Court's COVID-19 limitation extension.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Gyanendra Chaturvedi
Respondent Advocate(s)
- Siddharth Nandwani
- Abhishek Shukla
Official RERA Tribunal Orders (4)
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to show sufficient cause for the 396-day delay following the Supreme Court's COVID-19 limitation extension.
The Tribunal allowed the respondent's application to recall an order imposing a Rs. 10,000 cost and noted that both parties are attempting an amicable settlement outside of court.
The Tribunal ordered the respondent to pay costs of Rs. 10,000 to the appellant before the next listing date on 04.04.2025.
The Tribunal granted the respondent a final 3-day extension to file objections and an application for condonation of delay, subject to a cost of Rs. 10,000/- to be used for the legal library.
Need to research all rulings for pratham buildcon private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.