up_reraStatus: Completed
CASE ID: 0901126028052023

Appellant / Complainant

Ramu Sankhla

VS

Respondent

Pratham Buildcon Private Limited

Developer Firm

pratham buildcon private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

27 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126028052023 by Ramu Sankhla against Pratham Buildcon Private Limited before up_rera.

2
Stage 111/08/2025

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to show sufficient cause for the 396-day delay following the Supreme Court's COVID-19 limitation extension.

3
Stage 202/07/2025

Delay condonation

The Tribunal heard arguments regarding the application for condonation of delay and has reserved its judgment.

4
Stage 321/05/2025

Delay condonation

The Tribunal has adjourned the matter to 02.07.2025 as the parties are currently engaged in negotiations for an amicable settlement.

5
Stage 430/04/2025

Delay condonation

The Tribunal allowed the respondent's application to recall an order imposing a Rs. 10,000 cost and noted that both parties are attempting an amicable settlement outside of court.

6
Stage 504/04/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 30.04.2025.

7
Stage 617/03/2025

Delay condonation

The Tribunal ordered the respondent to pay costs of Rs. 10,000 to the appellant before the next listing date on 04.04.2025.

8
Stage 719/02/2025

Delay condonation

The Tribunal granted the respondent 10 days to file a reply regarding an amendment application and scheduled the matter for hearing on March 17, 2025.

9
Stage 829/01/2025

Delay condonation

The Tribunal granted the respondent time to file a reply to newly submitted documents and scheduled the matter for hearing on the application for condonation of delay on 19.02.2025.

10
Stage 916/01/2025

Delay condonation

The Tribunal directed the appellant's counsel to comply with a previous order by filing a copy of the CC obtained via RTI and scheduled the matter for orders on 29.01.2025.

11
Stage 1006/12/2024

Delay condonation

The Tribunal granted the appellant's counsel time to file a copy of the CC obtained via RTI and adjourned the matter for hearing on 16.01.2025.

12
Stage 1105/11/2024

Delay condonation

No text available.

13
Stage 1223/09/2024

Delay condonation

The tribunal granted an adjournment requested by the appellant's counsel and rescheduled the matter for hearing on 05.11.2024.

14
Stage 1320/08/2024

Delay condonation

The Tribunal has adjourned the appeal to 23.09.2024 for orders/hearing based on a joint request from the counsel for both parties.

15
Stage 1423/07/2024

Delay condonation

The Tribunal granted a joint request from the counsels of both parties to list the defective appeal for orders or hearing on 20.08.2024.

16
Stage 1523/05/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to health issues and rescheduled the hearing for July 23, 2024.

17
Stage 1623/04/2024

Delay condonation

The Tribunal granted the respondent one week to examine the reply filed regarding the application for condonation of delay and scheduled the matter for hearing on 23.05.2024.

18
Stage 1718/03/2024

Delay condonation

The Tribunal granted the respondent a final 3-day extension to file objections and an application for condonation of delay, subject to a cost of Rs. 10,000/- to be used for the legal library.

19
Stage 1813/02/2024

Delay condonation

The Tribunal granted the respondent a 10-day extension to comply with a previous order and scheduled the matter for hearing on March 18, 2024, regarding the application for condonation of delay.

20
Stage 1909/01/2024

Delay condonation

The Tribunal granted the respondent 10 days to file a reply to the applicant's objections and scheduled the matter for hearing on February 13, 2024, regarding the application for condonation of delay.

21
Stage 2003/10/2023

Delay condonation

No text available.

22
Stage 2121/08/2023

Delay condonation

The Tribunal issued a notice to the respondent regarding the application for condonation of delay and directed the applicant to serve the notice via speed-post and email, scheduling the matter for hearing on 03.10.2023.

23
Stage 22Final Ruling Order

Tribunal Order #0901126028052023-11-08-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to show sufficient cause for the 396-day delay following the Supreme Court's COVID-19 limitation extension.

24
Stage 23Interim Order

Tribunal Order #0901126028052023-30-04-2025

The Tribunal allowed the respondent's application to recall an order imposing a Rs. 10,000 cost and noted that both parties are attempting an amicable settlement outside of court.

25
Stage 24Interim Order

Tribunal Order #0901126028052023-17-03-2025

The Tribunal ordered the respondent to pay costs of Rs. 10,000 to the appellant before the next listing date on 04.04.2025.

26
Stage 25Interim Order

Tribunal Order #0901126028052023-18-03-2024

The Tribunal granted the respondent a final 3-day extension to file objections and an application for condonation of delay, subject to a cost of Rs. 10,000/- to be used for the legal library.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to show sufficient cause for the 396-day delay following the Supreme Court's COVID-19 limitation extension. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to show sufficient cause for the 396-day delay following the Supreme Court's COVID-19 limitation extension.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Gyanendra Chaturvedi

Respondent Advocate(s)

  • Siddharth Nandwani
  • Abhishek Shukla

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126028052023-11-08-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal because the appellant failed to show sufficient cause for the 396-day delay following the Supreme Court's COVID-19 limitation extension.

INTERIM_ORDEROrder ID: 0901126028052023-30-04-2025

The Tribunal allowed the respondent's application to recall an order imposing a Rs. 10,000 cost and noted that both parties are attempting an amicable settlement outside of court.

INTERIM_ORDEROrder ID: 0901126028052023-17-03-2025

The Tribunal ordered the respondent to pay costs of Rs. 10,000 to the appellant before the next listing date on 04.04.2025.

INTERIM_ORDEROrder ID: 0901126028052023-18-03-2024

The Tribunal granted the respondent a final 3-day extension to file objections and an application for condonation of delay, subject to a cost of Rs. 10,000/- to be used for the legal library.

TathyaGrid RERA Intelligence AI

Need to research all rulings for pratham buildcon private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →