up_reraStatus: Completed
CASE ID: 0901126027382021

Appellant / Complainant

Arvind Kumar Shukla

VS

Respondent

U.P. Awas Evam Vikas Parishad, U.P. Real Estate Regulatory Authority Lucknow

Developer Firm

u.p. awas evam vikas parishad

Disputed Amount

6,09,821

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

31 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126027382021 by Arvind Kumar Shukla against U.P. Awas Evam Vikas Parishad, U.P. Real Estate Regulatory Authority Lucknow before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 118/08/2023

for delivery of Judgment/Order

The Tribunal set aside the Regulatory Authority's order and directed the respondent to pay interest at the rate of MCLR+1% per annum for the delay in possession from April 29, 2017, until June 26, 2020.

3
Stage 209/08/2023

Hearing

The Tribunal heard arguments from the counsel for both parties, and the judgment has been reserved.

4
Stage 329/05/2023

Hearing

The Tribunal has adjourned the matter to 09.08.2023 for orders/hearing following a joint request from the counsels of both parties.

5
Stage 421/04/2023

Hearing

The Tribunal acknowledged a delay in possession by the respondent and directed their counsel to seek instructions regarding the admissible interest payable to the allottee due to said delay.

6
Stage 514/03/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the case for hearing on 21.04.2023.

7
Stage 603/02/2023

Hearing

No text available.

8
Stage 702/01/2023

Further Hearing

The Tribunal directed the respondent's counsel to rectify any defects regarding their uploaded objection and scheduled the appeal for hearing on 03.02.2023.

9
Stage 801/12/2022

Further Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on January 2, 2023.

10
Stage 902/11/2022

Further Hearing

The Tribunal has called the case for hearing and scheduled it for a subsequent listing on December 1, 2022.

11
Stage 1027/09/2022

Further Hearing

The Tribunal has rescheduled the hearing of the appeal to 02.11.2022 following a joint request from the counsels for both parties.

12
Stage 1105/09/2022

Further Hearing

The Tribunal granted a joint request from the counsels of both parties to list the appeal for hearing on 27.09.2022.

13
Stage 1216/08/2022

Further Hearing

This text represents the header/caption of an appeal (APPEAL-473/2021) before the U.P. Real Estate Appellate Tribunal involving Arvind Kumar Shukla and U.P. Awas Evam Vikas Parishad, but it contains no substantive ruling or directive.

14
Stage 1322/07/2022

Further Hearing

The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and scheduled the next hearing for 16.08.2022.

15
Stage 1411/05/2022

Further Order

The Tribunal granted the appellant's request for time to file a replication against the respondent's reply and scheduled the next hearing for 22.07.2022.

16
Stage 1507/04/2022

Hearing

The Tribunal granted an adjournment requested by the appellant and rescheduled the hearing to May 11, 2022.

17
Stage 1615/03/2022

Further Order

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and directed that the reply be served via email and uploaded to the e-portal.

18
Stage 1705/01/2022

Further Order

The Tribunal granted the appellant's request for a short adjournment to file a replication/rejoinder and directed that a copy be served to the respondent via email before the next hearing.

19
Stage 1829/11/2021

Further Order

The Tribunal allowed the appellant's limitation application to condone a 129-day delay in filing the appeal, subject to a cost of Rs. 600/- to be split between the Tribunal fund and the respondent's counsel.

20
Stage 1928/10/2021

Delay condonation

The Tribunal granted the respondent 15 days to file their Vakalat Nama and objection to the limitation application, with the case scheduled for further orders on 29.11.2021.

21
Stage 2028/09/2021

Delay condonation

The Tribunal granted the respondent two weeks to file objections to the condonation of delay application and grounds of appeal, with a subsequent timeline set for the appellant's reply and the next hearing scheduled for 28.10.2021.

22
Stage 2107/09/2021

Delay condonation

The Tribunal directed the Registry to issue fresh dasti summons to the respondent and scheduled the next hearing for 28.09.2021.

23
Stage 2224/08/2021

Delay condonation

The Tribunal directed the appellant to take fresh steps for service of summons to the respondent via 'Dasti' summons due to a previous failure in service, and scheduled the next hearing for 07.09.2021.

24
Stage 2323/08/2021

Delay condonation

No text available.

25
Stage 2403/08/2021

Delay condonation

The Tribunal directed the Housing Commissioner of U.P. Awas Evam Vikas Parishad to ensure representation for the organization on the next date and noted that the respondent is deemed aware of proceedings via the web portal's automatic notification system.

26
Stage 2502/07/2021

Delay condonation

The Tribunal issued notice on the application for condonation of delay and directed the parties to exchange documents via email and upload their respective objections/replies on the e-portal before the next hearing on 03.08.2021.

27
Stage 26Interim Order

Tribunal Order #0901126027382021-29-11-2021

The Tribunal allowed the appellant's limitation application to condone a 129-day delay in filing the appeal, subject to a cost of Rs. 600/- to be split between the Tribunal fund and the respondent's counsel.

28
Stage 27Final Ruling Order

Tribunal Order #0901126027382021-18-08-2023

The Tribunal set aside the Regulatory Authority's order and directed the respondent to pay interest at the rate of MCLR+1% per annum for the delay in possession from April 29, 2017, until June 26, 2020.

29
Stage 28Interim Order

Tribunal Order #0901126027382021-21-04-2023

The Tribunal acknowledged a delay in possession by the respondent and directed their counsel to seek instructions regarding the admissible interest payable to the allottee due to said delay.

30
Stage 29Interim Order

Tribunal Order #0901126027382021-03-08-2021

The Tribunal directed the Housing Commissioner of U.P. Awas Evam Vikas Parishad to ensure representation for the organization on the next date and noted that the respondent is deemed aware of proceedings via the web portal's automatic notification system.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order and directed the respondent to pay interest at the rate of MCLR+1% per annum for the delay in possession from April 29, 2017, until June 26, 2020. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% p.a..

Disposal Winner: AppellantInterest Rate: MCLR + 1% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order and directed the respondent to pay interest at the rate of MCLR+1% per annum for the delay in possession from April 29, 2017, until June 26, 2020.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% p.a.

Interest Period

from the proposed date of possession i.e. 29.04.2017 till offer of possession after receipt of OC/CC i.e. (26.06.2020)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra
  • Krishna Kumar Singh
  • Gautam Johri

Respondent Advocate(s)

  • N N Pandey

Official RERA Tribunal Orders (4)

INTERIM_ORDEROrder ID: 0901126027382021-29-11-2021

The Tribunal allowed the appellant's limitation application to condone a 129-day delay in filing the appeal, subject to a cost of Rs. 600/- to be split between the Tribunal fund and the respondent's counsel.

FINAL_ORDEROrder ID: 0901126027382021-18-08-2023

The Tribunal set aside the Regulatory Authority's order and directed the respondent to pay interest at the rate of MCLR+1% per annum for the delay in possession from April 29, 2017, until June 26, 2020.

INTERIM_ORDEROrder ID: 0901126027382021-21-04-2023

The Tribunal acknowledged a delay in possession by the respondent and directed their counsel to seek instructions regarding the admissible interest payable to the allottee due to said delay.

INTERIM_ORDEROrder ID: 0901126027382021-03-08-2021

The Tribunal directed the Housing Commissioner of U.P. Awas Evam Vikas Parishad to ensure representation for the organization on the next date and noted that the respondent is deemed aware of proceedings via the web portal's automatic notification system.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. awas evam vikas parishad?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →