up_reraStatus: Completed
CASE ID: 0901126040452024

Appellant / Complainant

Badri Prasad Singh

VS

Respondent

U.P. Awas Evam Vikas Parishad, The Uttar Pradesh Real Estate Regulatory Authority

Developer Firm

u.p. awas evam vikas parishad

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

14 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126040452024 by Badri Prasad Singh against U.P. Awas Evam Vikas Parishad, The Uttar Pradesh Real Estate Regulatory Authority before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 129/08/2025

for delivery of Judgment/Order

The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations by citing delay or the execution of conveyance deeds.

3
Stage 223/04/2025

Further Hearing

The Tribunal has heard arguments from various counsels representing the appellant and respondents, and has reserved its judgment.

4
Stage 321/04/2025

Further Hearing

No text available.

5
Stage 411/04/2025

Hearing

The Tribunal has adjourned the ongoing arguments and scheduled the appeal for further hearing on April 21, 2025, at 1:30 p.m.

6
Stage 509/04/2025

For Order

The Tribunal has adjourned the appeal to 11.04.2025 at 10:30 a.m. following a joint request from the learned counsel for both parties.

7
Stage 627/03/2025

For Order

The Tribunal has scheduled the case for orders/hearing on 09.04.2025 and directed that pleadings be completed in the interim.

8
Stage 725/02/2025

For Order

The appeal is adjourned to 27.03.2025 due to a strike by the Bar Council of Uttar Pradesh.

9
Stage 805/02/2025

For Order

The Tribunal granted a request for adjournment from the appellant's counsel and rescheduled the hearing for February 25, 2025.

10
Stage 908/01/2025

For Order

The Tribunal granted a request to list the appeal for orders/hearing on 05.02.2025 and directed the parties to exchange pleadings in the interim.

11
Stage 1010/12/2024

For Order

The Tribunal granted Respondent No. 2 ten days to file objections against the grounds of appeal and directed the appellant to file a reply within one week thereafter, with the next hearing scheduled for 08.01.2025.

12
Stage 1108/11/2024

Admission

The Tribunal has admitted the appeal, issued notice to the respondent, and established a procedural timeline for service of notice and filing of objections before the next hearing on 10-12-2024.

13
Stage 12Final Ruling Order

Tribunal Order #0901126040452024-29-08-2025

The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations by citing delay or the execution of conveyance deeds.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations by citing delay or the execution of conveyance deeds. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations by citing delay or the execution of conveyance deeds.

Ruling Awarded To

Appellant

Interest Period

from the date of allotment/agreement till the date of offer of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav

Respondent Advocate(s)

  • Shireesh Kumar

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126040452024-29-08-2025

The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations by citing delay or the execution of conveyance deeds.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. awas evam vikas parishad?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →