Appellant / Complainant
Ar Landcraft Llp
Respondent
Shailendra Jaiswal, Priyanka Jaiswal
ar landcraft llp
₹1,89,55,746
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126027142023 by Ar Landcraft Llp against Shailendra Jaiswal, Priyanka Jaiswal before up_rera.
Hearing
The Tribunal has granted a joint request to reschedule the appeal for a hearing on 21.04.2026 before Bench No. 2.
Hearing
The Tribunal has scheduled the appeal for a final hearing on March 12, 2026, following a reference to a previous order passed in Appeal No. 196/2024.
Hearing
The Tribunal directed that this appeal be listed on 17.02.2026, following the orders passed in Appeal No. 196 of 2024.
for delivery of Judgment/Order
The Tribunal dismissed the developer's appeal and ruled that the promoter must pay delay interest to allottees, execute supplementary deeds to correct omitted plot/exclusive areas, refund mandatory club fees, and face investigation for fraudulent practices and statutory violations.
Further Hearing
The Tribunal has reserved judgment in the matter and directed both parties to file their written arguments within 10 days.
Further Hearing
The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000/- to be paid to the respondent by the next hearing date on 07.11.2025.
Further Hearing
The Tribunal has granted a request by the appellant's counsel to list the appeal for orders or hearing on 14.10.2025.
Hearing
The Tribunal heard arguments from both parties and adjourned the appeal for further hearing on 16.09.2025, directing both parties to submit their written submissions.
Hearing
The Tribunal granted the appellant two weeks to file a rejoinder and directed the parties to exchange pleadings, scheduling the next hearing for August 11, 2025.
Hearing
The Tribunal noted the appellant's submission that the process for correcting the sublease deed is underway and adjourned the matter to 21.07.2025.
Hearing
The Tribunal granted the appellant ten days to file a rejoinder and permitted the respondent to file objections to the appellant's affidavit, with the matter scheduled for hearing on 29.05.2025.
Delay condonation
The Tribunal admitted the appeal and accepted the appellant's undertaking to reverse the Advance Payment Rebate (APR) error and execute a correction deed for the sub-lease deed to include the exclusive area.
Delay condonation
The Appellant/Promoter submitted an undertaking to hand over possession of the unit before the next hearing date following the deposit of sale consideration, which the Tribunal accepted.
Delay condonation
The Tribunal accepted an undertaking from the appellant to hand over the letter of offer of possession and a demand draft for costs to the respondents, with a commitment to provide physical possession of the habitable units on or before February 28, 2025.
Delay condonation
The Tribunal directed the appellant/promoter to hand over possession of the unit on or before the next hearing date, which is scheduled for 30.01.2025.
Delay condonation
The Tribunal granted the appellant time to file a reply to the respondent's objections regarding compliance with Section 43(5) of the Act and scheduled the matter for orders on 15.01.2025.
Delay condonation
The Tribunal granted a request for adjournment filed by the appellant's counsel and scheduled the case for orders on December 3, 2024.
Delay condonation
The Tribunal granted the appellant a final seven-day extension to file objections against a recall application, with the respondent permitted to reply within one week thereafter.
Delay condonation
The Tribunal adjourned the proceedings for Appeal-49/2024 following an adjournment application filed by the respondent's counsel, rescheduling the hearing for 24.09.2024.
Delay condonation
The Tribunal granted the appellant seven days to file objections against a recall application and scheduled the next hearing for August 21, 2024.
Delay condonation
The Tribunal granted the respondent a final 10-day extension to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for 22.07.2024.
Delay condonation
The Tribunal has scheduled the appeal for orders/hearing on 22.05.2024 due to the absence of the respondent's counsel.
Delay condonation
The Tribunal granted the applicant 10 days to file objections and a vakalatnama, and scheduled the recall application for hearing on 22.04.2024.
Delay condonation
The Tribunal noted the appearance of counsel for the applicant and scheduled the defective appeal for orders on 14.03.2024.
Delay condonation
The Tribunal has issued a routine procedural order to list the appeal on 05.03.2024.
Tribunal Order #0901126027142023-14-10-2025
The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000/- to be paid to the respondent by the next hearing date on 07.11.2025.
Tribunal Order #0901126027142023-15-01-2025
The Tribunal directed the appellant/promoter to hand over possession of the unit on or before the next hearing date, which is scheduled for 30.01.2025.
Tribunal Order #0901126027142023-12-12-2025
The Tribunal dismissed the developer's appeal and ruled that the promoter must pay delay interest to allottees, execute supplementary deeds to correct omitted plot/exclusive areas, refund mandatory club fees, and face investigation for fraudulent practices and statutory violations.
Tribunal Order #0901126027142023-09-04-2025
The Tribunal admitted the appeal and accepted the appellant's undertaking to reverse the Advance Payment Rebate (APR) error and execute a correction deed for the sub-lease deed to include the exclusive area.
Tribunal Order #0901126027142023-12-03-2025
The Appellant/Promoter submitted an undertaking to hand over possession of the unit before the next hearing date following the deposit of sale consideration, which the Tribunal accepted.
Tribunal Order #0901126027142023-30-01-2025
The Tribunal accepted an undertaking from the appellant to hand over the letter of offer of possession and a demand draft for costs to the respondents, with a commitment to provide physical possession of the habitable units on or before February 28, 2025.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the developer's appeal and ruled that the promoter must pay delay interest to allottees, execute supplementary deeds to correct omitted plot/exclusive areas, refund mandatory club fees, and face investigation for fraudulent practices and statutory violations. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the developer's appeal and ruled that the promoter must pay delay interest to allottees, execute supplementary deeds to correct omitted plot/exclusive areas, refund mandatory club fees, and face investigation for fraudulent practices and statutory violations.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR + 1 percent
Interest Period
from 02.03.2021 till the date of handing over physical possession of the unit, except for the Covid pandemic period w.e.f. 23.03.2020 to 25.09.2020
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Harish Pandey
Respondent Advocate(s)
- Dron Mishra
Official RERA Tribunal Orders (6)
The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000/- to be paid to the respondent by the next hearing date on 07.11.2025.
The Tribunal directed the appellant/promoter to hand over possession of the unit on or before the next hearing date, which is scheduled for 30.01.2025.
The Tribunal dismissed the developer's appeal and ruled that the promoter must pay delay interest to allottees, execute supplementary deeds to correct omitted plot/exclusive areas, refund mandatory club fees, and face investigation for fraudulent practices and statutory violations.
The Tribunal admitted the appeal and accepted the appellant's undertaking to reverse the Advance Payment Rebate (APR) error and execute a correction deed for the sub-lease deed to include the exclusive area.
The Appellant/Promoter submitted an undertaking to hand over possession of the unit before the next hearing date following the deposit of sale consideration, which the Tribunal accepted.
The Tribunal accepted an undertaking from the appellant to hand over the letter of offer of possession and a demand draft for costs to the respondents, with a commitment to provide physical possession of the habitable units on or before February 28, 2025.
Need to research all rulings for ar landcraft llp?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.