up_reraStatus: Active
CASE ID: 0901126025342024

Appellant / Complainant

Ar Landcraft Llp

VS

Respondent

Radhakrishnan Srinivasan

Developer Firm

ar landcraft llp

Disputed Amount

1,89,55,746

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

39 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126025342024 by Ar Landcraft Llp against Radhakrishnan Srinivasan before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability
2
Stage 115/05/2026

Hearing

No text available.

3
Stage 221/04/2026

Hearing

No text available.

4
Stage 302/04/2026

Hearing

Upon a joint request from the parties, the appeal has been adjourned and rescheduled to be heard on 21.04.2026 before Bench No. 2.

5
Stage 412/03/2026

Hearing

No text available.

6
Stage 517/02/2026

Hearing

The Tribunal granted a request from both counsels to adjourn the matter and list the appeal along with several other related appeals for final hearing on 12.03.2026.

7
Stage 605/02/2026

Hearing

The Tribunal noted that the appeal was wrongly listed for today and ordered it to be relisted on 17.02.2026 along with a bunch of other connected appeals.

8
Stage 712/12/2025

for delivery of Judgment/Order

The Tribunal dismissed the developer's appeal, directing the payment of delay interest to allottees, the execution of supplementary deeds to correct area/plot size discrepancies, the refund of mandatory club fees, and an investigation into potential collusion between the developer and GNIDA regarding land use violations.

9
Stage 807/11/2025

Further Hearing

The Tribunal has reserved its judgment in Appeal-196/2024 and directed both parties to file their written arguments within 10 days.

10
Stage 914/10/2025

Further Hearing

The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000/- to be paid to the respondent, while noting allegations of harassment and threats made by the appellant against the respondent.

11
Stage 1016/09/2025

Further Hearing

The Tribunal granted a request from the appellant's counsel to list the appeal for orders or hearing on 14.10.2025.

12
Stage 1111/08/2025

Hearing

The Tribunal adjourned the appeal to 16.09.2025 for further hearing and directed both parties to submit their written submissions.

13
Stage 1221/07/2025

Hearing

The Tribunal granted the appellant two weeks to file a rejoinder and directed the parties to exchange pleadings, scheduling the next hearing for August 11, 2025.

14
Stage 1329/05/2025

Hearing

The Tribunal directed the respondent promoter to pay the due APR amount to the appellant on or before the next hearing date, noting that the process for correcting the sublease deed is underway.

15
Stage 1405/05/2025

Hearing

The Tribunal granted the appellant ten days to file a rejoinder and allowed the respondent to file objections to the appellant's affidavit, scheduling the next hearing for May 29, 2025.

16
Stage 1509/04/2025

Delay condonation

The Tribunal admitted the appeal and accepted an undertaking from the appellant's Deputy Director to correct errors regarding the Advance Payment Rebate (APR) and the exclusion of exclusive area in the sub-lease deed.

17
Stage 1612/03/2025

Delay condonation

The Tribunal directed the appellant/promoter to summon their Accounts Officer with relevant records to explain alleged manipulation of interest accounts and ordered the filing of documents regarding the actual area of the unit to address claims of a 250 sq. ft. shortfall.

18
Stage 1730/01/2025

Delay condonation

The Tribunal accepted an undertaking from the appellant (AR Landcraft LLP) to hand over letters of offer of possession and demand drafts for costs, with a commitment to provide physical possession of the units by February 28, 2025.

19
Stage 1810/01/2025

Delay condonation

The Tribunal granted a final adjournment to the appellant subject to a penalty of Rs. 50,000 to be paid to the respondent, while clarifying that possession of the unit must be handed over free from all encumbrances.

20
Stage 1903/12/2024

Delay condonation

The appellant requested time to deposit the balance amount required under Section 43(5) of the Act 2016, and the matter is scheduled for hearing on the application for condonation of delay on 10.01.2025.

21
Stage 2014/11/2024

Delay condonation

The Tribunal adjourned the matter and imposed a cost of Rs. 15,000 on the appellant/promoter to be paid to the respondent, while also restraining the appellant from creating any third-party interest in the unit.

22
Stage 2104/10/2024

Delay condonation

The Tribunal has scheduled the appeal for orders/hearing on 14.11.2024.

23
Stage 2204/09/2024

Delay condonation

The appeal was adjourned at the request of the respondent's counsel due to an urgent matter in the High Court, with the next hearing scheduled for 04.10.2024.

24
Stage 2302/08/2024

Delay condonation

No text available.

25
Stage 2403/07/2024

Compliance of section 43(5)

The Tribunal noted the appellant's deposit of Rs. 56,89,111/- in compliance with Section 43(5) of the Act and granted the respondent 10 days to file objections to the condonation of delay application and grounds of appeal.

26
Stage 2519/06/2024

Defect Removal

The Tribunal granted the appellant a final 10-day extension to comply with Section 43(5) of the Act, warning that failure to comply will result in the dismissal of the defective appeal.

27
Stage 2612/06/2024

Defect Removal

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act 2016 and scheduled the defective appeal for orders on 19.06.2024.

28
Stage 27Interim Order

Tribunal Order #0901126025342024-03-12-2024

The appellant requested time to deposit the balance amount required under Section 43(5) of the Act 2016, and the matter is scheduled for hearing on the application for condonation of delay on 10.01.2025.

29
Stage 28Interim Order

Tribunal Order #0901126025342024-14-10-2025

The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000/- to be paid to the respondent, while noting allegations of harassment and threats made by the appellant against the respondent.

30
Stage 29Interim Order

Tribunal Order #0901126025342024-03-07-2024

The Tribunal noted the appellant's deposit of Rs. 56,89,111/- in compliance with Section 43(5) of the Act and granted the respondent 10 days to file objections to the condonation of delay application and grounds of appeal.

31
Stage 30Final Ruling Order

Tribunal Order #0901126025342024-12-12-2025

The Tribunal dismissed the developer's appeal, directing the payment of delay interest to allottees, the execution of supplementary deeds to correct area/plot size discrepancies, the refund of mandatory club fees, and an investigation into potential collusion between the developer and GNIDA regarding land use violations.

32
Stage 31Interim Order

Tribunal Order #0901126025342024-29-05-2025

The Tribunal directed the respondent promoter to pay the due APR amount to the appellant on or before the next hearing date, noting that the process for correcting the sublease deed is underway.

33
Stage 32Interim Order

Tribunal Order #0901126025342024-09-04-2025

The Tribunal admitted the appeal and accepted an undertaking from the appellant's Deputy Director to correct errors regarding the Advance Payment Rebate (APR) and the exclusion of exclusive area in the sub-lease deed.

34
Stage 33Interim Order

Tribunal Order #0901126025342024-12-03-2025

The Tribunal directed the appellant/promoter to summon their Accounts Officer with relevant records to explain alleged manipulation of interest accounts and ordered the filing of documents regarding the actual area of the unit to address claims of a 250 sq. ft. shortfall.

35
Stage 34Interim Order

Tribunal Order #0901126025342024-30-01-2025

The Tribunal accepted an undertaking from the appellant (AR Landcraft LLP) to hand over letters of offer of possession and demand drafts for costs, with a commitment to provide physical possession of the units by February 28, 2025.

36
Stage 35Interim Order

Tribunal Order #0901126025342024-10-01-2025

The Tribunal granted a final adjournment to the appellant subject to a penalty of Rs. 50,000 to be paid to the respondent, while clarifying that possession of the unit must be handed over free from all encumbrances.

37
Stage 36Interim Order

Tribunal Order #0901126025342024-14-11-2024

The Tribunal adjourned the matter and imposed a cost of Rs. 15,000 on the appellant/promoter to be paid to the respondent, while also restraining the appellant from creating any third-party interest in the unit.

38
Stage 37Interim Order

Tribunal Order #0901126025342024-19-06-2024

The Tribunal granted the appellant a final 10-day extension to comply with Section 43(5) of the Act, warning that failure to comply will result in the dismissal of the defective appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the developer's appeal, directing the payment of delay interest to allottees, the execution of supplementary deeds to correct area/plot size discrepancies, the refund of mandatory club fees, and an investigation into potential collusion between the developer and GNIDA regarding land use violations. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1 percent.

Disposal Winner: RespondentInterest Rate: MCLR + 1 percentStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the developer's appeal, directing the payment of delay interest to allottees, the execution of supplementary deeds to correct area/plot size discrepancies, the refund of mandatory club fees, and an investigation into potential collusion between the developer and GNIDA regarding land use violations.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1 percent

Interest Period

from 02.03.2021 till the date of handing over physical possession of the unit, except for the Covid pandemic period w.e.f. 23.03.2020 to 25.09.2020

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 12Section 11(4)(d)Section 19(6)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Syed Mohammad Abid
  • Saurabh Gauba

Respondent Advocate(s)

  • Dron Mishra

Official RERA Tribunal Orders (11)

INTERIM_ORDEROrder ID: 0901126025342024-03-12-2024

The appellant requested time to deposit the balance amount required under Section 43(5) of the Act 2016, and the matter is scheduled for hearing on the application for condonation of delay on 10.01.2025.

INTERIM_ORDEROrder ID: 0901126025342024-14-10-2025

The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000/- to be paid to the respondent, while noting allegations of harassment and threats made by the appellant against the respondent.

INTERIM_ORDEROrder ID: 0901126025342024-03-07-2024

The Tribunal noted the appellant's deposit of Rs. 56,89,111/- in compliance with Section 43(5) of the Act and granted the respondent 10 days to file objections to the condonation of delay application and grounds of appeal.

FINAL_ORDEROrder ID: 0901126025342024-12-12-2025

The Tribunal dismissed the developer's appeal, directing the payment of delay interest to allottees, the execution of supplementary deeds to correct area/plot size discrepancies, the refund of mandatory club fees, and an investigation into potential collusion between the developer and GNIDA regarding land use violations.

INTERIM_ORDEROrder ID: 0901126025342024-29-05-2025

The Tribunal directed the respondent promoter to pay the due APR amount to the appellant on or before the next hearing date, noting that the process for correcting the sublease deed is underway.

INTERIM_ORDEROrder ID: 0901126025342024-09-04-2025

The Tribunal admitted the appeal and accepted an undertaking from the appellant's Deputy Director to correct errors regarding the Advance Payment Rebate (APR) and the exclusion of exclusive area in the sub-lease deed.

INTERIM_ORDEROrder ID: 0901126025342024-12-03-2025

The Tribunal directed the appellant/promoter to summon their Accounts Officer with relevant records to explain alleged manipulation of interest accounts and ordered the filing of documents regarding the actual area of the unit to address claims of a 250 sq. ft. shortfall.

INTERIM_ORDEROrder ID: 0901126025342024-30-01-2025

The Tribunal accepted an undertaking from the appellant (AR Landcraft LLP) to hand over letters of offer of possession and demand drafts for costs, with a commitment to provide physical possession of the units by February 28, 2025.

INTERIM_ORDEROrder ID: 0901126025342024-10-01-2025

The Tribunal granted a final adjournment to the appellant subject to a penalty of Rs. 50,000 to be paid to the respondent, while clarifying that possession of the unit must be handed over free from all encumbrances.

INTERIM_ORDEROrder ID: 0901126025342024-14-11-2024

The Tribunal adjourned the matter and imposed a cost of Rs. 15,000 on the appellant/promoter to be paid to the respondent, while also restraining the appellant from creating any third-party interest in the unit.

INTERIM_ORDEROrder ID: 0901126025342024-19-06-2024

The Tribunal granted the appellant a final 10-day extension to comply with Section 43(5) of the Act, warning that failure to comply will result in the dismissal of the defective appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ar landcraft llp?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →