up_reraStatus: Completed
CASE ID: 0901126026652023

Appellant / Complainant

Gaursons Hi-Tech Infrastructure Private Limited

VS

Respondent

Kamini, Gopal Singh

Developer Firm

gaursons hi-tech infrastructure private limited

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126026652023 by Gaursons Hi-Tech Infrastructure Private Limited against Kamini, Gopal Singh before up_rera.

2
Stage 106/03/2025

Delay condonation

The Tribunal allowed the withdrawal of the appeal following an amicable settlement between the parties and directed the release of the amount deposited by the promoter under Section 43(5) of the Act 2016, including any accrued interest from fixed deposits, via RTGS.

3
Stage 228/02/2025

Delay condonation

The Tribunal has scheduled the appeal for hearing/orders on 06.03.2025 following a request to align its listing with similar matters.

4
Stage 304/02/2025

Delay condonation

The Tribunal has granted a request by the appellant's counsel to list the case for orders on 28.02.2025.

5
Stage 406/01/2025

Delay condonation

The Tribunal noted a settlement deed filed by the appellant and directed notice to be issued to the respondent to allow for statements or objections regarding the settlement before listing the matter on 04.02.2025.

6
Stage 518/11/2024

Delay condonation

The Tribunal granted a request for adjournment made by the appellant's counsel and rescheduled the appeal for hearing on 06.01.2025.

7
Stage 603/10/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 18.11.2024.

8
Stage 702/09/2024

Delay condonation

The Tribunal decided to proceed ex parte against the respondent due to their repeated failure to appear or file objections, and scheduled the matter for an ex-parte hearing on 03.10.2024.

9
Stage 831/07/2024

Delay condonation

No text available.

10
Stage 901/07/2024

Delay condonation

The Tribunal granted the respondent a final one-week extension to file objections to the application for condonation of delay and grounds of appeal, noting previous non-compliance.

11
Stage 1001/05/2024

Delay condonation

No text available.

12
Stage 1129/03/2024

Delay condonation

The Tribunal treated the service of notice on the respondent as sufficient and granted a 10-day extension for filing objections, with the next hearing scheduled for May 1, 2024.

13
Stage 1223/02/2024

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the defective appeal for consideration of a condonation of delay application on 29.03.2024.

14
Stage 1316/01/2024

Delay condonation

The Tribunal granted a one-week extension to the respondent for filing objections to the condonation of delay application and grounds of appeal, scheduling the next hearing for February 23, 2024.

15
Stage 1412/10/2023

Delay condonation

No text available.

16
Stage 1504/09/2023

Delay condonation

The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 12.10.2023.

17
Stage 1618/08/2023

Delay condonation

The Tribunal granted a one-week extension for the appellant to file an affidavit of service following an adjournment request due to counsel's health and rescheduled the hearing for September 4, 2023.

18
Stage 1703/07/2023

Delay condonation

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and outlined the procedural requirements for service of documents.

19
Stage 18Final Ruling Order

Tribunal Order #0901126026652023-06-03-2025

The Tribunal allowed the withdrawal of the appeal following an amicable settlement between the parties and directed the release of the amount deposited by the promoter under Section 43(5) of the Act 2016, including any accrued interest from fixed deposits, via RTGS.

20
Stage 19Interim Order

Tribunal Order #0901126026652023-06-01-2025

The Tribunal noted a settlement deed filed by the appellant and directed notice to be issued to the respondent to allow for statements or objections regarding the settlement before listing the matter on 04.02.2025.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the withdrawal of the appeal following an amicable settlement between the parties and directed the release of the amount deposited by the promoter under Section 43(5) of the Act 2016, including any accrued interest from fixed deposits, via RTGS. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the withdrawal of the appeal following an amicable settlement between the parties and directed the release of the amount deposited by the promoter under Section 43(5) of the Act 2016, including any accrued interest from fixed deposits, via RTGS.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 43(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Samrat Vaish
  • Mohit Yadav
  • Sangya Negi

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126026652023-06-03-2025

The Tribunal allowed the withdrawal of the appeal following an amicable settlement between the parties and directed the release of the amount deposited by the promoter under Section 43(5) of the Act 2016, including any accrued interest from fixed deposits, via RTGS.

INTERIM_ORDEROrder ID: 0901126026652023-06-01-2025

The Tribunal noted a settlement deed filed by the appellant and directed notice to be issued to the respondent to allow for statements or objections regarding the settlement before listing the matter on 04.02.2025.

TathyaGrid RERA Intelligence AI

Need to research all rulings for gaursons hi-tech infrastructure private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →