Appellant / Complainant
Arun Chauhan
Respondent
Gaursons Hi-Tech Infrastructure Private Limited
gaursons hi-tech infrastructure private limited
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126025542021 by Arun Chauhan against Gaursons Hi-Tech Infrastructure Private Limited before up_rera.
for delivery of Judgment/Order
The Tribunal partially allowed the appeal, modifying the RERA order to grant the appellant interest for delayed possession from 01.07.2019 to 19.03.2021, while excluding periods attributed to COVID-19 and environmental construction bans.
Hearing on Appeal
The Tribunal heard arguments from the appellant in person and the respondent's representative via video conferencing, subsequently reserving the judgment for a later date.
Hearing on Appeal
The Tribunal directed the respondent to produce the NGT order regarding construction stoppage within one week and scheduled the appeal for a hearing on 31.08.2021.
Hearing on Appeal
The Tribunal adjourned the appeal to 16.08.2021 and issued a warning that the matter may proceed ex parte if the respondent fails to appear.
Hearing on Appeal
The Tribunal directed the respondent to explain its failure to comply with a previous order for unit possession and granted the appellant 10 days to file a reply to the respondent's objections.
Hearing on Appeal
The Tribunal issued notice to the respondent and established a procedural timeline for the exchange of appeal documents and objections via email and the e-portal.
Tribunal Order #0901126025542021-07-10-2021
The Tribunal partially allowed the appeal, modifying the RERA order to grant the appellant interest for delayed possession from 01.07.2019 to 19.03.2021, while excluding periods attributed to COVID-19 and environmental construction bans.
Tribunal Order #0901126025542021-16-07-2021
The Tribunal directed the respondent to explain its failure to comply with a previous order for unit possession and granted the appellant 10 days to file a reply to the respondent's objections.
Tribunal Disposal & Final Award Ruling
The Tribunal partially allowed the appeal, modifying the RERA order to grant the appellant interest for delayed possession from 01.07.2019 to 19.03.2021, while excluding periods attributed to COVID-19 and environmental construction bans. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partially allowed the appeal, modifying the RERA order to grant the appellant interest for delayed possession from 01.07.2019 to 19.03.2021, while excluding periods attributed to COVID-19 and environmental construction bans.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR+1%
Interest Period
from 01.07.2019 till 19.03.2021, excluding the period from 25.03.2020 to 25.09.2020 and 116 days on account of restriction/ban imposed by the Environment Pollution (Prevention & Control) Authority, as well as vide order of Hon'ble Supreme Court dated 14.11.2019
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Applicant/Appellant In-Person
Respondent Advocate(s)
- D N Verma
Official RERA Tribunal Orders (2)
The Tribunal partially allowed the appeal, modifying the RERA order to grant the appellant interest for delayed possession from 01.07.2019 to 19.03.2021, while excluding periods attributed to COVID-19 and environmental construction bans.
The Tribunal directed the respondent to explain its failure to comply with a previous order for unit possession and granted the appellant 10 days to file a reply to the respondent's objections.