up_reraStatus: Completed
CASE ID: 0901126025542021

Appellant / Complainant

Arun Chauhan

VS

Respondent

Gaursons Hi-Tech Infrastructure Private Limited

Developer Firm

gaursons hi-tech infrastructure private limited

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126025542021 by Arun Chauhan against Gaursons Hi-Tech Infrastructure Private Limited before up_rera.

Delay in PossessionDelay Compensation / InterestMaintenance & Utility Disputes
2
Stage 107/10/2021

for delivery of Judgment/Order

The Tribunal partially allowed the appeal, modifying the RERA order to grant the appellant interest for delayed possession from 01.07.2019 to 19.03.2021, while excluding periods attributed to COVID-19 and environmental construction bans.

3
Stage 231/08/2021

Hearing on Appeal

The Tribunal heard arguments from the appellant in person and the respondent's representative via video conferencing, subsequently reserving the judgment for a later date.

4
Stage 316/08/2021

Hearing on Appeal

The Tribunal directed the respondent to produce the NGT order regarding construction stoppage within one week and scheduled the appeal for a hearing on 31.08.2021.

5
Stage 403/08/2021

Hearing on Appeal

The Tribunal adjourned the appeal to 16.08.2021 and issued a warning that the matter may proceed ex parte if the respondent fails to appear.

6
Stage 516/07/2021

Hearing on Appeal

The Tribunal directed the respondent to explain its failure to comply with a previous order for unit possession and granted the appellant 10 days to file a reply to the respondent's objections.

7
Stage 616/06/2021

Hearing on Appeal

The Tribunal issued notice to the respondent and established a procedural timeline for the exchange of appeal documents and objections via email and the e-portal.

8
Stage 7Final Ruling Order

Tribunal Order #0901126025542021-07-10-2021

The Tribunal partially allowed the appeal, modifying the RERA order to grant the appellant interest for delayed possession from 01.07.2019 to 19.03.2021, while excluding periods attributed to COVID-19 and environmental construction bans.

9
Stage 8Interim Order

Tribunal Order #0901126025542021-16-07-2021

The Tribunal directed the respondent to explain its failure to comply with a previous order for unit possession and granted the appellant 10 days to file a reply to the respondent's objections.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partially allowed the appeal, modifying the RERA order to grant the appellant interest for delayed possession from 01.07.2019 to 19.03.2021, while excluding periods attributed to COVID-19 and environmental construction bans. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.

Disposal Winner: PartialInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partially allowed the appeal, modifying the RERA order to grant the appellant interest for delayed possession from 01.07.2019 to 19.03.2021, while excluding periods attributed to COVID-19 and environmental construction bans.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.07.2019 till 19.03.2021, excluding the period from 25.03.2020 to 25.09.2020 and 116 days on account of restriction/ban imposed by the Environment Pollution (Prevention & Control) Authority, as well as vide order of Hon'ble Supreme Court dated 14.11.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Applicant/Appellant In-Person

Respondent Advocate(s)

  • D N Verma

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126025542021-07-10-2021

The Tribunal partially allowed the appeal, modifying the RERA order to grant the appellant interest for delayed possession from 01.07.2019 to 19.03.2021, while excluding periods attributed to COVID-19 and environmental construction bans.

INTERIM_ORDEROrder ID: 0901126025542021-16-07-2021

The Tribunal directed the respondent to explain its failure to comply with a previous order for unit possession and granted the appellant 10 days to file a reply to the respondent's objections.

TathyaGrid RERA Intelligence AI

Need to research all rulings for gaursons hi-tech infrastructure private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →