Appellant / Complainant
Nitin Gupta, Sakshi Shail
Respondent
Ar Landcraft Llp
ar landcraft llp
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126023792025 by Nitin Gupta, Sakshi Shail against Ar Landcraft Llp before up_rera.
Delay condonation
The appellant withdrew the appeal with liberty to file an application before UP RERA seeking an expedited hearing of the original complaint.
Delay condonation
The Tribunal has adjourned the matter to 16.02.2026 for orders, following a joint request from the counsel for both parties.
Delay condonation
The Tribunal granted the appellant 15 days to file a rejoinder affidavit and scheduled the matter for orders on January 12, 2026.
Delay condonation
The Respondent (promoter) has committed to endeavoring to execute conveyance deeds within 30 days and handover physical possession of the units in habitable condition within 45 days thereafter, or 30 days if the deed is already executed.
Delay condonation
The Tribunal noted the appellant's claim regarding non-execution of sub-lease deed and non-delivery of possession, and subsequently listed the appeal for hearing on 06.11.2025.
Delay condonation
The Tribunal granted the respondent time to seek instructions and file objections, subsequently listing the matter for hearing on 13.10.2025.
Delay condonation
The Tribunal granted the respondent time to file objections and scheduled the next hearing for September 15, 2025, following arguments regarding a final demand letter issued by the respondent.
Delay condonation
The Tribunal issued a notice to the respondent and provided specific procedural instructions for the service of the appeal and application for condonation of delay.
Tribunal Order #0901126023792025-06-11-2025
The Respondent (promoter) has committed to endeavoring to execute conveyance deeds within 30 days and handover physical possession of the units in habitable condition within 45 days thereafter, or 30 days if the deed is already executed.
Tribunal Disposal & Final Award Ruling
Dismissed as withdrawn Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed as withdrawn
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Dron Mishra
Respondent Advocate(s)
- Syed Mohammad Abid
- Saurabh Gauba
Official RERA Tribunal Orders (1)
The Respondent (promoter) has committed to endeavoring to execute conveyance deeds within 30 days and handover physical possession of the units in habitable condition within 45 days thereafter, or 30 days if the deed is already executed.
Need to research all rulings for ar landcraft llp?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.