up_reraStatus: Completed
CASE ID: 0901126023142022

Appellant / Complainant

Gaursons Hi-Tech Infrastructure Private Limited

VS

Respondent

Meenal Singh

Developer Firm

gaursons hi-tech infrastructure private limited

Disputed Amount

57,61,694

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

35 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126023142022 by Gaursons Hi-Tech Infrastructure Private Limited against Meenal Singh before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 123/01/2025

Hearing

The Tribunal dismissed the promoter's appeal, ruling that the allottee is entitled to interest at MCLR+1% until the date of possession or execution of the conveyance deed, and ordered the promoter to execute the deed and pay rent as compensation for the delay.

3
Stage 203/01/2025

Delay condonation

The Tribunal granted an adjournment requested by the counsel for the appellant and rescheduled the appeal for hearing on 23.01.2025.

4
Stage 313/12/2024

Delay condonation

The Tribunal allowed the appellant's application for condonation of delay, citing COVID-19 as a sufficient cause for the 12-day delay, and directed the Registry to convert the defective appeal into a regular appeal.

5
Stage 413/11/2024

Hearing

The tribunal adjourned the proceedings following an adjournment request by the respondent's counsel and scheduled the matter for December 13, 2024, to consider the application for condonation of delay.

6
Stage 515/10/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 13.11.2024.

7
Stage 604/09/2024

Hearing

Upon a joint request from the counsels for both parties, the tribunal has adjourned the appeal to be listed for hearing or orders on 15.10.2024.

8
Stage 702/08/2024

Hearing

No text available.

9
Stage 804/07/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to a personal emergency and rescheduled the hearing for August 2, 2024.

10
Stage 906/05/2024

Hearing

The Tribunal granted a request for adjournment from both parties and rescheduled the hearing for the application for condonation of delay to 04.07.2024.

11
Stage 1003/04/2024

Hearing

The Tribunal noted that the appeal is currently defective and ordered it to be listed for a hearing on May 6, 2024.

12
Stage 1128/02/2024

Delay condonation

The Tribunal has ordered the appeal to be listed for a hearing on 03.04.2024.

13
Stage 1218/01/2024

Delay condonation

The Tribunal has scheduled the defective appeal for consideration of the application for condonation of delay and a subsequent hearing on 28.02.2024.

14
Stage 1316/10/2023

Delay condonation

No text available.

15
Stage 1406/09/2023

Delay condonation

The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for October 16, 2023.

16
Stage 1518/07/2023

Delay condonation

The Tribunal granted the respondent one week to file objections to a proposed amendment application and scheduled the matter for consideration on 06.09.2023.

17
Stage 1617/07/2023

Delay condonation

The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the hearing for July 18, 2023.

18
Stage 1706/07/2023

Delay condonation

The Tribunal granted a request to list the appeal for orders on 17.07.2023 and directed the respondent to file objections to the application for condonation of delay and the grounds of appeal in the interim.

19
Stage 1819/05/2023

Delay condonation

The Tribunal granted the appellant 24 hours to upload an application for amendment to the prayer clause and scheduled the matter for hearing on July 6, 2023.

20
Stage 1907/04/2023

Delay condonation

No text available.

21
Stage 2027/02/2023

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for consideration of the application for condonation of delay to 07.04.2023.

22
Stage 2125/01/2023

Delay condonation

No text available.

23
Stage 2215/12/2022

Delay condonation

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the defective appeal for hearing on 25.01.2023.

24
Stage 2308/12/2022

Delay condonation

The Tribunal noted that no time remained during the hearing and ordered the defective appeal to be listed on 15.12.2022 for further orders.

25
Stage 2411/11/2022

Delay condonation

The Tribunal directed the appellant to file an amendment application regarding the prayer clause and scheduled the defective appeal for further orders on 08.12.2022.

26
Stage 2511/10/2022

Delay condonation

The Tribunal directed the appellant to ensure full compliance with Section 43(5) of the Act and scheduled the matter for 11.11.2022 to address the delay condonation application and statutory compliance.

27
Stage 2605/09/2022

Delay condonation

The Tribunal adjourned the matter to 11.10.2022 because the counsel for the appellant was on sanctioned leave.

28
Stage 2708/08/2022

Delay condonation

The Tribunal granted the respondent an additional week to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for September 5, 2022.

29
Stage 2819/07/2022

Delay condonation

The Tribunal directed the respondent's counsel to register on the e-portal and granted 10 days to file objections to the condonation of delay application and grounds of appeal.

30
Stage 2920/06/2022

Defect Removal

The Tribunal issued notice to the respondent regarding an application for condonation of delay and directed the Registry to verify the statutory deposit made under Section 43(5) of the Act.

31
Stage 30Final Ruling Order

Tribunal Order #0901126023142022-23-01-2025

The Tribunal dismissed the promoter's appeal, ruling that the allottee is entitled to interest at MCLR+1% until the date of possession or execution of the conveyance deed, and ordered the promoter to execute the deed and pay rent as compensation for the delay.

32
Stage 31Interim Order

Tribunal Order #0901126023142022-13-12-2024

The Tribunal allowed the appellant's application for condonation of delay, citing COVID-19 as a sufficient cause for the 12-day delay, and directed the Registry to convert the defective appeal into a regular appeal.

33
Stage 32Interim Order

Tribunal Order #0901126023142022-20-06-2022

The Tribunal issued notice to the respondent regarding an application for condonation of delay and directed the Registry to verify the statutory deposit made under Section 43(5) of the Act.

34
Stage 33Interim Order

Tribunal Order #0901126023142022-11-10-2022

The Tribunal directed the appellant to ensure full compliance with Section 43(5) of the Act and scheduled the matter for 11.11.2022 to address the delay condonation application and statutory compliance.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the promoter's appeal, ruling that the allottee is entitled to interest at MCLR+1% until the date of possession or execution of the conveyance deed, and ordered the promoter to execute the deed and pay rent as compensation for the delay. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% p.a..

Disposal Winner: RespondentInterest Rate: MCLR+1% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the promoter's appeal, ruling that the allottee is entitled to interest at MCLR+1% until the date of possession or execution of the conveyance deed, and ordered the promoter to execute the deed and pay rent as compensation for the delay.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1% p.a.

Interest Period

from 04.03.2020 till the date of possession/execution of conveyance deed whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Samrat Vaish

Respondent Advocate(s)

  • Suchita Singh

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126023142022-23-01-2025

The Tribunal dismissed the promoter's appeal, ruling that the allottee is entitled to interest at MCLR+1% until the date of possession or execution of the conveyance deed, and ordered the promoter to execute the deed and pay rent as compensation for the delay.

INTERIM_ORDEROrder ID: 0901126023142022-13-12-2024

The Tribunal allowed the appellant's application for condonation of delay, citing COVID-19 as a sufficient cause for the 12-day delay, and directed the Registry to convert the defective appeal into a regular appeal.

INTERIM_ORDEROrder ID: 0901126023142022-20-06-2022

The Tribunal issued notice to the respondent regarding an application for condonation of delay and directed the Registry to verify the statutory deposit made under Section 43(5) of the Act.

INTERIM_ORDEROrder ID: 0901126023142022-11-10-2022

The Tribunal directed the appellant to ensure full compliance with Section 43(5) of the Act and scheduled the matter for 11.11.2022 to address the delay condonation application and statutory compliance.

TathyaGrid RERA Intelligence AI