up_reraStatus: Completed
CASE ID: 0901126021402022

Appellant / Complainant

Sachinder Mohan Mehta

VS

Respondent

Elegant Infracon Private Limited

Developer Firm

elegant infracon private limited

Disputed Amount

14,63,201

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

24 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126021402022 by Sachinder Mohan Mehta against Elegant Infracon Private Limited before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 110/02/2026

for delivery of Judgment/Order

The Uttar Pradesh Real Estate Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the entire deposited amounts to both appellants with interest at MCLR + 1% due to project delays.

3
Stage 217/11/2025

Hearing

The Tribunal heard arguments from both the appellant and respondent regarding Appeal-18/2023 and subsequently reserved its judgment.

4
Stage 314/11/2025

Hearing

The Tribunal directed the respondent to upload specific documents in compliance with a previous order and provided a new hearing date of 17.11.2025.

5
Stage 415/10/2025

Hearing

The Tribunal granted the respondent a final 10-day extension to file documents regarding the point of force majeure and scheduled the next hearing for November 14, 2025.

6
Stage 509/09/2025

Hearing

The Tribunal granted the respondent seven days to file documents and scheduled the appeal for a hearing on 15.10.2025.

7
Stage 628/08/2025

Hearing

The Tribunal granted the respondent one week to file documents concerning NGT orders and Section 8 proceedings, and scheduled the next hearing for September 9, 2025.

8
Stage 712/08/2025

Delay condonation

The Tribunal allowed the application for condonation of delay, ruling that the appeal was filed within the limitation period extended by the Supreme Court, and directed the Registry to convert the defective appeal into a regular appeal.

9
Stage 822/07/2025

Delay condonation

The Tribunal granted the appellant a final 10-day extension to file a better affidavit for condonation of delay, noting that failure to do so will result in automatic dismissal of the appeal.

10
Stage 921/07/2025

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to the unavailability of their senior counsel and rescheduled the matter for hearing on 22.07.2025.

11
Stage 1010/07/2025

For Order

The parties reported that an amicable settlement could not be reached and requested time to prepare arguments; consequently, the tribunal adjourned the matter for a final hearing on 21.07.2025.

12
Stage 1119/05/2025

For Order

The parties informed the Tribunal that they are negotiating an amicable settlement; consequently, the matter has been adjourned to 10.07.2025.

13
Stage 1212/05/2025

For Order

The Tribunal noted the respondent's proposal for an amicable settlement and adjourned the matter to 19.05.2025 to allow the appellant to seek instructions.

14
Stage 1323/04/2025

For Order

The Tribunal granted the appellant seven days to deposit a specified cost amount and scheduled the matter for further orders on May 12, 2025.

15
Stage 1405/07/2023

Delay condonation

The U.P. Real Estate Appellate Tribunal dismissed the defective appeal (APPEAL-18/2023) due to the non-appearance of the appellant and their legal representative.

16
Stage 1502/05/2023

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on July 5, 2023.

17
Stage 1621/03/2023

Delay condonation

No text available.

18
Stage 1713/02/2023

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the matter for hearing on March 21, 2023.

19
Stage 1810/01/2023

Delay condonation

The Tribunal noted a delay in filing the appeal and ordered notice to be issued to the respondent regarding the application for condonation of delay, scheduling the matter for hearing on 13.02.2023.

20
Stage 19Final Ruling Order

Tribunal Order #0901126021402022-10-02-2026

The Uttar Pradesh Real Estate Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the entire deposited amounts to both appellants with interest at MCLR + 1% due to project delays.

21
Stage 20Interim Order

Tribunal Order #0901126021402022-23-04-2025

The Tribunal granted the appellant seven days to deposit a specified cost amount and scheduled the matter for further orders on May 12, 2025.

22
Stage 21Final Ruling Order

Tribunal Order #0901126021402022-05-07-2023

The U.P. Real Estate Appellate Tribunal dismissed the defective appeal (APPEAL-18/2023) due to the non-appearance of the appellant and their legal representative.

23
Stage 22Interim Order

Tribunal Order #0901126021402022-12-08-2025

The Tribunal allowed the application for condonation of delay, ruling that the appeal was filed within the limitation period extended by the Supreme Court, and directed the Registry to convert the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Uttar Pradesh Real Estate Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the entire deposited amounts to both appellants with interest at MCLR + 1% due to project delays. The U.P. Real Estate Appellate Tribunal dismissed the defective appeal (APPEAL-18/2023) due to the non-appearance of the appellant and their legal representative. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Uttar Pradesh Real Estate Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the entire deposited amounts to both appellants with interest at MCLR + 1% due to project delays. The U.P. Real Estate Appellate Tribunal dismissed the defective appeal (APPEAL-18/2023) due to the non-appearance of the appellant and their legal representative.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

from the date of deposit till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Sourabh Gupta

Respondent Advocate(s)

  • Siddharth Singh
  • Fuhar Gupta

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126021402022-10-02-2026

The Uttar Pradesh Real Estate Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the entire deposited amounts to both appellants with interest at MCLR + 1% due to project delays.

INTERIM_ORDEROrder ID: 0901126021402022-23-04-2025

The Tribunal granted the appellant seven days to deposit a specified cost amount and scheduled the matter for further orders on May 12, 2025.

FINAL_ORDEROrder ID: 0901126021402022-05-07-2023

The U.P. Real Estate Appellate Tribunal dismissed the defective appeal (APPEAL-18/2023) due to the non-appearance of the appellant and their legal representative.

INTERIM_ORDEROrder ID: 0901126021402022-12-08-2025

The Tribunal allowed the application for condonation of delay, ruling that the appeal was filed within the limitation period extended by the Supreme Court, and directed the Registry to convert the defective appeal into a regular appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for elegant infracon private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →