up_reraStatus: Completed
CASE ID: 0901126019892022

Appellant / Complainant

U.P. Awas Evam Vikas Parishad

VS

Respondent

Arun Kumar Dwivedi

Developer Firm

u.p. awas evam vikas parishad

Disputed Amount

16,60,000

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

9 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126019892022 by U.P. Awas Evam Vikas Parishad against Arun Kumar Dwivedi before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 105/09/2022

Hearing

The Tribunal partly allowed the appeal, modifying the interest period for the appellant to pay interest on the flat cost from 30.10.2015 to 11.02.2020 based on a reasonable construction period of 36 months, and directed the release of deposited funds accordingly.

3
Stage 216/08/2022

Hearing

The Tribunal directed the Registry to verify and upload the respondent's objections to the e-portal and scheduled the defective appeal for a hearing on 05.09.2022.

4
Stage 318/07/2022

Notice

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's order regarding extension of limitation, and directed the registry to convert the defective appeal into a regular appeal.

5
Stage 431/05/2022

Notice

The Tribunal granted the respondent 15 days to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent week allowed for the applicant to reply. The matter is scheduled for hearing on 18.07.2022.

6
Stage 505/05/2022

Defect Removal

The Tribunal issued notice to the respondent regarding the appeal and directed the applicant to serve the notice via speed-post and email, with the matter listed for 31.05.2022 to consider the application for condonation of delay.

7
Stage 628/04/2022

Defect Removal

The Tribunal noted procedural defects in the appeal filing and directed the appellant to upload missing documents, including the Authority Letter, respondent's email ID, and a C.A. Certificate, before the next hearing on 05.05.2022.

8
Stage 7Final Ruling Order

Tribunal Order #0901126019892022-05-09-2022

The Tribunal partly allowed the appeal, modifying the interest period for the appellant to pay interest on the flat cost from 30.10.2015 to 11.02.2020 based on a reasonable construction period of 36 months, and directed the release of deposited funds accordingly.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partly allowed the appeal, modifying the interest period for the appellant to pay interest on the flat cost from 30.10.2015 to 11.02.2020 based on a reasonable construction period of 36 months, and directed the release of deposited funds accordingly. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.

Disposal Winner: PartialInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partly allowed the appeal, modifying the interest period for the appellant to pay interest on the flat cost from 30.10.2015 to 11.02.2020 based on a reasonable construction period of 36 months, and directed the release of deposited funds accordingly.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1%

Interest Period

from 30.10.2015 to 11.02.2020

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shikhar Srivastava

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126019892022-05-09-2022

The Tribunal partly allowed the appeal, modifying the interest period for the appellant to pay interest on the flat cost from 30.10.2015 to 11.02.2020 based on a reasonable construction period of 36 months, and directed the release of deposited funds accordingly.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. awas evam vikas parishad?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →