Appellant / Complainant
U.P. Awas Evam Vikas Parishad
Respondent
Arun Kumar Dwivedi
u.p. awas evam vikas parishad
₹16,60,000
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126019892022 by U.P. Awas Evam Vikas Parishad against Arun Kumar Dwivedi before up_rera.
Hearing
The Tribunal partly allowed the appeal, modifying the interest period for the appellant to pay interest on the flat cost from 30.10.2015 to 11.02.2020 based on a reasonable construction period of 36 months, and directed the release of deposited funds accordingly.
Hearing
The Tribunal directed the Registry to verify and upload the respondent's objections to the e-portal and scheduled the defective appeal for a hearing on 05.09.2022.
Notice
The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's order regarding extension of limitation, and directed the registry to convert the defective appeal into a regular appeal.
Notice
The Tribunal granted the respondent 15 days to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent week allowed for the applicant to reply. The matter is scheduled for hearing on 18.07.2022.
Defect Removal
The Tribunal issued notice to the respondent regarding the appeal and directed the applicant to serve the notice via speed-post and email, with the matter listed for 31.05.2022 to consider the application for condonation of delay.
Defect Removal
The Tribunal noted procedural defects in the appeal filing and directed the appellant to upload missing documents, including the Authority Letter, respondent's email ID, and a C.A. Certificate, before the next hearing on 05.05.2022.
Tribunal Order #0901126019892022-05-09-2022
The Tribunal partly allowed the appeal, modifying the interest period for the appellant to pay interest on the flat cost from 30.10.2015 to 11.02.2020 based on a reasonable construction period of 36 months, and directed the release of deposited funds accordingly.
Tribunal Disposal & Final Award Ruling
The Tribunal partly allowed the appeal, modifying the interest period for the appellant to pay interest on the flat cost from 30.10.2015 to 11.02.2020 based on a reasonable construction period of 36 months, and directed the release of deposited funds accordingly. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partly allowed the appeal, modifying the interest period for the appellant to pay interest on the flat cost from 30.10.2015 to 11.02.2020 based on a reasonable construction period of 36 months, and directed the release of deposited funds accordingly.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR+1%
Interest Period
from 30.10.2015 to 11.02.2020
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shikhar Srivastava
Respondent Advocate(s)
- Amit Yadav
Official RERA Tribunal Orders (1)
The Tribunal partly allowed the appeal, modifying the interest period for the appellant to pay interest on the flat cost from 30.10.2015 to 11.02.2020 based on a reasonable construction period of 36 months, and directed the release of deposited funds accordingly.
Need to research all rulings for u.p. awas evam vikas parishad?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.