up_reraStatus: Active
CASE ID: 0901126017502020

Appellant / Complainant

Ajay Kumar Srivastava

VS

Respondent

Sahara Prime City Ltd.

Developer Firm

sahara prime city ltd.

Disputed Amount

30,45,900

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126017502020 by Ajay Kumar Srivastava against Sahara Prime City Ltd. before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestNon-Compliance & Execution
2
Stage 107/11/2022

For Order

The Tribunal noted that the records of the Regulatory Authority were never summoned; consequently, no records could be transmitted back, and the file was ordered to be consigned to the record room.

3
Stage 212/10/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal set aside the Regulatory Authority's order and directed Sahara Prime City Ltd. to refund the total amount deposited by the appellants with interest at MCLR+1% per annum from the date of deposit until actual payment.

4
Stage 307/03/2022

Further Order

No text available.

5
Stage 404/01/2022

Further Order

The court heard arguments from the appellant's counsel and reserved the judgment for further consideration.

6
Stage 529/11/2021

For Order

The Tribunal directed both counsels to exchange a list of dates, events, and relied-upon cases before the next hearing, which is scheduled for 04.01.2022.

7
Stage 608/11/2021

Further Order

The Tribunal granted the respondent one week to file their Vakalat Nama and reply to the appeal, directing that a copy be emailed to the appellant before the next hearing on 29.11.2021.

8
Stage 720/09/2021

Hearing

The Tribunal directed the respondent's counsel to file a Vakalat Nama and a reply to the grounds of appeal before the next hearing date.

9
Stage 820/04/2021

Hearing

No text available.

10
Stage 922/03/2021

Hearing

The Tribunal directed the respondent to file their vakalatnama and a reply to the grounds of appeal within specified timeframes, with the case scheduled for hearing on 20.04.2021.

11
Stage 1004/03/2021

Ex-Parte

The appeal was adjourned due to a lawyers' strike, with the court directing the parties to exchange pleadings and rescheduling the defective appeal for 22.03.2021.

12
Stage 1115/02/2021

Notice

The Tribunal adjourned the appeal to 04.03.2021 due to the respondent's absence and issued a warning that the matter may be heard ex-parte on the next date.

13
Stage 1202/02/2021

Defect Removal

The Tribunal converted the defective appeal into a regular appeal and directed that notice be re-issued to the respondent via email within five days.

14
Stage 1312/01/2021

Defect Removal

No text available.

15
Stage 14Final Ruling Order

Tribunal Order #0901126017502020-12-10-2022

The U.P. Real Estate Appellate Tribunal set aside the Regulatory Authority's order and directed Sahara Prime City Ltd. to refund the total amount deposited by the appellants with interest at MCLR+1% per annum from the date of deposit until actual payment.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal set aside the Regulatory Authority's order and directed Sahara Prime City Ltd. to refund the total amount deposited by the appellants with interest at MCLR+1% per annum from the date of deposit until actual payment. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% p.a..

Disposal Winner: AppellantInterest Rate: MCLR + 1% p.a.Status: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal set aside the Regulatory Authority's order and directed Sahara Prime City Ltd. to refund the total amount deposited by the appellants with interest at MCLR+1% per annum from the date of deposit until actual payment.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% p.a.

Interest Period

from the date of deposit till the date of actual payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shailender Singh

Respondent Advocate(s)

  • Surendra Kumar Mishra

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126017502020-12-10-2022

The U.P. Real Estate Appellate Tribunal set aside the Regulatory Authority's order and directed Sahara Prime City Ltd. to refund the total amount deposited by the appellants with interest at MCLR+1% per annum from the date of deposit until actual payment.