Appellant / Complainant
Panchsheel Buildtech Pvt. Ltd.
Respondent
Syed Mohammad Abbas
panchsheel buildtech pvt. ltd.
₹24,43,929
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126016692020 by Panchsheel Buildtech Pvt. Ltd. against Syed Mohammad Abbas before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal dismissed the promoter's appeal against a Regulatory Authority order, upholding the requirement to provide an alternative unit or refund the amount paid with interest, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.
Final Hearing
The court heard arguments from both parties and reserved the judgment for a later date.
Final Hearing
The Tribunal noted the absence of a stay order and granted the respondent liberty to file an execution petition before the Regulatory Authority; the matter is scheduled for further hearing on 05.01.2022.
Final Hearing
The Tribunal noted that the matter is part-heard and ordered the appeal to be listed on 22.12.2021 before Bench No. 1.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for December 1, 2021.
Hearing
The Tribunal granted the appellant permission to amend the prayer clause to challenge only direction no. 2 of the impugned order and adjourned the matter to 15.11.2021 following a joint request for potential settlement.
Exchange of pleadings
The Tribunal adjourned the appeal to 25.10.2021 following a joint request from counsel indicating that settlement negotiations between the parties are ongoing.
For Order
The appeal was dismissed for want of prosecution because no one appeared on behalf of the appellant to press the application.
Tribunal Order #0901126016692020-23-03-2022
The Appellate Tribunal dismissed the promoter's appeal against a Regulatory Authority order, upholding the requirement to provide an alternative unit or refund the amount paid with interest, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the promoter's appeal against a Regulatory Authority order, upholding the requirement to provide an alternative unit or refund the amount paid with interest, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the promoter's appeal against a Regulatory Authority order, upholding the requirement to provide an alternative unit or refund the amount paid with interest, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Suyash Gupta
Respondent Advocate(s)
- Amit Asthana
Official RERA Tribunal Orders (1)
The Appellate Tribunal dismissed the promoter's appeal against a Regulatory Authority order, upholding the requirement to provide an alternative unit or refund the amount paid with interest, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.