Appellant / Complainant
Gaursons Hi-Tech Infrastructure Pvt. Ltd.
Respondent
Himanshu Talwar
gaursons hi-tech infrastructure pvt. ltd.
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126016552020 by Gaursons Hi-Tech Infrastructure Pvt. Ltd. against Himanshu Talwar before up_rera.
Final Hearing
The Tribunal set aside the RERA order dated 31.10.2019, ruling that the respondent's complaint was not maintainable because the project had received its completion certificate (OC/CC) prior to the enforcement of the RERA Act, 2016.
Final Hearing
Upon the request of the appellant's counsel, the matter has been adjourned to be heard on 29.08.2022.
Final Hearing
The Tribunal granted the appellant three days to file an appropriate application to set aside a RERA order, following a request based on Supreme Court precedent, and scheduled the next hearing for 26.08.2022.
Final Hearing
Upon the joint request of the counsels for both parties, the tribunal has rescheduled the hearing of the appeal to 18.08.2022.
Final Hearing
The Tribunal directed the respondent's counsel to file a reply/objection to the grounds of appeal within one week and scheduled the next hearing for 10.08.2022.
Final Hearing
The Tribunal granted the respondent an extension of 15 days to file a reply to the memo of appeal and directed the parties to exchange pleadings via e-portal/email before the next hearing on 25.07.2022.
Final Hearing
The Tribunal granted the respondent a final opportunity to file a reply to the grounds of appeal and adjourned the matter to 13.05.2022.
Final Hearing
The Tribunal adjourned the matter due to the non-appearance of the appellant's counsel and scheduled the next hearing for 11.04.2022.
Hearing
The Tribunal directed the appellant builder to execute the sale deed for the flat in favor of the respondent upon payment of required stamp fees and additional charges to the Greater Noida Development Authority.
Hearing
The Tribunal directed the appellant to issue a letter for physical inspection of the flat by 04.12.2021 and ordered the respondent to inspect the premises and proceed with the conveyance deed if no shortcomings are found.
Compliance of section 43(5)
The Tribunal granted an adjournment requested by the appellant's counsel due to personal illness and scheduled the next hearing for 23.11.2021.
Compliance of section 43(5)
The Tribunal rejected a misconceived application for amendment as the requested amendments had already been allowed previously; however, it granted the appellant three days to incorporate those amendments and comply with prior directions regarding CA certification and possession formalities.
For Order
The Tribunal adjourned the appeal to 22.03.2021 and directed the appellant to ensure compliance with a previous order dated 15.02.2021.
For Order
The Tribunal directed the appellant to ensure complete compliance with Section 43(5) of the Act within one week, warning that failure to do so by the next hearing may result in dismissal of the appeal.
Tribunal Order #0901126016552020-13-09-2022
The Tribunal set aside the RERA order dated 31.10.2019, ruling that the respondent's complaint was not maintainable because the project had received its completion certificate (OC/CC) prior to the enforcement of the RERA Act, 2016.
Tribunal Order #0901126016552020-04-10-2021
The Tribunal rejected a misconceived application for amendment as the requested amendments had already been allowed previously; however, it granted the appellant three days to incorporate those amendments and comply with prior directions regarding CA certification and possession formalities.
Tribunal Order #0901126016552020-10-12-2021
The Tribunal directed the appellant builder to execute the sale deed for the flat in favor of the respondent upon payment of required stamp fees and additional charges to the Greater Noida Development Authority.
Tribunal Order #0901126016552020-23-11-2021
The Tribunal directed the appellant to issue a letter for physical inspection of the flat by 04.12.2021 and ordered the respondent to inspect the premises and proceed with the conveyance deed if no shortcomings are found.
Tribunal Order #0901126016552020-15-02-2021
The Tribunal directed the appellant to ensure complete compliance with Section 43(5) of the Act within one week, warning that failure to do so by the next hearing may result in dismissal of the appeal.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the RERA order dated 31.10.2019, ruling that the respondent's complaint was not maintainable because the project had received its completion certificate (OC/CC) prior to the enforcement of the RERA Act, 2016. Awarded in favor of Appellant. Awarded interest rate: Rs. 5/- per sq. ft. per month.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the RERA order dated 31.10.2019, ruling that the respondent's complaint was not maintainable because the project had received its completion certificate (OC/CC) prior to the enforcement of the RERA Act, 2016.
Ruling Awarded To
Appellant
Awarded Interest Rate
Rs. 5/- per sq. ft. per month
Interest Period
w.e.f 21.09.2013 till receipt of OC/CC i.e. 29.04.2016
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- D N Verma
- Samrat Vaish
- Ankit Raj Chaudhary
Respondent Advocate(s)
- Rajesh Chadha
Official RERA Tribunal Orders (5)
The Tribunal set aside the RERA order dated 31.10.2019, ruling that the respondent's complaint was not maintainable because the project had received its completion certificate (OC/CC) prior to the enforcement of the RERA Act, 2016.
The Tribunal rejected a misconceived application for amendment as the requested amendments had already been allowed previously; however, it granted the appellant three days to incorporate those amendments and comply with prior directions regarding CA certification and possession formalities.
The Tribunal directed the appellant builder to execute the sale deed for the flat in favor of the respondent upon payment of required stamp fees and additional charges to the Greater Noida Development Authority.
The Tribunal directed the appellant to issue a letter for physical inspection of the flat by 04.12.2021 and ordered the respondent to inspect the premises and proceed with the conveyance deed if no shortcomings are found.
The Tribunal directed the appellant to ensure complete compliance with Section 43(5) of the Act within one week, warning that failure to do so by the next hearing may result in dismissal of the appeal.
Need to research all rulings for gaursons hi-tech infrastructure pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.