Appellant / Complainant
Dinesh Panwar
Respondent
Gaursons Hi-tech Infrastructure Pvt. Ltd.
gaursons hi-tech infrastructure pvt. ltd.
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126015022022 by Dinesh Panwar against Gaursons Hi-tech Infrastructure Pvt. Ltd. before up_rera.
Hearing
The appeal was dismissed as not pressed following a submission by the appellant's counsel that the parties have reached an amicable out-of-court settlement.
Hearing
The Tribunal granted a joint request from the parties to adjourn the appeal to 13.08.2025 and directed the parties to exchange pleadings in the interim.
Hearing
The Tribunal has adjourned the appeal to 22.07.2025 following a joint request from the counsel for both the appellant and the respondent.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for July 2, 2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal has adjourned the appeal to May 27, 2025, following a joint request from the counsels for both parties.
Hearing
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Dinesh Panwar due to the appellant's failure to appear and lack of prosecution.
Hearing
The Tribunal granted a request for adjournment made by the appellant's counsel and rescheduled the hearing for December 5, 2024.
Hearing
The Tribunal noted that amicable settlement processes are underway between the parties and adjourned the matter to 06.11.2024 to allow the respondent to seek instructions.
Hearing
Upon a joint request from both parties, the Tribunal has adjourned the appeal and rescheduled the matter for orders/hearing on 26.09.2024.
Hearing
Upon the joint request of the counsels for both parties, the Tribunal has adjourned the appeal for orders/hearing to 23.08.2024.
Hearing
The Tribunal granted a request for urgency and scheduled the appeal for orders or hearing on 17.05.2024.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 07.05.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the hearing for 04.04.2024.
Hearing
The Tribunal granted the appellant 10 days to file the original online complaint and clarify whether any amendments were sought in the prayer or grounds of the initial complaint.
Hearing
The Tribunal has scheduled the appeal for orders/hearing on 03-11-2023.
Hearing
The Tribunal has listed Appeal-590/2022 for a hearing on 21.09.2023 and referred to a previous order passed in a related appeal.
Hearing
The Tribunal has scheduled the case for hearing/orders on 26.05.2023 and directed reference to a previous order passed in Appeal No. (D) 416/2022.
Hearing
The Tribunal scheduled the case for orders/hearing on 25.04.2023 and referred to a previous order passed in Appeal No. 354/2022.
For Order
The Tribunal granted an adjournment requested by the appellant's counsel due to personal difficulty and rescheduled the hearing for 27.01.2023.
Delay condonation
The Tribunal granted a joint request from the counsels to reschedule the hearing for the application for condonation of delay to 20.12.2022.
Delay condonation
The Tribunal listed the defective appeal for November 24, 2022, to consider an application for condonation of delay and for hearing.
Delay condonation
This is a formal header of a court order from the U.P. Real Estate Appellate Tribunal regarding Appeal-590/2022 between Dinesh Panwar and Gaursons Hi-Tech Infrastructure Pvt. Ltd., dated September 28, 2022.
Delay condonation
The Tribunal directed the parties to exchange electronic copies of the appeal memo, objections, and replies within specified timelines and ordered the appeal to be listed for hearing on 09.09.2022.
Tribunal Order #0901126015022022-05-12-2024
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Dinesh Panwar due to the appellant's failure to appear and lack of prosecution.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Dinesh Panwar due to the appellant's failure to appear and lack of prosecution. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Dinesh Panwar due to the appellant's failure to appear and lack of prosecution.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Applicant/Appellant In-Person
- Praveen K Sharma
Respondent Advocate(s)
- Samrat Vaish
- Mohit Yadav
Official RERA Tribunal Orders (1)
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Dinesh Panwar due to the appellant's failure to appear and lack of prosecution.