up_reraStatus: Completed
CASE ID: 0901126009702023

Appellant / Complainant

Gaursons Hi-Tech Infrastructure Private Limited

VS

Respondent

Anil Kumar Srivastava, Hema Srivastava

Developer Firm

gaursons hi-tech infrastructure private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126009702023 by Gaursons Hi-Tech Infrastructure Private Limited against Anil Kumar Srivastava, Hema Srivastava before up_rera.

2
Stage 108/01/2025

Delay condonation

The appeal was dismissed as withdrawn following an amicable settlement between the parties, with a directive to release the amount deposited under Section 43(5) of the Act 2016 to the appellant-promoter.

3
Stage 227/11/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the hearing for the application for condonation of delay on 08.01.2025.

4
Stage 322/10/2024

Delay condonation

The parties have expressed an intent to explore an out-of-court settlement; consequently, the appeal has been adjourned and listed for further orders on 27.11.2024.

5
Stage 427/09/2024

Delay condonation

The Tribunal has scheduled the appeal for hearing/orders on 22.10.2024 to align with the listing of similar or connected matters.

6
Stage 528/08/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to his unavailability and scheduled the case for orders on 27.09.2024.

7
Stage 625/07/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to his unavailability and rescheduled the hearing for 28.08.2024.

8
Stage 729/05/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to personal illness and scheduled the matter for hearing on 25.07.2024.

9
Stage 827/05/2024

Delay condonation

The Tribunal has scheduled a hearing for May 29, 2024, to consider the appellant's application for condonation of delay, noting that no further adjournments will be granted on that date.

10
Stage 925/04/2024

Delay condonation

The Tribunal has listed the defective appeal for consideration of a condonation of delay application and subsequent hearing on 27.05.2024 due to the absence of the respondent's counsel.

11
Stage 1020/03/2024

Delay condonation

The Tribunal noted that the appeal is ripe for hearing and scheduled the matter for 25.04.2024 to consider an application for condonation of delay.

12
Stage 1121/02/2024

Delay condonation

The Tribunal granted a request for adjournment by the appellant's counsel and rescheduled the hearing for consideration of the application for condonation of delay to 20.03.2024.

13
Stage 1211/01/2024

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the hearing for the application for condonation of delay on 21.02.2024.

14
Stage 1304/01/2024

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for orders on 11.01.2024.

15
Stage 1427/09/2023

Delay condonation

No text available.

16
Stage 1514/08/2023

Delay condonation

No text available.

17
Stage 1631/05/2023

Delay condonation

The Tribunal issued notice to the respondents following the appellant's deposit of Rs. 50,000 as per Section 43(5) of the Act and scheduled the matter for hearing on 14.08.2023.

18
Stage 17Final Ruling Order

Tribunal Order #0901126009702023-08-01-2025

The appeal was dismissed as withdrawn following an amicable settlement between the parties, with a directive to release the amount deposited under Section 43(5) of the Act 2016 to the appellant-promoter.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal was dismissed as withdrawn following an amicable settlement between the parties, with a directive to release the amount deposited under Section 43(5) of the Act 2016 to the appellant-promoter. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal was dismissed as withdrawn following an amicable settlement between the parties, with a directive to release the amount deposited under Section 43(5) of the Act 2016 to the appellant-promoter.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Samrat Vaish
  • Mohit Yadav
  • Sangya Negi

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126009702023-08-01-2025

The appeal was dismissed as withdrawn following an amicable settlement between the parties, with a directive to release the amount deposited under Section 43(5) of the Act 2016 to the appellant-promoter.

TathyaGrid RERA Intelligence AI

Need to research all rulings for gaursons hi-tech infrastructure private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →