Appellant / Complainant
Rajeev Kumar Singh
Respondent
Paarth Infrabuild Pvt Ltd
paarth infrabuild pvt ltd
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126008252021 by Rajeev Kumar Singh against Paarth Infrabuild Pvt Ltd before up_rera.
Hearing
The appeal is disposed of following an out-of-court settlement where the respondent agreed to install a video door phone and intercom facility within 30 days and provided interim access to the Paarth Republic Stadium club facility while the project's club is under construction.
Hearing
The Tribunal directed the parties to explore a potential settlement, advising the appellant to visit the respondent's office on 16.04.2022, and listed the matter for further orders on 16.05.2022.
Hearing
The Tribunal directed the respondent builder to issue a fresh revised demand letter to the appellant and file it with the Registry, following arguments regarding the appellant's refusal to pay material cost escalation due to construction delays.
Hearing
The Tribunal noted the respondent's absence and an adjournment application, subsequently directing both parties to appear on the next scheduled date of 23.03.2022.
Hearing
The Tribunal adjourned the appeal due to the illness of the respondent's counsel and scheduled the next hearing for 21.01.2022.
Hearing
The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on January 4, 2022.
Hearing
The Tribunal granted the appellant 10 days to file a reply to the respondent's objection and directed the filing process via e-mail and the e-portal before the next hearing on 15.12.2021.
Hearing
The Tribunal granted an adjournment requested by the opposite party and rescheduled the appeal for hearing on 22.11.2021 to align with similar pending appeals.
Notice
The Tribunal directed the appellant to rectify insufficient postal stamps and serve notice to the respondent, while establishing a timeline for electronic exchange of appeal documents and objections.
Defect Removal
The Tribunal converted the defective appeal into a regular appeal after defects were removed and directed that notice be issued to the respondent.
Tribunal Order #0901126008252021-16-05-2022
The appeal is disposed of following an out-of-court settlement where the respondent agreed to install a video door phone and intercom facility within 30 days and provided interim access to the Paarth Republic Stadium club facility while the project's club is under construction.
Tribunal Order #0901126008252021-23-03-2022
The Tribunal directed the respondent builder to issue a fresh revised demand letter to the appellant and file it with the Registry, following arguments regarding the appellant's refusal to pay material cost escalation due to construction delays.
Tribunal Disposal & Final Award Ruling
The appeal is disposed of following an out-of-court settlement where the respondent agreed to install a video door phone and intercom facility within 30 days and provided interim access to the Paarth Republic Stadium club facility while the project's club is under construction. Awarded in favor of Partial.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The appeal is disposed of following an out-of-court settlement where the respondent agreed to install a video door phone and intercom facility within 30 days and provided interim access to the Paarth Republic Stadium club facility while the project's club is under construction.
Ruling Awarded To
Partial
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shailender Singh
Respondent Advocate(s)
- Rajiv Shukla
- Suyash Bajpai
Official RERA Tribunal Orders (2)
The appeal is disposed of following an out-of-court settlement where the respondent agreed to install a video door phone and intercom facility within 30 days and provided interim access to the Paarth Republic Stadium club facility while the project's club is under construction.
The Tribunal directed the respondent builder to issue a fresh revised demand letter to the appellant and file it with the Registry, following arguments regarding the appellant's refusal to pay material cost escalation due to construction delays.
Need to research all rulings for paarth infrabuild pvt ltd?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.