up_reraStatus: Active
CASE ID: 0901126006422024

Appellant / Complainant

Ar Landcraft LLP

VS

Respondent

Rahul Gupta

Developer Firm

ar landcraft llp

Disputed Amount

1,89,55,746

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

39 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126006422024 by Ar Landcraft LLP against Rahul Gupta before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability
2
Stage 115/05/2026

Hearing

No text available.

3
Stage 221/04/2026

Hearing

No text available.

4
Stage 302/04/2026

Hearing

The Tribunal granted a joint request to reschedule the appeal to be heard on 21.04.2026 before Bench No. 2.

5
Stage 412/03/2026

Hearing

No text available.

6
Stage 517/02/2026

Hearing

The Tribunal has listed Appeal-48/2024 for a final hearing on 12.03.2026, referring to a previous order passed in Appeal No. 196/2024.

7
Stage 605/02/2026

Hearing

The Tribunal directed that the appeal be listed on 17.02.2026, following the orders passed in Appeal No. 196 of 2024.

8
Stage 712/12/2025

for delivery of Judgment/Order

The Tribunal dismissed the developer's appeal and ruled that the promoter must pay delay interest to allottees, execute supplementary deeds to correct omitted plot/exclusive areas, refund mandatory club fees, and face potential penalties for fraudulent practices and statutory violations.

9
Stage 807/11/2025

Further Hearing

The Tribunal has reserved judgment in the appeal of AR Landcraft LLP versus Rahul Gupta and directed both parties to file written arguments within 10 days.

10
Stage 914/10/2025

Further Hearing

The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000/- to be paid to the respondent, noting previous orders regarding non-adjournment and prior penalties.

11
Stage 1016/09/2025

Further Hearing

The Tribunal has adjourned the appeal to 14.10.2025 for orders/hearing following a request from the appellant's counsel.

12
Stage 1111/08/2025

Hearing

The Tribunal heard arguments in the appeal and scheduled the matter for further hearing on 16.09.2025, directing parties to submit written submissions.

13
Stage 1221/07/2025

Hearing

The Tribunal granted the appellant two weeks to file a rejoinder and directed the parties to exchange pleadings, with the matter listed for hearing on 11.08.2025.

14
Stage 1329/05/2025

Hearing

The Tribunal noted the appellant's submission that the process for correcting the sublease deed is underway and adjourned the matter to 21.07.2025.

15
Stage 1405/05/2025

Hearing

The Tribunal granted the appellant ten days to file a rejoinder and permitted the respondent to file objections to the appellant's affidavit, scheduling the next hearing for May 29, 2025.

16
Stage 1509/04/2025

Hearing

The Tribunal admitted the appeal and accepted an undertaking from the appellant's Deputy Director to reverse Advance Payment Rebate (APR) errors and execute a correction deed for the sub-lease to include the exclusive area.

17
Stage 1612/03/2025

For Order

The appellant/promoter submitted that physical possession of the unit has been handed over to the allottee and the conveyance deed has been executed, which the Tribunal accepted and recorded.

18
Stage 1730/01/2025

For Order

The Appellant (AR Landcraft LLP) has undertaken to hand over letters of offer of possession and demand drafts to the respondent, with a commitment to provide physical possession of the habitable units on or before February 28, 2025.

19
Stage 1802/12/2024

Hearing

The appeal filed by AR Landcraft LLP was dismissed for non-prosecution due to the appellant's failure to appear or argue the case, with a directive for the RERA Authority to execute the impugned order.

20
Stage 1925/10/2024

Hearing

The Tribunal adjourned the matter to 02.12.2024 due to the appellant's failure to file a rejoinder, imposing a cost of Rs. 5,000/- to be paid by the appellant to the respondent.

21
Stage 2018/09/2024

For Order

The Tribunal granted the appellant seven days to file a rejoinder affidavit and scheduled the matter for orders on 25.10.2024.

22
Stage 2113/08/2024

For Order

The Tribunal noted that previous notices were not served on the respondent and ordered the issuance of fresh notice, directing the appellant to serve the respondent via speed-post and email before the next hearing on 18.09.2024.

23
Stage 2215/07/2024

For Order

No text available.

24
Stage 2315/05/2024

For Order

No text available.

25
Stage 2415/04/2024

Defect Removal

The Tribunal converted the defective appeal into a regular appeal after verifying that the appellant complied with the mandatory pre-deposit requirements under Section 43(5) of the Act and filed within the limitation period.

26
Stage 2528/03/2024

Defect Removal

The Tribunal granted the Appellant a final one-week extension to comply with Section 43(5) of the Act 2016, warning that failure to do so will result in the dismissal of the defective appeal.

27
Stage 2612/03/2024

Defect Removal

The Tribunal granted the appellant a one-week extension to ensure compliance with Section 43(5) of the Act and scheduled the defective appeal for further orders on 28.03.2024.

28
Stage 2701/03/2024

Defect Removal

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act and to file a CA certificate in support of said compliance.

29
Stage 28Interim Order

Tribunal Order #0901126006422024-09-04-2025

The Tribunal admitted the appeal and accepted an undertaking from the appellant's Deputy Director to reverse Advance Payment Rebate (APR) errors and execute a correction deed for the sub-lease to include the exclusive area.

30
Stage 29Interim Order

Tribunal Order #0901126006422024-12-03-2025

The appellant/promoter submitted that physical possession of the unit has been handed over to the allottee and the conveyance deed has been executed, which the Tribunal accepted and recorded.

31
Stage 30Interim Order

Tribunal Order #0901126006422024-28-03-2024

The Tribunal granted the Appellant a final one-week extension to comply with Section 43(5) of the Act 2016, warning that failure to do so will result in the dismissal of the defective appeal.

32
Stage 31Interim Order

Tribunal Order #0901126006422024-01-03-2024

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act and to file a CA certificate in support of said compliance.

33
Stage 32Final Ruling Order

Tribunal Order #0901126006422024-12-12-2025

The Tribunal dismissed the developer's appeal and ruled that the promoter must pay delay interest to allottees, execute supplementary deeds to correct omitted plot/exclusive areas, refund mandatory club fees, and face potential penalties for fraudulent practices and statutory violations.

34
Stage 33Interim Order

Tribunal Order #0901126006422024-14-10-2025

The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000/- to be paid to the respondent, noting previous orders regarding non-adjournment and prior penalties.

35
Stage 34Interim Order

Tribunal Order #0901126006422024-30-01-2025

The Appellant (AR Landcraft LLP) has undertaken to hand over letters of offer of possession and demand drafts to the respondent, with a commitment to provide physical possession of the habitable units on or before February 28, 2025.

36
Stage 35Final Ruling Order

Tribunal Order #0901126006422024-02-12-2024

The appeal filed by AR Landcraft LLP was dismissed for non-prosecution due to the appellant's failure to appear or argue the case, with a directive for the RERA Authority to execute the impugned order.

37
Stage 36Interim Order

Tribunal Order #0901126006422024-25-10-2024

The Tribunal adjourned the matter to 02.12.2024 due to the appellant's failure to file a rejoinder, imposing a cost of Rs. 5,000/- to be paid by the appellant to the respondent.

38
Stage 37Interim Order

Tribunal Order #0901126006422024-15-04-2024

The Tribunal converted the defective appeal into a regular appeal after verifying that the appellant complied with the mandatory pre-deposit requirements under Section 43(5) of the Act and filed within the limitation period.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the developer's appeal and ruled that the promoter must pay delay interest to allottees, execute supplementary deeds to correct omitted plot/exclusive areas, refund mandatory club fees, and face potential penalties for fraudulent practices and statutory violations. The appeal filed by AR Landcraft LLP was dismissed for non-prosecution due to the appellant's failure to appear or argue the case, with a directive for the RERA Authority to execute the impugned order. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1 percent.

Disposal Winner: RespondentInterest Rate: MCLR + 1 percentStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the developer's appeal and ruled that the promoter must pay delay interest to allottees, execute supplementary deeds to correct omitted plot/exclusive areas, refund mandatory club fees, and face potential penalties for fraudulent practices and statutory violations. The appeal filed by AR Landcraft LLP was dismissed for non-prosecution due to the appellant's failure to appear or argue the case, with a directive for the RERA Authority to execute the impugned order.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1 percent

Interest Period

from 02.03.2021 till the date of handing over physical possession of the unit, except for the Covid pandemic period w.e.f. 23.03.2020 to 25.09.2020

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 12Section 11(4)(d)Section 19(6)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Syed Mohammad Abid
  • Saurabh Gauba

Respondent Advocate(s)

  • Dron Mishra

Official RERA Tribunal Orders (10)

INTERIM_ORDEROrder ID: 0901126006422024-09-04-2025

The Tribunal admitted the appeal and accepted an undertaking from the appellant's Deputy Director to reverse Advance Payment Rebate (APR) errors and execute a correction deed for the sub-lease to include the exclusive area.

INTERIM_ORDEROrder ID: 0901126006422024-12-03-2025

The appellant/promoter submitted that physical possession of the unit has been handed over to the allottee and the conveyance deed has been executed, which the Tribunal accepted and recorded.

INTERIM_ORDEROrder ID: 0901126006422024-28-03-2024

The Tribunal granted the Appellant a final one-week extension to comply with Section 43(5) of the Act 2016, warning that failure to do so will result in the dismissal of the defective appeal.

INTERIM_ORDEROrder ID: 0901126006422024-01-03-2024

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act and to file a CA certificate in support of said compliance.

FINAL_ORDEROrder ID: 0901126006422024-12-12-2025

The Tribunal dismissed the developer's appeal and ruled that the promoter must pay delay interest to allottees, execute supplementary deeds to correct omitted plot/exclusive areas, refund mandatory club fees, and face potential penalties for fraudulent practices and statutory violations.

INTERIM_ORDEROrder ID: 0901126006422024-14-10-2025

The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000/- to be paid to the respondent, noting previous orders regarding non-adjournment and prior penalties.

INTERIM_ORDEROrder ID: 0901126006422024-30-01-2025

The Appellant (AR Landcraft LLP) has undertaken to hand over letters of offer of possession and demand drafts to the respondent, with a commitment to provide physical possession of the habitable units on or before February 28, 2025.

FINAL_ORDEROrder ID: 0901126006422024-02-12-2024

The appeal filed by AR Landcraft LLP was dismissed for non-prosecution due to the appellant's failure to appear or argue the case, with a directive for the RERA Authority to execute the impugned order.

INTERIM_ORDEROrder ID: 0901126006422024-25-10-2024

The Tribunal adjourned the matter to 02.12.2024 due to the appellant's failure to file a rejoinder, imposing a cost of Rs. 5,000/- to be paid by the appellant to the respondent.

INTERIM_ORDEROrder ID: 0901126006422024-15-04-2024

The Tribunal converted the defective appeal into a regular appeal after verifying that the appellant complied with the mandatory pre-deposit requirements under Section 43(5) of the Act and filed within the limitation period.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ar landcraft llp?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →