Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126004142022 by Nikhil Mishra against Paramount Propbuild Pvt. Ltd. before up_rera.
Further Order
The appellant requested to withdraw the appeal following an amicable settlement between the parties, and the Tribunal permitted the withdrawal, resulting in the dismissal of the appeal.
Further Order
The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 24.01.2023.
Further Order
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the defective appeal for hearing on 15.12.2022.
Further Order
On the joint request of the counsels for both parties, the Tribunal adjourned the appeal and scheduled it for further orders on 18.11.2022.
Further Order
The Tribunal directed the respondent to file a list of dates, events, and relied-upon judgments before the next hearing date, which is scheduled for 19.10.2022.
Hearing
The Tribunal directed the parties to exchange a list of dates, events, and relied-upon judgments before the next hearing scheduled for 14.09.2022.
Hearing
The Tribunal directed the appellant to file a replication or rejoinder affidavit following the respondent's submission of their reply and scheduled the case for hearing on 17.08.2022.
Hearing
The Tribunal condoned the 99-day delay in filing the appeal, citing COVID-19 pandemic relaxations, and directed the respondent to file a reply to the grounds of appeal.
Hearing
The Tribunal issued a notice to the respondent and directed the appellant to serve the appeal via speed post and file an affidavit of service before the next hearing on 27.04.2022.
Defect Removal
The Tribunal directed the appellant's counsel to rectify existing procedural defects within three days and scheduled the matter for a subsequent hearing on 16.03.2021.
Tribunal Order #0901126004142022-27-04-2022
The Tribunal condoned the 99-day delay in filing the appeal, citing COVID-19 pandemic relaxations, and directed the respondent to file a reply to the grounds of appeal.
Tribunal Disposal & Final Award Ruling
Dismissed as withdrawn Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed as withdrawn
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Bal Kishor Verma
- Amit Yadav
Respondent Advocate(s)
- Saurabh Misra
Official RERA Tribunal Orders (1)
The Tribunal condoned the 99-day delay in filing the appeal, citing COVID-19 pandemic relaxations, and directed the respondent to file a reply to the grounds of appeal.